| 1 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.In cement mortar DSR NO. 15.7.4 |
| 2 | Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 3031 (With Ordinery Earth in Patri work) |
| 3 | 1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) DSR NO 4.1.8 |
| 4 | Brick masonry work in cement mortar (1:4) in substructure complete excepting pointing and plastering, as per drawing and technical specification Clauses 602, 603, 604, 1202 & 1204 |
| 5 | Plastering with cement mortar (1:4), 15/12 mm thick on brick work in as per technical specification Clauses 613.4 & 1204 |
| 6 | Plain/reinforced cement concrete M20 (1:2:4) in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 |
| 7 | Plain/reinforced cement concrete (Grade M20) in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 |
| 8 | Supplying, fitting and placing with MS bar reinforcement (Fe 415) in substructrue complete as per drawings and technical specification Clauses 1002, 1005, 1010 & 1202 including bending for proper and necessary completion of the work and including supply of steel and wastages, bends, hooks and authorised overlapping shall be measurised as per direction of Engineer-in-charge. |
| 9 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density. |
| 10 | Providing and Laying of Interlocking Concrete Block Pavements having thickness 80 mm as per drawings and Technical Specification Clause 1504. Gray Base ISI MARK |
| 11 | Laying of interlocking tiles of 60 to 80 mm thick including levelling and dressing of surface up to required level and slopes filling joints with local sand including cost of labour, T&P etc complete But excluding cost of material as directed by Engineer in charge. |
| 12 | GST Please Enable Macros to View BoQ information |