| 1 | Repairs to E.Velayuthapuram Road to Thuvaranthai Road. KM 0/0-2/2 |
| 2 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp. |
| 3 | Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 50mm using 45mm IRC size HBG metal |
| 4 | KM 0/0-1/0 |
| 5 | KM 1/0-2/0 |
| 6 | KM 2/0-2/2 |
| 7 | Providing and laying Tack coat over BT surface using 3Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat |
| 8 | Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com. |
| 9 | KM 0/0-1/0 |
| 10 | KM 1/0-2/0 |
| 11 | KM 2/0-2/2 |
| 12 | Repairs to Thathaneri to E.Velayuthapuram Road. KM 0/0-2/6 (R-79) |
| 13 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp. |
| 14 | Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 50mm using 45mm IRC size HBG metal |
| 15 | KM 0/0-1/0 |
| 16 | KM 1/0-2/0 |
| 17 | KM 2/0-2/6 |
| 18 | Providing and laying Tack coat over BT surface using 3Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat |
| 19 | Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com. |
| 20 | KM 0/0-1/0 |
| 21 | KM 1/0-2/0 |
| 22 | KM 2/0-2/6 |
| 23 | Repairs to Reddiapatti to Matharajapuram Road. KM 0/0-1/3 |
| 24 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp. |
| 25 | Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 50mm using 45mm IRC size HBG metal |
| 26 | KM 0/0-1/0 |
| 27 | KM 1/0-1/3 |
| 28 | Providing and laying Tack coat over BT surface using 3Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat |
| 29 | Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com. |
| 30 | KM 0/0-1/0 |
| 31 | KM 1/0-1/3 |
| 32 | Renewal BT of Km 10 /4 of E.Velayuthapuram Road to Matharasipuram Road KM 0/0-0/600 |
| 33 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp. |
| 34 | Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 50mm using 45mm IRC size HBG metal |
| 35 | Providing and laying Tack coat over BT surface using 3Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat |
| 36 | BITUMINOUS CONCRETE 25/30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete asper specification using CMP as per clause 507 of MORTH Rev-5 |
| 37 | Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS |
| 38 | Renewal BT of Sippikulam Beach road km 0/0-0/365. |
| 39 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp. |
| 40 | Advance patch work for making up the undulation in the existing B.T surface to an average thickness of of 50mm using 45mm IRC size HBG metal |
| 41 | Providing and laying Tack coat over BT surface using 3Kg of bitumen 60/70 for 10sqm area including cost and conveyance of bituminous binder including labour charges for preparing the surface and applying the required quantity of bitumen as tack coat |
| 42 | BITUMINOUS CONCRETE 25/30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete asper specification using CMP as per clause 507 of MORTH Rev-5 |
| 43 | Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS |
| 44 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \\"BB\\" for all works in this package} Please Enable Macros to View BoQ information |