| 1 | Scarifying the existing bituminous surface to a depth of 50 mm and disposal of scarified material within all lifts and leads upto 1000 metres. Aa per MoRTH 305.4.3 |
| 2 | Excavation in Soil using Hydraulic Excavator and Tippers with Disposal upto 1000 metres. Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m |
| 3 | Construction of Embankment with Material Deposited from Roadway Cutting Construction of embankment with approved material obtained from right of way with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2. |
| 4 | Construction of Subgrade and Earthen Shoulders Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 |
| 5 | Granular Sub-Base with Graded Material (Table:- 400-1) Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with front end loader at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401 |
| 6 | Wet Mix Macadam (Plant Mix Method) Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. |
| 7 | Prime coat Providing and applying primer coat with SS1 grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means. |
| 8 | Dense Graded Bituminous Macadam Grading 1 Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @ 4 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. |
| 9 | Tack coat Providing and applying tack coat with bitumen (VG-10) using bitumen pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical |
| 10 | Bituminous Concrete Providing and laying bituminous concrete with 100 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509 complete in all respects |
| 11 | Excavation for Structures Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work. |
| 12 | Sand Filling Sand Filling in Foundation Trenches as per Drawing & Technical Specification |
| 13 | PCC 1:3:6 in Foundation Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. |
| 14 | Stone masonary. Stone Masonry Work in Cement Mortar 1:3 in Foundation complete as per Drawing and Technical Specifications. |
| 15 | R.C.C. grade M 20 Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. RCC Grade M20 using batching plant transit mixer & Concrete pump |
| 16 | R.C.C. grade M 25 Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. RCC Grade M25 using batching plant transit mixer & Concrete pump |
| 17 | Wearing coat Providing and laying Cement concrete wearing coat M-30 grade including reinforcement complete as per drawing and Technical Specifications |
| 18 | Reinforcement work(Substructure) Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as per drawing and Technical Specifications |
| 19 | Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical Specifications |
| 20 | Pointing Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical Specifications |
| 21 | Plastering Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical Specifications |
| 22 | Laying Reinforced cement concrete pipe NP4/prestressed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets .600 mm |
| 23 | Filter media Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return wall to the full height compacted to a firm condition complete as per drawing and Technical Specification. |
| 24 | Laying Reinforced cement concrete pipe NP4/prestressed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets . 1000 mm Please Enable Macros to View BoQ information |