| 1 | CHAPTER - VIII SUPPLYING OF MATERIALS HIRE CHARGES OF MACHINERIES 8.27Hire charges of moveable type mounted earth excavator having minimum cutter size (1.0 cubic meter) & loader size (2.0 meter length x 0.75m width) for cutting & removal of any kind of soil, spoli etc. including cost of fuel, lubricants & manpower etc. in Water Supply Works. [ This item will be operated on prior permission from the concerned SE/Dy. Chief Engineer] For minimum engagement of 8 hrs. In a day |
| 2 | Water Bound Macadam Sub Base by consolidating Jhama metal / Laterite chelly or stone metal / shingles of specific size in hard crust to requisite thickness (measured after compaction) in layers including screening of metals etc. as necessary, hand packing, sweeping, watering and rolling in stages with power roller to proper line, grade and camber, lighting, guarding & barricading and making necessary earthen bundh of one metre width on each side where necessary to protect edges and preparing the bed by necessary cutting or filling and rolling all complete including the cost of all materials and hire and labour charges of all men and machineries and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (i) For Construction of Sub Base by consolidating Jhama metal / Laterite (63 mm to 45 mm) (Moorum replaced with course sand) (For compacted thickness 75mm) |
| 3 | Providing and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming to IS: 8887-1978 on the prepared surface cleaned with Hydraulic broom, moistening the surface including cost and carriage of emulsion, hire charges of machinery and labour, cost of fuel and lubricants all complete as per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (ii) On Granular surfaces treated with primer. (Using Bitumen emulsion at the rate of 0.25 to 0.30 kg per sqm.) |
| 4 | Transportation and laying 40 mm thick hot asphaltum mixture from kmc plant to the work site including rolling but excluding the cost of tack coat (covered area- 1250 square meter per 100 mt hot-mixture) a) without paver finisher i) Day Time |
| 5 | Taking out stone slab of kerb & channel of road side drain and stacking as directed. b) flat channel stone. |
| 6 | Taking out stone slab of kerb & channel of road side drain and stacking as directed. a) vertical kerb stone. |
| 7 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc B. CONCRETE WORKS 1. Cement concrete with graded jhama khoa (30 mm size) excluding shuttering In ground floor and foundation (a) 1:3:6 proportion |
| 8 | Resetting of Stone Slabs of kerb & channel of road side drain to correct line and level including cement pointing (1:2). b) flat channel stone. |
| 9 | Resetting of Stone Slabs of kerb & channel of road side drain to correct line and level including cement pointing (1:2). a) Vertical Kerb |
| 10 | Supplying and laying factory made vertical kerb stone of cement concrete M-20 (1:1.5:3) machanicaly vibrated size 500mm X 350mm X 150mm tapered at top, making joints with cement mortar (1:4) incldg cost of all materials and labours but excluding the cost of under bed (for road-diveder / footpath) ( Ref :Rate based on PWD Current SOR [PWD(B) 2017, p-26 (it -10(i)), consumption chart pg-B-60, sl-3 and Annex-II , Format-A & 3rd Corr. & adda. dtd-04.06.2018, p-303 , p-191 (i -6)and 3rd Corr. & Adda, page-52, PWD-2018(R & B) p-332 (it -18.05)), Chapter-1, pg-227 I-1.03, pg-230,Table-I , Table III-2 pg-226, ) |
| 11 | Lowering manhole cover and frame with CBW (1:4), 250 mm thick up to 100mm DEPTH with 20mm thick sand and cement plaster including finishing with neat cement after cutting the asphaltum pavement and taking out and re-fixing the existing manhole cover and frame with cement concrete (1:1.5:3) with stone chips all round the frame surface including removal of surplus spoils. |
| 12 | (23)Supplying, fitting and fixing in positing reinforced cement polymer concrete manhole /gully pit cover with matching frame as per I.S. 12592 (m.D.) ii) 25 mT load bearing capacity round manhole cover provided with two lifter hooks fitted with matching frame of size Cover : 680 mm. X 90 mm. Frame : 800 mm. X 165 mm. Opening : 500 mm. Weight : 196 Kg. (approx.) |
| 13 | (23)Supplying, fitting and fixing in positing reinforced cement polymer concrete manhole /gully pit cover with matching frame as per I.S. 12592 (m.D.)xii) 15 mT load bearing capacity gully pit cover with frame and hinge arrangement for opening of size Cover : 565 mm. X 410 mm. X 90 mm. Frame : 715 mm. X 565 mm. X 185 mm. Weight : 140 Kg. (approx.) |
| 14 | Sub Total |
| 15 | GST 18% |
| 16 | CESS 1% Please Enable Macros to View BoQ information |