| 1 | Reconductoring LT line |
| 2 | Transporting LT ABC by hired vehicle to a distance up to 5 km and carring up to 2 drum including loading and un loading using crane |
| 3 | Stringing of 1.1 kV Aerial bunched cable of size 3 x 70 + 1 x 16+1x 50 sqmm with bare/insulated Messenger through existing poles |
| 4 | Erection of Anchor clamp / dead end clamp for LT ABC of any size |
| 5 | Erection of suspension clamp for LT ABC of any size |
| 6 | Installing One No. Insulation piercing connector of size Main :16 to 95 ,Tap:1.5 to 16 Sq.mm |
| 7 | Installation of Pre-insulated straight through joints for 16sqmm cable |
| 8 | Installation of Pre-insulated straight through joints for 50sqmm cable |
| 9 | Installation of Pre-insulated straight through joints for 70sqmm cable |
| 10 | Installation of Pre-insulated lugs for 70sqmm |
| 11 | Installation of Pre-insulated lugs for 50sqmm |
| 12 | Installation of Pre-insulated lugs for 16sqmm |
| 13 | Fitting of one No. pole top service connection box of standard size (up to 4 way) using ss strap/B&N of suitable size in to the PSC/A poles at the standard height excluding giving connections |
| 14 | Providing End Caps |
| 15 | Installing One No. 4 way Satellite Connector of size Main :16 to 95, Tap:4 to 35 Sq.mm to the LT AB cable of Standard size |
| 16 | Dismantling (without damage) one km LT additional conductor line, cross arms, insulators and stacking the conductors in rolls. |
| 17 | Dismantling one section fuse |
| 18 | Fitting one No. Section fuse on LT line with dropping cables, crimping sockets, connecting with bolt&nut etc. |
| 19 | Dismantling (without damage) one ordinary street light/CFL/LED fitting from the pole and stacking. |
| 20 | Wiring and installing one new CFL street light fitting on existing pole and giving connections. |
| 21 | Dismantling and reconnecting Sph service connection from the OH line incl. lowering down the WP portion. |
| 22 | Dismantling and reconnecting 3ph service connection from the OH line incl. lowering down the WP portion. |
| 23 | Reshackling one span LT Sph 2 wire OH line, replacing insulators, tightening stay, cutting tree branches incl. conveyance. |
| 24 | Reshackling one span LT 3ph 4 wire OH line, replacing insulators, tightening stay, cutting tree branches incl. conveyance. |
| 25 | Installing one pole top service connection box Sph 6way and giving connections. |
| 26 | Dismantling (without damage) one km LT 3ph 4 wire OH line, cross arms, insulators and stacking the conductors in rolls. |
| 27 | Insertion of one HT PSC pole in existing line incl. digging & backfilling pit, fitting cross arm, insulators, binding etc. |
| 28 | Insertion of one HT A type pole in existing line incl. digging & backfilling pit, fitting cross arm, insulators, binding etc. |
| 29 | Fitting and providing one HT Stay for 11kV pole incl. digging & back filling pit. |
| 30 | Providing one Coil Earth using GI earth wire, digging separate pit at standard distance away from the pole/structure & backfilling. |
| 31 | Providing concrete muffing (0.45x0.45x1.5m) inclusive of cost of all material (as per specification). |
| 32 | Straightening one slanted 11kV pole after unbinding the line and rebinding the line after work. |
| 33 | Installation of Insulation piercing connector for main to service line main :16-95 sqmm, Tap 16-95 sqmm Please Enable Macros to View BoQ information |