| 1 | Upgradation of road from Kalnadu to Erumakadai road Km.1/2-2/70 H/o.Sitheri |
| 2 | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201 in all etc complete |
| 3 | Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A |
| 4 | Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) |
| 5 | Km.1/2-2/00 |
| 6 | Km.2/0-2/70 |
| 7 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in Subbase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 8 | Km.1/20-2/70 |
| 9 | Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. |
| 10 | Km.1/20-2/70 |
| 11 | Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete |
| 12 | Km.1/20-2/70 |
| 13 | Providing and laying Bituminious concrete which shall consists of construction of a single course binder /wearing corse on a previosly prepared Bituminous base to the requirements of the specification using 60/70 grade bitumen as per MorRTH specificaton CI.508. |
| 14 | Km.1/20-2/70 |
| 15 | Providing and laying including cost and conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by power roller to achieve the required Proctor density at 100% compaction at Optimum moisture content and hire fuel charges for powerroller, watersprinkler and all other incidental charges such as traffic barricading and providing dangerlights etc. comp for side berm |
| 16 | Km.1/2-2/00 |
| 17 | Km.2/0-2/70 |
| 18 | Road Marking by providing and laying of hot applied Thermoplastic Compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5mm exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and free from streaks and holes. |
| 19 | Km.1/20-2/70 |
| 20 | Supplying and fixing Kilometer Metre stones including painting and lettering as directed by the departmental officers etc., complete |
| 21 | Supplying and fixing Hecta Metre stones including painting and lettering as directed by the departmental officers etc., complete |
| 22 | Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete |
| 23 | Construction of Culvert at Ch.1380 m |
| 24 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B etc |
| 25 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Levelling course |
| 26 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Foundation |
| 27 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Superstructure |
| 28 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Superstructure |
| 29 | Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for Deckslab |
| 30 | Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and superstructure for Abutment /pier using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers etc. |
| 31 | Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and superstructure for Abutment /pier using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers etc. |
| 32 | Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length,bending to shape and tying in position and forming grills for all R.C.C works |
| 33 | Providing and fixing 20mm Bitumen felt for expansion joint Between Dirtwall &Deck slab |
| 34 | Provision for Weepholes |
| 35 | Collection and supply of Well gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for filling etc.complete, |
| 36 | Construction of Culvert at Ch.2110 m |
| 37 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B etc |
| 38 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Levelling course |
| 39 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Foundation |
| 40 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Superstructure |
| 41 | Cement concrete 1:2:4 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Superstructure |
| 42 | Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for Deckslab |
| 43 | Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and superstructure for Abutment /pier using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers etc. |
| 44 | Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and superstructure for Abutment /pier using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers etc. |
| 45 | Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length,bending to shape and tying in position and forming grills for all R.C.C works |
| 46 | Providing and fixing 20mm Bitumen felt for expansion joint Between Dirtwall &Deck slab |
| 47 | Provision for Weepholes |
| 48 | Collection and supply of Well gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for filling etc.complete, |
| 49 | Construction of Hardbed @ Ch.1910-1925 m |
| 50 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B etc |
| 51 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Levelling course |
| 52 | Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc |
| 53 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for Foundation |
| 54 | Cement conerete 1:1.5:3 using 20mm H.B.G.Metal including watering wherever necessary sand laid in layers compacting etc. complete complying with standard specification and directed by the departmental officers. |
| 55 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column \\"BB\\" for all works in this package}(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) Please Enable Macros to View BoQ information |