| 1 | Name of Work :Strengthening of the Road From Arakottai AD Colony Road |
| 2 | Clearing the Scrub jungle including all labour charges for burrying and burning etc., |
| 3 | Earth work excavation and depositing on bank within initial lead and lift in hard gravelly soil for Cutting side drain etc, complete. as per SS20 A |
| 4 | Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m |
| 5 | Providing and Laying Gravel to 100mm compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction |
| 6 | Km 0/0-1/0 |
| 7 | Km 1/0-1/400 |
| 8 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 9 | Km 0/0-1/400 |
| 10 | Providing and laying Prime Coat over WBM/ WMM surface using 7 Kg of Emulsion Bitumen (SS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5 |
| 11 | Km 0/0-1/400 |
| 12 | Providing and laying Tack Coat over WBM/ WMM surface (treated with primer) using 2.50 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5 |
| 13 | Km 0/0-1/400 |
| 14 | Providing and laying Bituminous Concrete to 25/30/40 mm thick using 0.13 cum of 19.00-9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30 kgs of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP using( Vibratory Roller) |
| 15 | Km 0/0-1/400 |
| 16 | Construction of Retaining wall Ch 500 to 550,Ch 600 to 700 |
| 17 | Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth, earth mixed with small sized boulders and hard gravelly soil as per SS 20B |
| 18 | Collection and supply of River sand and filling in to the basement including cost and conveyance to the site and all labour charges for filling as per standard specifications |
| 19 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks for 10 cum |
| 20 | Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc using mild steel sheets of size 90 x 60 cm and 10 guage stiffened, welded with mild steel angles of size 25mmx25mmx3mm for boarding laid over silver oak (country wood) scantlings of size 10cm x 6.5cm spaced of about 90cm centre to centre and supported by casurina props of 10cm to 13cm dia spaced at 75cm centre to centre complete complying with standard specifications and as directed by departmental officers including conveyance of all materials to site and proper centering etc complete. (BELOW GROUND LEVEL) |
| 21 | Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for bed blocks for 10 cum |
| 22 | Provision for Weep Holes |
| 23 | Provision for 60 cm equilateral (Cautionary Sign Board) |
| 24 | Provision for 60 cm equilateral (Mandatory Sign Board) |
| 25 | Provision for Kilo Metre Stone |
| 26 | Provision for Hecta Metre Stone |
| 27 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column \\"BB\\" for all works in this package}(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) Please Enable Macros to View BoQ information |