| 1 | Erection, Testing and Commissioning of Single Phase and Three Phase CCMS Panel for street light zone 1 to 4 under limit of Municipal Corporation Gurugram. |
| 2 | Restoring the road cut, in level with the existing road surface, including preparation of subgrade laying and relaying of soiling and laying and consolidation of wearing coats to water bound macadam specification and laying 20mm thick premix carpet, on top including cost of tack and sealcoat complete in all respects... |
| 3 | Providing trench less cuttting by Hydraulic Drilling Device boring/ Manual OR through some suitable alternate method with insertion of HDPE Pipe including supply, Delivery of HDPE pipe at work site and laying of 50mm internal diameter HDPE pipe inside road for road corssing of cable by Hydraulic Drilling Device without opening of the road top surface, laid at a depth of at least 900mm below the road surface from the feeding point to the feeder pillar box in median (OR) from feeder pillar to respective street light pole including cost of all accessories for road crossing for laying of cables.. |
| 4 | Supply and erection of LT Shackle insulator brown glazed size 115 mm x 100 mm type 1 suitable for 415/240 volt with latest amendment other accessories to fit it at LT PCC poles i.e nut and bolts complete in all respect as per DHBVN approved make. |
| 5 | Supply and erection of MSD strap made out of 50x6 mm ms flat having suitable holes and other accessories to fit it at LT PCC poles i.e nut and bolts complete in all respect. |
| 6 | Erection Testing and commissioning of single phase CCMS panel including all petty material required for installation of ccms panel i.e clamp,nut and bolts,thimble ,wire etc complete in all material required for installation on PCC pole or Pedstal. |
| 7 | Erection Testing and commissioning of Three phase CCMS panel petty material required for installation of ccms panel i.e clamp,nut and bolts,thimble ,wire etc complete in all material required for installation on PCC pole or Pedstal. complete in all material required for installation on PCC pole or Pedstal. |
| 8 | Providing and fixing of 4G/5G Sim Card and recharse fees per month for street lights CCMS panel Compelte in all respect required for proper operation of CCMS panel. 500 Nos x 60 |
| 9 | S/E/T/C of LT IPC connector suitable for 10sqmm armourd cable as per DHBVN specification and approved make in dhbvn complete in all respect. |
| 10 | Defect liablity period for Replacement of burnt/faulty cables of various sizes 10x3core,e and 25X 4 core cable SPMCB, EPMCB,contractor, wiring and other item required for CCMS panel and Installation of material supplied by the M/s Surya Co. as per rate contract term and Condition i.e SPMCB, EPMCB, contractor, wiring etc and other item required for CCMS panel and maintaining the connectivity of CCMS panel with the GMDA/other portal through sim and removing of fault in ccmspanel for 1st and 2nd year free of cost |
| 11 | Defect liablity period for Replacement of burnt/faulty cables of various sizes 10x3core,and 25X 4 core cable SPMCB, EPMCB,contractor, wiring and other item required for CCMS panel and Installation of material supplied by the M/s Surya Co. as per rate contract term and Condition i.e SPMCB, EPMCB, contractor, wiring etc and other item required for CCMS panel and maintaining the connectivity of CCMS panel with the GMDA/other portal through sim and removing of fault in ccmspanel for 3rd year@4% |
| 12 | Defect liablity period for Replacement of burnt/faulty cables of various sizes 10x3 core,and 25X 4 core cable SPMCB, EPMCB,contractor, wiring and other item required for CCMS panel and Installation of material supplied by the M/s Surya Co. as per rate contract term and Condition i.e SPMCB, EPMCB, contractor, wiring etc and other item required for CCMS panel and maintaining the connectivity of CCMS panel with the GMDA/other portal through sim and removing of fault in ccmspanel for 4th year @4% |
| 13 | Defect liablity period for Replacement of burnt/faulty cables of various sizes 10x3 core,and 25X 4 core cable SPMCB, EPMCB,contractor, wiring and other item required for CCMS panel and Installation of material supplied by the M/s Surya Co. as per rate contract term and Condition i.e SPMCB, EPMCB, contractor, wiring etc and other item required for CCMS panel and maintaining the connectivity of CCMS panel with the GMDA/other portal through sim and removing of fault in ccmspanel for 5th year @5% |
| 14 | Credit of old dismantled material 20/50 sqmm ACSR conductor/ Angle/ d stap / shackle insulator available at site complete in all respect |
| 15 | Erection, Testing and Commissioning of Single Phase and Three Phase CCMS Panel for street light zone 1 to 4 under limit of Municipal Corporation Gurugram. Please Enable Macros to View BoQ information |