| 1 | Appendix A : Road Work |
| 2 | OD294883/2025-2026:Earth work excavation in all classes of soil including removal of garbage, old plastic bags and other debris from the chalked culvert and from the berms of road conveyingthe deposit of soil and garbage anywhere with in 5km from the site including all labour charge, hire charge of lorry, loading and unloading etc. complete |
| 3 | 2.3.2.A:Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness <br> In area of light jungle - By Mechanical Means<br> |
| 4 | 3.6:Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m |
| 5 | 12.8.A.1:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. <br> PCC Grade M15 <br> |
| 6 | OD295200/2025-2026:Dismantling of flexible pavement and sectioning the dismantled materials and rerolling |
| 7 | 4.1.B.1:Construction of granular sub-base by providing graded material, spreading in uniform layers with a motor grader on a prepared surface, mixing by mix in-place method with rotavator at OMC, and compacting with a vibratory roller to achieve the desired density, complete as per clause 401. Grading-V - For sub-base cum drainage layer - Mix in Place Method |
| 8 | 4.12:Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. |
| 9 | 5.1.a:Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means. |
| 10 | 5.2.a:Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. |
| 11 | OD294975/2025-2026:Providing, laying and rolling of close-graded premix surfacing material of 40 mm thickness composed of 11.2 mm to 0.09 mm (Type-A) aggregates using viscosity grade bitumen ( VG -30) to the required line, grade, and level to serve as wearing course on a previously prepared base, including mixing in a suitable HMP of appropriate capacity not less than 75 tonnes/hour,laying and rolling with a Smooth wheeled roller 8-10 tonne capacity, and finishing to the required level and grade. |
| 12 | 12.4:Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. |
| 13 | 12.8.1.C:Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications <br> RCC Grade M20 - Using Concrete Mixer - (Without formwork) <br> |
| 14 | 3.16:Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2. Please Enable Macros to View BoQ information |