| 1 | 01.Repairs to PUMS Toilets at Voimedu West in Voimedu Panchayat.Plastering with Cement Mortar 1:5 (One cement and Five M.Sand), 12mm thick in all floors including curing etc. complete |
| 2 | White washing two coats using shell lime including cost and conveyance of all materials to site and all labour charges etc complete for 100 Sq.m |
| 3 | Painting the plastered wall surfaces with two coats oil bound distemper (inside the building) of approved quality and colour over one coat of wall primer including clearing surface in all floors etc complete with standard specification |
| 4 | Painting the newly plastered wall surface with two coats of colour emulsion outside the building over one coat of cement primer including clearing the surface in all floors etc., complete as per standard specification. |
| 5 | Painting two coats with ready mix paint of approved colour and trade for doors & windows including cost and conveyance of all materials and all other labour charges etc., complete. |
| 6 | Provision for Door Repairs |
| 7 | Provision for Sanitary arrangements |
| 8 | Provision for Water Supply arrangements |
| 9 | Provision for Septic tank Cleaning charges |
| 10 | Provision for Name Board and Photo charges |
| 11 | 02.Repairs to PUMS at Voimedu west in Voimedu Panchayat. Dismantling the top of roof with one course of pressed tiles etc., complete. |
| 12 | Finishing the top of roof with one course of machine pressed tiles of size 230mm x 230mm x 20mm of approved quality set in Cement Mortar 1:3 (One Cement and Three Crushed stone M.Sand) 12mm thick including all labour charges etc., complete. |
| 13 | Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. |
| 14 | Painting the plastered wall surfaces with two coats oil bound distemper (inside the building) of approved quality and colour over one coat of wall primer including clearing surface in all floors etc complete with standard specification |
| 15 | Painting the newly plastered wall surface with two coats of colour emulsion outside the building over one coat of cement primer including clearing the surface in all floors etc., complete as per standard specification. |
| 16 | Painting two coats with ready mix paint of approved colour and trade for doors & windows including cost and conveyance of all materials and all other labour charges etc., complete. |
| 17 | Painting two coats with Approved Block Oxide for Old Black Board including including cost and all labour charges etc complete |
| 18 | Provision for Door Repairs |
| 19 | Provision for Bala painitng |
| 20 | Provision for Name Board and Photo charges etc |
| 21 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \\"BB\\" for all works in this package} 18% for other than Earth Quantity Please Enable Macros to View BoQ information |