Name of Work:- RENOVATION OF UTTARAN PASSAGES & OTHERS AT 3NO LAKE COLONY,61,64 GARCHA RD AND SURROUNDING IN WARD NO-086
Sl. No.
Item Description
1
Box cutting or filling in Road embankment in all sorts of soil including spreading the spoils properly over the flank as necessary or on berm to approximate grade & camber and rolling the sub-grade with power roller to proper camber and grade as per direction and satisfaction of Engineer-in-charge including uprooting and removing plants and jungles when and where necessary. (a) Depth up to 150 mm.
2
BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 2. Labour for laying single brick flat soling including ramming and dressing bed to proper level and filling joints with powdered earth.
3
BUILDING WORKS ( C ) BRICKWORKS, CONCRETE WORKS Etc. A. BRICK WORKS 1. Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. ( 3rd Corrigenda & addenda dated 04.06.2018)
4
35mm thick Cement Concrete Pavement (1:2:4) in floor/footpath etc. with graded stone chips 11.2mm down,properly leveled with 3mm thick screen on top by cement slurry [email protected] cement per Sqm. Rounding off corners, chequering as required including taking necessary protective measure complete in Gr.floor/footpath.
5
Raising manhole cover and frame with CBW (1:4), 250mm thick up to 100mm high with 20mm thick sand and cement plaster including finishing with neat cement after cutting the asphaltum pavement and taking out and re-fixing the existing manhole cover and frame with cement concrete (1:1.5:3) with stone chips all round the frame surface including removal of surplus spoils.
6
Raising cover and frame of Catch Pit with CBW (1:4), 250 mm thick up to 100mm high with 20mm thick sand and cement plaster (1:4) including finishing with neat cement after cutting the asphaltum pavement taking out and re-fixing the existing cover and frame with cement concrete (1:1.5:3) with stone chips all round the frame surface including removal of surplus spoils.
7
BUILDING WORKS. (T)MISCELLANEOUS WORKS: A. SPECIAL WORKS. II. COMPOUND DEVELOPMENT: 8) Taking out stone slabs of flat V-shaped drain of road side and resetting the same to correct line and level with cement mortar (1 : 4) including cement pointing (1 :2). (a) Vertical kerb stone. (Cement- 1.25 Kg/M)
8
BUILDING WORKS. (T)MISCELLANEOUS WORKS: A. SPECIAL WORKS. II. COMPOUND DEVELOPMENT: 8) Taking out stone slabs of flat V-shaped drain of road side and resetting the same to correct line and level with cement mortar (1 : 4) including cement pointing (1 :2). (b) Flat channel stone. (Cement- 1.75 Kg/M)
9
BUILDING WORKS ( C ) Brickworks,Concrete Works etc B. CONCRETE WORKS 1. Cement concrete with graded jhama khoa (30 mm size) excluding shuttering In ground floor and foundation (a) 1:3:6 proportion
10
Sub Total
11
GST 18%
12
CESS 1% Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.