Tender For General-Rectification Work 2024-25-Kip(Lb) - Rectification Work Of Melila East Distributory At Ch. Between 352M To 4000M-General Civil Work, Melila-Kerala
TDR : 54502733
Tender Notice
BOQ
6 Days Left
Melila
Kerala
Tender For General-Rectification Work 2024-25-Kip(Lb) - Rectification Work Of Melila East Distributory At Ch. Between 352M To 4000M-General Civil Work
Name of Work:- GENERAL-Rectification work 2024-25-KIP(LB) - Rectification work of Melila east distributory at Ch. between 352m to 4000m-General Civil Work
Sl. No.
Item Description
1
Rectification Work
2
2.32:Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared.
3
2.31:Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared
4
2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
5
2.25:Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m.
6
15.56:Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead.
7
15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 leaner mix ( including equivalent design mix)
8
4.1.8:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 nominal size)
9
5.9.1:Centering and shuttering including strutting, etc. and removal of form for:Foundations, footings, bases of columns, etc for mass concrete
10
4.1.5:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
11
4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size)
12
50.13.1:9 mm cement plastering of mix : 1:3 (1 cement : 3 fine sand ) including all cost of materials, labour charges etc complete
13
OD37402/2024-2025:Engaging man for clearing the obstructions in the pipe syphon and other canal portions as per the direction of the officers in charge Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.