| 2 | 15.9.2:Demolishing stone rubble masonry manually / by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer -in- Charges:In cement mortar |
| 3 | 2.6.1:Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.All kinds of soil |
| 4 | 2.26.1:Extra for every additional lift 1.5 m or part there of in excavation / banking excavated or stacked materials.All kinds of soil |
| 5 | 15.2.2:Demolishing cement concrete manually / by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in-Charge.Nominal concrete 1:4:8 or leaner mix ( including equivalent design mix) |
| 6 | 2.16.2:Close timbering in trenches including strutting, shoring and packing cavities (wherever required) complete (Measurements to be taken of the face area timbered).Depth exceeding 1.5 m but not exceeding 3 m |
| 7 | 50.2.3.1:Pumping or Bailing out water and removing slush etc by using pump set including cost of labour, oil hire charges of pumpset, etc complete |
| 8 | 4.3.1:Centering and shuttering including strutting, propping etc. and removal of form work for:Foundations, footings, bases for columns |
| 9 | 4.1.4:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (1 Cement : 2 coarse sand (zone-III) derived from natural sources : 4 gradedstone aggregate 40 mm nominal size derived from natural sources) |
| 10 | 4.1.3:Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:2:4 (cement : 2 coarse sand (zone-III)derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 11 | 10.25.2:Item Shifted to Sub head 14 as item 14.73Item Shifted to head 14 as item 14.74Steel work welded in built up sections/framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works |
| 12 | 5.22.6:Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more |
| 13 | OD24442/2025-2026:null Providing and laying in position ready mixed M-25 grade concrete for reinforced cement concrete work, using cement content as per approved design mix, manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work including pumping of R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering finishing and reinforcement including cost of admixtures in recommended proportions as per IS: 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer - in -charge. All work up to plinth level |
| 14 | 13.1.2:12 mm cement plaster of mix:1:6 (1 cement : 6 fine sand). |
| 15 | 13.7.2:12 mm cement plaster finished with a floating coat of neat cement of mix:1:4 ( 1 cement : 4 fine sand) |
| 16 | 22.5:Providing and laying water proofing treatment in sunken portion of WCs, bathroom etc., by applying cement slurry mixed with water proofing cement compound consisting of applying : a) First layer of slurry of cement @ 0.488 kg/sqm mixed with water proofing cement compound @ 0.253 kg/sqm. This layer will be allowed to air cure for 4 hours. b) Second layer of slurry of cement @ 0.242 kg /sqm mixed with water proofing cement compound @ 0.126 kg/ sqm. This layer will be allowed to air cure for 4 hours followed with water curing for 48 hours. The rate includes preparation of surface, treatment and sealing of all joints, corners, junctions of pipes and masonry with polymer mixed slurry. |
| 17 | 50.18.9.10.1:Providing and fixing PVC pipes includings jointing of pipes with one step pvc solvent cement, trenching , refilling & testing of joints complete as per direction of Engineer in Charge. 150 mm dia 6 Kgf/cm2 |
| 18 | OD17039/2025-2026:Providing and fixing PVC moulded fittings/ accessories for Rigid PVC pipes, including jointing with PVC solvent cement- 150 mm dia Bend |
| 19 | OD17040/2025-2026:Repair of sewer manhole of size 60 x60 cm depth upto 120 cm using with brick work in cement mortar 1:6 of 30 cm wall including necessary earth work, foundation with cement concrete 1:4:8 using 40 mm hard granite broken stone, channels forming with C.C plastered with cement mortar 1:5, 18 mm thick and 12mm floating coat etc. complete as per the direction of Engineer in charge. |
| 20 | OD14599/2025-2026:Construction of slit pit up to 50 cm depth inside dimension and out side dimension 45x 45 cm with PCC 1:4:8 using 10 cm thick brick work and providing 1 No CI Grating 225x225 mm and necessary earth work excavation etc complete |
| 21 | OD17111/2025-2026:(Refered 19.18.3)Supplying and fixing C.I cover with frame for manhole of size 600X600 mm ( heavy duty) the weight of the cover to be not less than 100 kg |
| 22 | OD26472/2025-2026:Construction of sewer manhole of size 120 x120 cm depth upto 80cm using with R.C.C.work of 20cm wall including necessary earth work, foundation with cement concrete 1:4:8 using 40mm hard granite broken stone, channels forming with c c ,plastered with cement mortar 1:5, 18mm thick and 12mm floating coat etc complete as per the direction of Engineer in charge |
| 23 | OD14601/2025-2026:Labour engaged for cleaning the premises and removing the waste materials and stacking in a convening places |
| 24 | OD17155/2025-2026:Disposal of building rubbish/ malba/ similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved,(Derived from 15.56) Please Enable Macros to View BoQ information |