| 1 | SCHEDULE OF RATES FOR OH LINE INSTALLATION (LT DISTRIBUTION).Erection of Poles.Erection of Single Steel tubular pole of length as given below with/without sole plate & Cap etc. in CC foundation (Proportion and dimension indicated below), having 600x600x150 mm thick CC (4:2:1) base block below sole plate/pole with hard jhama metal including CC (6:3:1) muffing 0.30 mts. dia and 0.30 mts. above ground level including 3 mm thick neat cemented finish and GI earth bolt after making drilled holes etc. on pole & carriage of pole upto 1.6 Km from Store to work(site including filling up the excavated earth pit with shifted soil and ramming properlyUpto 9.0 mtr. Size 0.6x0.6x1.70 mts |
| 2 | SCHEDULE OF RATES FOR EARTHING INSTALLATIONS.Earthing Installation ... with Pipe Electrode.Earthing with 50 mm dia GI pipe 3.64 mm thick x 3.04 Mts. long and 1 x 4 SWG GI (HOT Dip) wire (4 Mts. long), 13 mm dia x 80 mm long GI bolts, double nuts, double washers incl. S & F 15 mm dia GI pipe protection (1 Mts. long) to be filled with bitumen partly under the ground level and partly above ground level driven to an average depth of 3.65 Mts. below the ground level as below:(a)By ISI Medium GI pipe. |
| 3 | Painting of Steel Tubular Pole of lengths and no. of coats of paint, as given below with ready mixed paint/primer of(approved make, and brand incl. preparation of surface by sand paper/emery paper, cleaning etc. FOR receiving fresh coat of paint.Upto 9.0 mtr. long pole.(i)1st coat of aluminium paint over 1 coat of RO priming |
| 4 | Painting of Steel Tubular Pole of lengths and no. of coats of paint, as given below with ready mixed paint/primer of(approved make, and brand incl. preparation of surface by sand paper/emery paper, cleaning etc. FOR receiving fresh coat of paint.Upto 9.0 mtr. long pole.ii2nd coat of aluminium paint over 1st coat |
| 5 | Fixing only Floodlight fittings on top of masonary structure by 3 Nos. 10 mm dia x 87 mm long rag bolts, nuts & double washers complete either 37 mm x 10 mm MS flat support/or by other means as required |
| 6 | S/F of special head type M S loop box (3 mm thick) with connecting bar and other accessories fixed on the top the pole as required and as per direction of Engineer-In-Charge. For 3 phase connection. |
| 7 | Supplying Al.conductor PVC insulated and sheathed unarmoredcable (1.1KVgrade,Gloster/Havells/Polycab). 4sqmm x 2core |
| 8 | Laying through RCC/Hume/GI Pipe.(a)Laying only Cable upto 50 sqmm through existing RCC/Hume/ GI Pipe/open masonary trench FOR single, 2, 3, 3... & 4 core |
| 9 | Laying on Pole with Clamps.Fixing of Cable along the lentgh of O.H. pole incl. S & F MS pole clamps fabricated from 25 mm x 6 mm MS flat incl. painting |
| 10 | Laying on Wall / surface with Saddles / clamps.(a)Laying of cable upto 2 core 25 sqmm on wall/surface incl. S & F MS saddles with earthing attachment in 10 SWG GI (HOT Dip) Wire, making holes etc. as necy. mending good damages and painting |
| 11 | Supplying Al.conductor PVC insulated and sheathed unarmoredcable (1.1KVgrade, Gloster/Havells/Polycab).10sqmm x 4core |
| 12 | Painting Block Letters or Digits within a circle/square as required, with ...Black Japan... paint of(approved make & brand, the size of letters and digits as given below.Size 40 mm and upto 50 mm |
| 13 | Outdoor Lighting Installation, Steel Tubular Pole, M.S. Pipe, G.I. Pipe, Pole CAP etc Supplying of Swaged Steel Tubular pole as per IS 2713, Pt. II, 1980 for following designation and of following dimensions.(Outside dia & thickness are given in Annexture -1)g) 410 SP - 21 ; 8.5 Mtr., 129.00 Kg. |
| 14 | A N N E X U R E - I Basic Rate of Materials: (All Rates of materials from K-1 to K-14 are excluding VAT) 145. Galv. Straining screw 12\\"x5/8\\" dia |
| 15 | Erection of Galv. (HOT Dip) Cross arms/ `D... Iron Clamp7).Supplying & Erection of Galv. `D... iron complete with suitable pole clamp 75mmx88mm porcelain shackle insulator & 15 mm dia Galv. bolts & nuts. incl. painting |
| 16 | S/F arm bracket of 50 mm bore tubular Pipe (M.S.) of 1. 5 m (5') length for fixing on 75/100 mm pole top including S/F 4 mm thick M.S. plate welded with bolts, nuts & clamps, etc. as required with fabrication work |
| 17 | S/F including fabrication, welding, fixing G.I. junction 6 arm projected bkt. with 2 nos. thro' bolts & nuts of 7\\"long and 5/8\\" dia including M.S.pole cap at the top of the junction with set screw etc. as reqd. and as per direction of Engineer-In-Charge for arm 2.1 M long (G.I.. Pipe) (ISI medium). |
| 18 | S/F projected lamp bracket made 50mm dia G.I. Pipe of 1.85 M (6') in length of which 0.9M (3') In projection having .an angle of 105 degree with clamps, bolts, nuts & clamps, etc. as required . |
| 19 | SUPPLY & DELIVERY OF 200 WATT LED STREET LIGHT FITTINGS. |
| 20 | SUPPLY & DELIVERY OF 200 WATT LED FLOOD LIGHT FITTINGS. |
| 21 | SUPPLY & DELIVERY OF 40 WATT LED STREET LIGHT FITTINGS. |
| 22 | SUPPLY & DELIVERY OF 100 WATT LED STREET LIGHT FITTINGS. |
| 23 | Sub Total |
| 24 | GST 18% |
| 25 | CESS 1% Please Enable Macros to View BoQ information |