| 1 | Making inter connection of proposed pipe line with existing pipe line of DI/CI including excavation dewatering etc. complete in all respect as directed by Engineer-in-charge for following dia. (i) 80-200 mm dia meter proposed pipe line. |
| 2 | P/F House Service Connection from the main/ distribution drinking water pipe line. (incl. dismantling and excavation of trench) GI Pipe and Nipple Make:- Jindal Hissar/ Ravindra, Union/ Elbow in Heavy Duty, Ferrule in Bras Heavy Duty.Note:- Payment will be made as per Actual work done at site. |
| 3 | [10.100.2]Cement Concrete 1:8:16 Flooring 2. Cement Concrete 1:8:16 with stone aggregate 40 mm size in foundation and plinth. [Through Rate] |
| 4 | [11.5.3]12 mm cement plaster of mix : 3. 1:4 (1 cement: 4 fine sand) [Through Rate] |
| 5 | [17.3]Dismantling of flexible pavement by Mechanical Means Bituminous course [Through Rate] |
| 6 | [20.58.2]Providing and fixing Cast Iron Detachable Joints class-15 marked with IS: 8794 for use with asbestos cement pressure pipes complete with 2 Nos. rubber rings marked with IS:5382 and IS:10292 and appropriate number of nut and bolts marked with IS:1363 including carriage, loading, unloading etc. complete in all respects to the satisfaction of the engineer-in-charge. (Excavation will be paid separately) 2. 100mm i/d CID Joint [Through Rate] |
| 7 | [20.58.3]Providing and fixing Cast Iron Detachable Joints class-15 marked with IS: 8794 for use with asbestos cement pressure pipes complete with 2 Nos. rubber rings marked with IS:5382 and IS:10292 and appropriate number of nut and bolts marked with IS:1363 including carriage, loading, unloading etc. complete in all respects to the satisfaction of the engineer-in-charge. (Excavation will be paid separately) 3. 150mm i/d CID Joint [Through Rate] |
| 8 | [20.64.1]Providing, lowering, laying in trenches, aligning, fixing in position and jointing Ductile Iron (DI) ISI marked K-7 grade SandS pipes as per IS:8329-2000 (amended up to date), with internal cement mortar lining for potable water with rubber ring (EPDM/SBR) joints as per IS: 5382-1985 (excluding special accessories) complete including all material, labour, hydraulic testing and commissioning as per Technical Specifications and as per direction of Engineer. Note: E/W to be measured and paid separately. 1. 100 mm i/d [Through Rate] |
| 9 | [20.66.1]Cutting DI pipe and chipping or filling the surface to a uniform finish 1. 100 mm i/d [Through Rate] |
| 10 | [20.66.2]Cutting DI pipe and chipping or filling the surface to a uniform finish 2. 150 mm i/d [Through Rate] |
| 11 | [20.68.1]Providing, lowering, laying in trenches, aligning, fixing in position and jointing at all level/depths Ductile Iron (DI) standard specials plain /flanged/ socketed confirming to IS9523-2000 with rubber ring (EPDM/SBR) joints such as tees, bends, tapers, caps etc. with in trenches in DI pipe line complete including all material, labour, testing and commissioning along with pipe line as per Technical Specifications and as per direction of Engineer. 1. Up to 300mm dia [Through Rate] |
| 12 | [20.69.1]Providing, lowering, laying in trenches, aligning, fixing in position and jointing at all level/depths cast iron (CI) standard specials plain /flanged/ socketed confirming to IS13382 with rubber ring, nut bolts and rubber sheet such as tees, bends, tapers, caps etc. complete including all material, labour, testing and commissioning along with pipe line as per Technical Specifications and as per direction of Engineer. 1. Up to 300mm dia [Through Rate] |
| 13 | [22.162.1.1]Providing and fixing C.I. sluice valves (with cap) complete with bolts, nuts, rubber insertions etc. (the tail pieces if required will be paid separately) : 1.1. 100 mm diameter Class I [Through Rate] |
| 14 | [3.1.5]By Mechanical Transport including loading, unloading and stacking 5. Sand, stone aggregate below 40 mm nominal size [5km] |
| 15 | [4.14.1]Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 1. All kinds of soil. [Through Rate] |
| 16 | [5.23.2]Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. 2. Nominal concrete 1:2:4 or leaner mix (i/c equivalent design mix) [Through Rate] |
| 17 | [6.16]Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor four level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). [Through Rate] |
| 18 | [6.30.3]Centering and shuttering including strutting, propping etc. and removal of form for 3. Suspended floors, roofs, landings, balconies and access platform [Through Rate] |
| 19 | [6.34.3]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect above plinth level Note:- Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 3. Cold twisted bars [Through Rate] |
| 20 | [7.22.1]Brick work with common burnt clay non-modular bricks of class designation 10.5 in superstructure above plinth level up to floor IV level in all shapes and sizes in : 1. Cement mortar 1:4 (1 cement : 4 coarse sand) [Through Rate] Please Enable Macros to View BoQ information |