| 1 | Supplying and erecting mains with 4x16 sq.mm FRLSH copper PVC insulated wire laid in provided conduit/trunking/inside pole/Bus bars or any other places as per specification No WG-MA/BW(1-3-10) |
| 2 | Supplying, installing, testing and commissioning of 30 kWp ON-GRID Solar PV System / Plant consisting Solar PV Poly Crystalline Panel (335 Wp X 90 Nos.) and Solar ON-GRID Inverter of similar capacity (THD<3%) with interconnecting wires / cables up to solar ON GRID inverter, proper base plate, canopy box to house Inverter and necessary accessories i.e. ACDB/ DCDB , MCB etc. wiring up to solar Inverter in casing and capping, display board, sign board, two distinct earthing, lightning arrester, liaisoning charges, remote monitoring system with maintaining card / chip for 5 years including net charges for RMS System, complete up to net meter installation and export to the grid with 5 year ON-SITE warranty and fully comprehensive maintenance contract as per Specification no. ESD-RT-ONG. (4-5-6)[{1228770+(5 x 58720)} x 1.1]= 1674607.00 |
| 3 | Providing & erecting 4 Pole MCCB, 415 V, 100A, rated short-circuit breaking capacity 25 kA (Ics=100% of Icu), adjustable thermal (overload) setting and fixed magnetic setting with provided leads, provision for installation of shunt/UV/trip alarm contact. MCCB with phase barriers on both sides, insulation withstand capacity 800V, no line-load bias in provided enclosure/panel as per specification no. SW-SWR/MCCB (5-5-1) |
| 4 | Supplying and erecting metal work in CRCA sheet including Iron work for supports with fabrication of boxes panel boards etc. including cutting bending drilling welding riveting treated with anti-rust treatment and duly powder coated or painted with one coat of red lead paint and 2 coats of enamel paint complete.(6-1-1) |
| 5 | Supplying and erecting iron work sheet metal work consisting of CRCA sheets various sections of iron plates chequered plates rods bars MS pipes etc. for panel board or any other purpose with bending cutting drilling and welding complete erected at the position with necessary materials duly painted with one coat of red oxide and two coats of enamel paint to match the switchgears authority.(6-1-19) |
| 6 | Supplying and erecting self-locking arrangement with keys in duplicate, made of brass of grade 1 compliance to IS 729-1979 duly erected, flush with surface of panel /cupboard(6-1-20) |
| 7 | Supplying and erecting LT CT multifunction DLMS compliance energy meter of accuracy of class 0.5 3x240V,50 Hz with optical & RS 232 port, backlit LCD, measure & display trivector energy, load survey, TOD, tamper detection & logging, power ON/OFF events, instantaneous parameters of rating 1/5 A with display in absence of power complete with zero adjustment & test certificate from manufacturer erected on provided M.S. box and connected to CTs.(6-3-5) |
| 8 | Supplying and erecting AC three phase LT CT multifunction net meter DLMS compliance of accuracy class 0.5, 3 x 240V, 50Hz, with backlit LCD display, optical port & RS 232 port (measures import kWh, kVAh, export kWh, kVAh, Net kWh, kVAh, V, I, kW, 6 months history of energy, load survey, TOD, tamper detection & logging, power ON/OFF events, instantaneous parameters of rating 1/5A with display in absence of power) with. wiring connections and mounting hardware on provided panels complete with calibration certificate from manufacturer.(6-3-14) |
| 9 | Supplying and erecting LT current transformer with bar primary 50/5 to 1000/5 ratio with 15 VA burden erected in provided CRCA box duly secured with insulating materials connected to the meter with test certificates. (6-5-2) |
| 10 | Supplying and erecting LED type indicating pilot lamp with LED colours red / yellow / green, 230/250V on provided box / panel with necessary material, wiring & connections etc.(6-5-5) |
| 11 | Supplying and erecting LED type indicating pilot lamp with LED colour blue, 230/250 V on provided box / panel with necessary material, wiring & connections etc. (6-5-6) |
| 12 | Supplying, installtion & marking of surge arrestor/ surge protection device at the sub main distribution board after the incoming breaker of type 2 tested for Imax 40 kA for three phase and neutral with compliance to IEC 61643-11 as per specification no. CP-SPD(6-6-6) |
| 13 | Supplying, erecting & terminating FR XLPE insulated, galvanised steel formed wire armoured (strip) cable 1100 V, 4 core 35 sq. mm. aluminium conductor complete erected with glands & lugs, on wall/ trusses/pole or laid in provided trench/ pipe as per specification no. CB-LT/AL (7-1-31) |
| 14 | Supplying and erecting G.I. pipe 'A' class 40 mm dia. erected for enclosing XLPE armoured cable on wall/pole as per specification no. CB-CE(7-6-2) |
| 15 | Providing earthing with galvanized iron earth plate size 60 x 60 x 0.6 cm complete with all materials testing & recording the results as per specification no. EA-EP(9-1-1) |
| 16 | Supplying, installing & testing maintenance free earthing comprising of Electrode of 17.2 mm diameter Low Carbon Steel with 250 micron molecular copper bonded earthing rod of Length 3m along with 25 kg Carbon based environment friendly back fill ground enhancing compound required to fill up the excavated earth with required quantity complete and recording the results Specification no. EA-MOBI(9-1-5) |
| 17 | Supplying and erecting copper strip of high purity required size used for earthing on wall and/or any other purpose with necessary copper clamps fixed on wall painted with bituminous paint with joints required. As per specification no. EA-EP.(9-2-2) |
| 18 | Supplying and erecting Gl strip of high purity required size used for earthing on wall and/or any other purpose with necessary Gl clamps fixed on wall painted with bituminous paint with joints required. As per specification no EA-EP.(9-2-3) |
| 19 | Supplying and erecting conventional spike type air termination suitable to carry lightning stroke made up of heavy gauge 40 mm dia copper pipe of standard length with 5 Nos. copper spikes fixed on copper ball as air terminals duly threaded in copper pipe erected on provided foundation complete. (9-3-1) |
| 20 | Supplying and erecting Carbon Dioxide (CO2) fire extinguisher of 4.5 kg. capacity cartridge type conform to IS 2878/15683 complete erected with necessary clamp made from 50 x 6 mm. M. S. flat with nut & bolts routed in wall complete. (13-15-1) |
| 21 | Making cement concrete foundation in 1 3 6 cement concrete (20 to 25) mm. stone metal duly plastered with necessary curing for complete. (pole muffing or any other purpose).(16-3-7) |
| 22 | MSEDCL Charges [Non CSR] Please Enable Macros to View BoQ information |