| 1 | Construction of Subgrade and Earthen Shoulders Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. |
| 2 | Cement Treated Sub base Providing, laying and spreading Material on a prepared sub grade, cement @ 2% by weight to the spread Material manually, mixing in place with rotavator and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base. As per MORD Technical Specification Clause 405 |
| 3 | Cement treated Grade III Providing, laying and spreading Material on a prepared sub base, cement @ 4% by weight to the spread Material manually, mixing in place with rotavator and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base/base. As per MORD Technical Specification Clause 405 |
| 4 | Tack coat Providing and applying tack coat with bitumen (VG-10) using emulsion distributor at the rate of 0.35 kg per sqm on the prepared bituminous/granular base surface cleaned with mechanical broom. |
| 5 | 20mm thick Open-Graded Premix Carpet using Bituminous Providing, laying and rolling of open - graded premix surfacing of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or cut-back or emulsion to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a smooth wheeled roller 8-10 tonne capacity, finished to required level and grades. |
| 6 | Seal Coat - Type C (Machnical Method) Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type C seal coat |
| 7 | Earthwork in excavation for structures as per drawing and technial specification Clause 305.1 including setting our construction of shoring and bracing removal fo stumps and other deleterious material and disposal upto a lead fo 50 m dressing of sides and bottom and backfilling in trenches with excvated suitable material. |
| 8 | P.C.C. M-10 Providing concrete for plain/rainforced concrete in open foundations complete as per drawings and technical specification Clauses 802,803,1202, 1203 |
| 9 | Brick masonary work in (1:3) cement coarse sand mortar in substructure complete excepting pointing and plastering, as per drawing and technical specification |
| 10 | Pointing with cement mortar (1:3) on brickwork/ C.R. Stone masonry as per drawing and technical specification Clause 613.3 and 1204 |
| 11 | Plastering with cement mortar (1:4), 15 mm thick on brickwork/ C.R. Stone masonary in substructure as per technical specification Clasuses 613.4 & 1204 |
| 12 | Providing and laying reinforced cement concrete pipe NP3 culvert on first class bedding of granular material in single row including fixing coller with cement mortar 1:2 but excluding excavation, protection works. Backfilling, concrete and masonry works in head wall parapets Clause 1106.600 mm dia Hume Pipe |
| 13 | Providing and laying reinforced cement concrete pipe NP3 culvert on first class bedding of granular material in single row including fixing coller with cement mortar 1:2 but excluding excavation, protection works. Backfilling, concrete and masonry works in head wall parapets Clause 1106350 mm dia Hume Pipe Please Enable Macros to View BoQ information |