|
| 1 | Dewatering of Nallah from site including DG Set charges,diesel charges,complete in all respect. |
| 2 | Recovery of old steel, recovered from site during demolishing work, complete in all respect. |
| 3 | Recovery of old bricks, recovered from site during demolishing work, complete in all respect. |
| 4 | Recovery of brick bats,recovered from site during demolishing work,complete in all respect. |
| 5 | [10.100.2]Cement Concrete 1:8:16 Flooring 2. Cement Concrete 1:8:16 with stone aggregate 40 mm size in foundation and plinth. [Through Rate] |
| 6 | [11.5.3]12 mm cement plaster of mix : 3. 1:4 (1 cement: 4 fine sand) [Through Rate] |
| 7 | [13.29.2]Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. 2. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works [Through Rate] |
| 8 | [17.4]Scarifying Existing Bituminous Surface to a depth of 50 mm by Mechanical Means Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with in all lifts and lead up to 1000 metres, as per technical clause 202 of MORT&H specifications [Through Rate] |
| 9 | [27.51.4]Filler joint 4. Providing and filling joint sealing compound as per drawings and MoRT&H specifications with coarse sand 6 per cent bitumen by weight - 10 mm depth [Through Rate] |
| 10 | [3.1.1]By Mechanical Transport including loading, unloading and stacking 1. Lime, moorum, building rubbish [5km] |
| 11 | [3.1.3]By Mechanical Transport including loading, unloading and stacking 3. Manure or sludge [5km] |
| 12 | [4.12.1]Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead up to 50 m and lift up to 1.5 m, as directed by Engineer-in-charge. 1. All kinds of soil [Through Rate] |
| 13 | [4.41]Earth work of silt-clearance of channels and drains. Kassi work undressed involving an average horizontal through upto 2 metres and average vertical lift upto 0.5 metre. [Through Rate] |
| 14 | [5.23.2]Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. 2. Nominal concrete 1:2:4 or leaner mix (i/c equivalent design mix) [Through Rate] |
| 15 | [5.25]Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. [Through Rate] |
| 16 | [5.7.4]Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. 4. In cement mortar [Through Rate] |
| 17 | [6.1.1]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 1. 1:1½:3 (1 Cement: 1½ coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 18 | [6.14.1]Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 19 | [6.30.3]Centering and shuttering including strutting, propping etc. and removal of form for 3. Suspended floors, roofs, landings, balconies and access platform [Through Rate] |
| 20 | [6.34.3]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect above plinth level Note:- Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 3. Cold twisted bars [Through Rate] |
| 21 | [7.21.2]Brick work with common burnt clay non-modular bricks of class designation 10.5 in foundation and plinth in: 2. Cement mortar 1:6 (1 cement : 6 coarse sand) [Through Rate] Please Enable Macros to View BoQ information |