| 1 | Construction of New Open Well at Andikulam at A.Maruthappapuram Village in Naranapuram Panchayat of Alangulam Panchayat Union |
| 2 | Open well Excavation Complying with Relevant Clauses of TNBP Well Sinking and with Lead up to 10m in Hard stiff clay, stiff black cotton soil, hard red earth, shales,murrams gravel, stoney earth and earth mixed with small size boulders and hard gravelly soil etc., complete. |
| 3 | 1st Depth from 0m - 2m |
| 4 | Open well Excavation Complying with Relevant Clauses of TNBP Well Sinking and with Lead up to 10m in soft disintegrated rock, laterite, soft rock or kankar, not requiring blasting (and excluding bailing out of water) etc., complete. |
| 5 | 2th Depth from 2m - 4m |
| 6 | Open well Excavation Complying with Relevant Clauses of TNBP Well Sinking and with Lead up to 10m in Medium Rock and Dense Medium Rock not requiring Blasting (and excluding bailing out of water) etc., complete. |
| 7 | 3th Depth from 4m - 6m |
| 8 | 4th Depth from 6m - 8m |
| 9 | 5th Depth from 8m - 10m |
| 10 | 6th Depth from 10m - 12m |
| 11 | Open well Excavation Complying with Relevant Clauses of TNBP Well Sinking and with Lead up to 10m in Medium Rock and Dense Medium Rock requiring Blasting (and excluding bailing out of water) etc., complete. |
| 12 | 7th Depth from 12m - 14m |
| 13 | 8th Depth from 14m - 16m |
| 14 | 9th Depth from 16m - 16.19m |
| 15 | Centering charges for RCC works including all cost and conveyance all materials to site etc., complete. |
| 16 | For Side wall (-3.300 to 0.000m) (ie., from 3.30m Below GL to 0.0m GL) |
| 17 | For Side wall (0.000m to +1.500m) (Above GL) |
| 18 | Supplying and fabrication of steel including all cost and conveyance and all labour charges for cutting, bending, tieing and placeing in position etc., complete. |
| 19 | RCC 1:1.5:3 mix using 20mm ISS HBG metal including all cost and conveyance and all labour charges etc., complete excluding cost of steel without centering. |
| 20 | 0.00m to 1.50m Below GL (ie., -1.50 to 0.00m) |
| 21 | 1.50m to 4.50m Below GL (ie., -4.50 to -1.50m) |
| 22 | Above GL (+0.000 - +1.500m) |
| 23 | Supplying and filling with excavated earth including cost and conveyance and all labour charges such as watering and ramming etc., complete as per standard specification. |
| 24 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \\"BB\\" for all works in this package} Please Enable Macros to View BoQ information |