| 1 | Carrying/shifiting of Pantoon from Anchoring/Stayed place/river to the bridge site of including required for proper completion of the work as per direction of E/I. (Kumbh Mela item 1-A) |
| 2 | Same as above but local shifting of Pantoon within 500m with help of crain/labour. (Kumbh Mela item 1-B) |
| 3 | Dragging the Pantoon from dry bed to the river water and making pair and anchoring them in the down stream side of Pantoon Bridge (Kumbh Mela item 2) |
| 4 | Carrying of pantoon pair from the place of anchoring (down streem side of bridge ) to the alignment of the bridge inwater and fixing the same with other pantoon pair and refixing the same in the bridge alignment required for proper completion of the work as per direction of E/I. (Kumbh Mela item 3) |
| 5 | Addition Hualage of Pantoon in River (per Km) required for proper completion of the work as per direction of E/I. (Kumbh Mela item 3-A) |
| 6 | During carrying the Pantoon pair from place of anchoring (D/S side of bridge) in water and then to crossthe dry bed /shallow water on the way upto the alignment, disconnecting the Pantoon pair and rolling the pantoon and fixing in the alignment after laying at site as per direction of E/I. (Kumbh Mela item 4) |
| 7 | Sinking the pantoons to obtain the proper gradient as laid in the dry bed/ shallow water in the alignment of pantoon bridge site as per direction of E/I. (Kumbh Mela item 5) |
| 8 | Laing of wooden anchors in the river on the Up stream/Down stream side of the pantoon bridge site including their weaving packing the sand filled bags (av 90 bags) properly before laying and fixing to pantoon with coir rope/sisall rope excluding cost its at site as per direction of E/I. (Kumbh Mela item 6) |
| 9 | Cartage and laying of Chaquered Plate including loading unloading cost of carriage from store and laying at site as per direction of E/I. (Kumbh Mela item 7) |
| 10 | Carriage and laying of sal sleeper with decking on the bridge including loading unloading cost of carriage from store and laying at site as per direction of E/I. (Kumbh Mela item 9-i) |
| 11 | Same as above but sal edging as per direction of E/I. (Kumbh Mela item 9-ii) |
| 12 | Carriage and laying of spliced R. S. Joist (5.00 M long) with decking on the bridge including loading unloading cost of carriage from store and laying at site as per direction of E/I (Kumbh Mela item 11). |
| 13 | Relaying of Chaquered Plate including loading unloading cost of carriage from store and laying at site as per direction of E/I. (Kumbh Mela item 13) |
| 14 | Supply and laying of empty cement bags filled with local earth sand and carriage up to site of work including stiching loading and unloading stacking and also including supply of all material labour T&P required for proper completion of the work etc.as per direction of Engineer In charge. |
| 15 | Supply & Providing of eucalyptus, ballies 10 to 15 cm dia including all materials labours and T&P etc. required for proper completion of work as per direction of E/I. |
| 16 | Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of tables 300.1 and 300.2 as per technical specification clause 301.5 |
| 17 | Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 |
| 18 | Supply and Fixing of M. S. Nut-Bolts with washer with required shape and size for fixing of Girder with pantoon and edging sleeper etc. including all material, labour T&P etc.required for proper completion of the work as per direction of E/I. |
| 19 | Dismentling of chequered plate road and lifting of chequered plate laying in the alignment of road for loading into truck/tractor trolly including cost of cartage, loading, unloading, T&P and duly stacked in store at site as per direction of E/I. (Kumbh Mela item 3). |
| 20 | Dismentling and carrying sal edging fixed over the sleeper including loading, unloading, cartage and duly stacked in store at site as per direction of E/I. (Kumbh Mela item 7). |
| 21 | Dismentling and carrying sal sleeper in deck over the bridge including cleaning the Kapsa soil and Kansa loading, unloading, cartage and duly stacked in store at site as per direction of E/I. (Kumbh Mela item 8). |
| 22 | Dismentling and carrying the spliced R. S. Joist between two pantoon after the dismantling of pantoon pair including loading, unloading, cartage and duly stacked in store at site as per direction of E/I. (Kumbh Mela item 9). |
| 23 | Cartage of pantoon by truck/Trailer etc. after Dismentling from bridge Bhundi ghat site to safe site disconnecting the pantoons laying in dry bed /Shallow water, rolling and haulage upto river bank, loading, unloading with the help of crane, labour,T&P at site as per direction of E/I. (Kumbh Mela item 13). |
| 24 | Maintenance of Pantoon Bridge Length of bridge including pile or either side (Period Start to end of Mela Day-Night=1 Month) as per direction of E/I. (Kumbh Mela item 17) ForAve 6 Month |
| 25 | Maintenance of Chaquered plate Road Length of bridge including pile or either side (Period Start to end of Mela Day-Night=1 Month) as per direction of E/I. (Kumbh Mela item 18-vi) |
| 26 | Hiring of Dozer D-50 A15 for earth work /pushing of pantoons in water including Driver & required fuel/iol required for proper completion of the work as per direction of E/I. (1423*1.85=2632.55) |
| 27 | Hiring of Hydraulic Excavator for earth work /pushing of pantoons in water including Driver & required fuel/iol required for proper completion of the work as per direction of E/I. |
| 28 | Hiring of Crane for Loading of pantoons in water including Driver & required fuel/iol required for proper completion of the work as per direction of E/I. |
| 29 | Hiring of Tralla for Shifting of pantoons in water including Driver & required fuel/iol required for proper completion of the work as per direction of E/I. |
| 30 | Hiring of Semi Skilled Mazdoors for lifting/pushing of pantoons in water including required for proper completion of the work as per direction of E/I. |
| 31 | Repair/Maintinance/Painting/Writing/Gas welding of likage pantoons Etc. of Sign Board as per direction of E/I. Please Enable Macros to View BoQ information |