| 1 | PART A Sewage Treatment Plant |
| 2 | STP WORK 300 KLD (SEWAGE TREATMENT PLANT) |
| 3 | SUB HEAD: SEWAGE TREATMENT PLANT |
| 4 | Supply, Fabrication, installation, testing and commisioning of Fully automatic sewage treatment plant based on MBR Process with sewage handling capacity of 300 KLD per day. The entire plant will be constructed in MSEP / JINK ALUMINIUM Febricated. The STP shall be designed as per Raw water, with necessary chemical dosing as required by the manufacturer's design. All the equipment, piping, pumps, air blowers and electrical panel etc. (Defect Liability Period will be 05 Years, All Parts and Machinery maintenance, Replacement included in 05 Year DLP) |
| 5 | Domestic Sewage from domestic Ward and Hospital toilets, kitchens etc. from the Commercial complex and shall be discharged into the STP. Design to take consideration of same. (inlets may vary from given below table) |
| 6 | Daily average flow : 300 M3/Day |
| 7 | PH : 6.5 - 8.5 |
| 8 | BOD5 : 250-300 mg/l |
| 9 | S. Solids : 200 - 450 mg/l |
| 10 | COD : 450-650 mg/l |
| 11 | Oil & Grease : 25-50 mg/L |
| 12 | Sewage discharge standard after treatment as per RPCB :- |
| 13 | PH : 7.0 - 8.5 |
| 14 | BOD5 : Less than 05 mg/l |
| 15 | TSS : Less than 10 mg/l |
| 16 | COD : Less than 50 mg/l |
| 17 | Oil & Grease : Less than 10 mg/l |
| 18 | Electro Machanical |
| 19 | 300 KLD Sewage Treatment Plant Based MBR Technologies |
| 20 | Bar Screen :- Providing & fixing of 2 nos. SS-304 wire Bar Screen of size 500mm x 600mm having provision for lifting arrangement etc. complete as required. 2 Nos |
| 21 | EQUALIZED WASTE WATER TRANSFER PUMPS / RAW SEWAGE PUMP : 2 (1W + 1S) Nos. |
| 22 | Providing & fixing fully submersible sewage handling type pump for raw sewage transfer from equalization tank to aeration tank. The pump shall have complete CI construction, TEFC induction motor including pressure gauge, lifting arrangement for the pump. Solid handling shall be 25-40 mm. Make- Kirloskar/ Wilo/ Cromton Greves/ Assurity/Toshio/CNP/Eqv. |
| 23 | Capacity : 16.25 M3/hr @ Discharge Head 10-15 M head (1 Working + 1 Standby), |
| 24 | Air Blower :- Diffusion system shall include the following: 2 (1W + 1S) Nos. |
| 25 | Tri Lobe type rotary air blowers 2 Nos. (1 W + 1 S) Capable of delivering 300 cum/hr (each) of free air at 0.45 kg/cm2 driven through “V” belt or directly coupled through flexible coupling to a TEFC motor of suitable HP Suitable for 415 ± 10% volts, 3 phase, 50 cycles a/c supply for aeration of EQT, SHT and TWT. Make: Everest/Beta/Akash/Airvac/Eqvt. |
| 26 | Air piping :- shall comprise of pipes droppers/ laterals with MS C Class Header complete with all fittings such as tees, crosses, plugs, sockets, elbows, reducers, supports & clamps, puddle flanges etc cutting chases & making good in Plant Room. Make: Tata/Jindal/Supreme/Astral/Prince/Surya Prakash/Eqv. :- 1 Lot |
| 27 | Diffusers :- Fine /coarse aeration bubble diffusers as required. :- 1 Lot |
| 28 | Air dispersion system shall be provided for Equalisation Tank, Sludge holding Tank and Ariation Tanks. (UPVC/CPVC) :- 1 Lot |
| 29 | MBR Membrane with skid MOC - PVDF/SS-304 :- 1 Lot |
| 30 | Make- Deerfos/ Flosys/ Memtrix Technologies/ Willmer/ Eqv. |
| 31 | TUBE MEDIA :- Supply, installation, testing Tube Settler reactor Media Packeg a) TUBE MEDIA - 1 Lot |
| 32 | Make- MM Aqua/ PP Aqua/ Pharmtech/ Vasu Enviro/ Bharat Industries/Eqv. |
| 33 | SLUDGE TRANSFER PUMP / SLUDGE RECIRCULATION PUMP : 2 (1W + 1S) Nos. |
| 34 | Providing and fixing horizontal, centrifugal sludge transfer pump with 7-10mm solid handling. The pumps shall have CI casing, CI Impeller & CS shaft & sleeve with mechanical seal. MSEP common base frame. |
| 35 | Make- Kirloskar/ Wilo/ Cromton Greves/ Assurity/Toshio/CNP/Eqv. |
| 36 | Capacity 16.25 m3/hr @ 8-10 m head |
| 37 | MEMBRANE SUCTION PUMP : 2 (1W + 1S) Nos. |
| 38 | Providing and fixing Horizontal centrifugal pumps for filtration. The pumps shall be made of CI casing, CI Impellar, CS shaft & sleeve, Mechanical Seal are connected to a TEFC induction motor. Motor to be suitable for 250/440 V, 3 Phase, 50 cycles AC power supply. |
| 39 | Make- Kirloskar/ Wilo/ Cromton Greves/ Assurity/Toshio/CNP/Eqv. |
| 40 | Capacity 16.25 M3/Hr.@ 20-25M head |
| 41 | CIP Dosing Tank:- Supplying, installing, testing & commissioning of 1000 Litres capacity HDPE tank with inlet / outlet connection & piping. 1 No. |
| 42 | Make- SYNTAX / eqvt. |
| 43 | CIP DOSING PUMP:- |
| 44 | Capacity 16.25 m3/hr @ 25-30 M Head. |
| 45 | Make- Kirloskar/ Wilo/ Cromton Greves/ Assurity/Toshio/CNP/Eqv. |
| 46 | CEB Dosing TANK :- Supplying, installing, testing & commissioning of 1000 Litres capacity HDPE tank with inlet / outlet connection & piping. :- 2 Nos. |
| 47 | Make- SYNTAX / eqvt. |
| 48 | CEB DOSING PUMP:- 2 Nos. |
| 49 | Capacity 0 TO 100 LPH |
| 50 | Make- Edose/ Aster/ Eqvt. |
| 51 | All Type Valves :- 1 Lot |
| 52 | Make- Astral/Supreme/Marck/Kartar/Eqv. |
| 53 | MS 'C' class : pumps & Blower interconnecting piping. :- 1 Lot |
| 54 | Make- Tata/Jindal/Surya Prakash/Eqvt. |
| 55 | Screw Press/Filter press:- Supply, erection & commissioning screw press / filter press with sludge feed as suitable :- 1 Nos |
| 56 | Make: Pharmtech / Vasu Enviro / Willmer / SkyLab/Eqv. |
| 57 | Pressure Gauge 0 to 7 KG (SS-304) :- 10 Nos |
| 58 | Make:- Hguru / Forbes Marshel / Eqvt. |
| 59 | Lavel Switch / Float Switch :- 6 Nos |
| 60 | Make:- Jigo / Sibaas / Inflo / Flo / Eqvt. |
| 61 | Membrene Back Wash Pump :- 2 (1W+ 1S) Nos |
| 62 | Capacity 35 m3/hr @ 20 M Head. |
| 63 | Make- Kirloskar/ Wilo/ Cromton Greves/ Assurity/Toshio/CNP/Eqv. |
| 64 | Electro magnetic type flow meter :- Providing & fixing on line Electro magnetic type flow meter cum Totaliser for Monitoring the total flow, Flow rate. etc. Including electrical wiring from panel to flow meter. Complete with all type of Plumbing & Electrical connections, accessories, wiring, conduits & supports complete with all respect. :- 2 Nos |
| 65 | Make- Unitech/ UPC/ Eqv. |
| 66 | Flash Mixture With Tank :- 1 No |
| 67 | Make- Kirloskar/ Wilo/ Cromton Greves/ Assurity/Toshio/CNP/Eqv. |
| 68 | Belt Type Oil Skimmer :- 1 Nos |
| 69 | Make- Cutedge/ Eqvt. |
| 70 | Prefabricated MSEP UNIT/TANKS :- 1 SET |
| 71 | Anoxic Tank-1 |
| 72 | Areation Tank-1 |
| 73 | Tube Settler Tank-1 |
| 74 | MBR Tank-1 |
| 75 | MCC PANEL for STP :- 1 Nos |
| 76 | Required MCC PANEL capacity of MCCB for DOL/ Star Delta starter and outgoing feeders for all pumps, motors and operating equipment. Each compartment shall contain Auto/ Manual switch, contactor, relay, single phase preventer, sequential controller for auto operation of working and standby equipment complete in all respects for the following, but not limited to: |
| 77 | Panel shall be designed on the actual HP as per model selection of pumps |
| 78 | starters shall be provided with Automatic level controller As Required |
| 79 | Notes: |
| 80 | All MCCBs / MCBs shall be of 18 / 10 KA breaking capacity and suitable for motor duty application. |
| 81 | All motor starters shall be provided with Automatic level controller |
| 82 | DOL starters shall be used for motors below 10 HP and Star-Delta Starters for other motors . |
| 83 | Provision for dry run protection shall be made in the panel. |
| 84 | MCC for STP as described above |
| 85 | All Control system to Make the STP fully automatic. The operation of the pumps shall be controlled by the level controller. |
| 86 | Supplying & Fixing of Cables , Conector, Cable Trays, to make Electrical Installation Complete. Necessary cable alleys, internal / cabling, wiring, cabling from MCC to various pumps / equipment and interlocking. |
| 87 | Total PART A : Design, Engineering, Supply, Installation, testing & commissioning of 300 KLD capacity Compact type MBR technology based Sewage treatment plant as per above specification |
| 88 | PART B ETP WORK 30 KLD (EFFULENT TREATMENT PLANT) |
| 89 | SUB HEAD: EFFULENT TREATMENT PLANT |
| 90 | Supply, Fabrication, installation, testing and commisioning of Fully automatic effluent treatment plant based on Areation Process (30 KLD ETP ) with effluent handling capacity of 30 KLD per day. The entire plant will be constructed in MSEP / JINK ALUMINIUM Febricated. The ETP shall be designed as per Raw water, with necessary chemical dosing as required by the manufacturer's design. All the equipment, piping, pumps, air blowers and electrical panel etc. (Defect Liability Period will be 05 Years, All Parts and Machinery maintenance, Replacement included in 05 Year DLP) |
| 91 | Electro Machanical |
| 92 | 30 KLD Effluent Treatment Plant Based Areation Technologies |
| 93 | Bar Screen :- Providing & fixing of 2 nos. SS-304 wire Bar Screen of size 500mm x 600mm having provision for lifting arrangement etc. complete as required. (Make:- Willmer/Eco Vibe Solutions Pvt. Ltd./eqv.) :- 2 Nos |
| 94 | EQUALIZED WASTE WATER TRANSFER PUMPS / RAW SEWAGE PUMP : 2 (1W + 1S) Nos. |
| 95 | Providing & fixing fully submersible sewage handling type pump for raw sewage transfer from equalization tank to aeration tank. The pump shall have complete CI construction, TEFC induction motor including pressure gauge, lifting arrangement for the pump. Solid handling shall be 25-40 mm. Make- Kirloskar/ Wilo/ Cromton Greves/ Assurity/Toshio/CNP/Eqv. |
| 96 | Capacity : 1.5 M3/hr @ Discharge Head 10-15 M head (1 Working + 1 Standby), |
| 97 | Air Blower :- Diffusion system shall include the following: 2 (1W + 1S) Nos |
| 98 | Ring Blower / Twin Lobe type rotary air blowers 2 Nos. (1 W + 1 S) Capable of delivering 30 cum/hr (each) of free air at 0.45 kg/cm2 driven through “V” belt or directly coupled through flexible coupling to a TEFC motor of suitable HP Suitable for 415 ± 10% volts, 3 phase, 50 cycles a/c supply for aeration of EQT and SHT. Make: Everest/Beta/Akash/Airvac/Usha/Eqvt. |
| 99 | Air piping :- shall comprise of pipes droppers/ laterals with MS C Class Header complete with all fittings such as tees, crosses, plugs, sockets, elbows, reducers, supports & clamps, puddle flanges etc cutting chases & making good in Plant Room. Make: Tata/Jindal/Supreme/Astral/Prince/Surya Prakash/Eqv. :- 1 Lot |
| 100 | Diffusers :- Fine /coarse aeration bubble diffusers as required. :- 1 Lot |
| 101 | Air dispersion system shall be provided for Equalisation Tank, Sludge holding Tank and Ariation Tanks. :- 1 Lot |
| 102 | TUBE MEDIA :- Supply, installation, testing Tube Settler reactor Media Package :- 1 Lota) TUBE MEDIA - |
| 103 | Make- MM Aqua/ PP Aqua/ Pharmtech/ Vasu Enviro/ Eqv. |
| 104 | SLUDGE TRANSFER PUMP / SLUDGE RECIRCULATION PUMP : 2 (1W + 1S) Nos. |
| 105 | Providing and fixing horizontal, centrifugal sludge transfer pump with 7-10mm solid handling. The pumps shall have CI casing, CI Impeller & CS shaft & sleeve with mechanical seal. MSEP common base frame. |
| 106 | Make- Kirloskar/ Wilo/ Cromton Greves/ Assurity/Toshio/CNP/Eqv. |
| 107 | Capacity 1.5 m3/hr @ 8-10 m head |
| 108 | FLASH MIXTURE:-Supplying, installing, testing & commissioning of 100 Litres capacity PVC tank with inlet / outlet connection & piping. |
| 109 | Make- Kirloskar/ Wilo/ Cromton Greves/ Assurity/Toshio/CNP/Eqv. |
| 110 | Chemical Dosing TANK :- Supplying, installing, testing & commissioning of 100 Litres capacity PVC tank with inlet / outlet connection & piping. :- 3 Nos |
| 111 | DOSING PUMP:- 3 Nos |
| 112 | Capacity 0 TO 10 LPH |
| 113 | Make- Edose/ Aster/ Eqvt. |
| 114 | All Type Valves :- 1 Lot |
| 115 | Make- Astral/Supreme/Marck/Kartar/Eqv. |
| 116 | MS 'C' class : pumps & Filters interconnecting piping. :- 1 Lot |
| 117 | Make- Tata/Jindal/Surya Prakash/Eqvt. |
| 118 | Pressure Gauge 0 to 7 KG (SS-304) :- 1 Nos |
| 119 | Make:- Hguru / Forbes Marshel / Eqvt. |
| 120 | Lavel Switch / Float Switch :- 2 Nos |
| 121 | Make:- Jigo / Sibaas / Inflo / Flo / Eqvt. |
| 122 | Electro magnetic type flow meter :- Providing & fixing on line Electro magnetic type flow meter cum Totaliser for Monitoring the total flow, Flow rate. etc. Including electrical wiring from panel to flow meter. Complete with all type of Plumbing & Electrical connections, accessories, wiring, conduits & supports complete with all respect. : 1 No. |
| 123 | Make- Unitech/ UPC/ Eqv. |
| 124 | Prefabricated MSEP UNIT/TANKS : 1 SET |
| 125 | Anoxic Tank-1 |
| 126 | Areation Tank-1 |
| 127 | Pre Clarifier Tank-1 |
| 128 | MCC PANEL for ETP :- 1 Nos |
| 129 | Required MCC PANEL capacity of MCCB for DOL/ Star Delta starter and outgoing feeders for all pumps, motors and operating equipment. Each compartment shall contain Auto/ Manual switch, contactor, relay, single phase preventer, sequential controller for auto operation of working and standby equipment complete in all respects for the following, but not limited to: |
| 130 | Panel shall be designed on the actual HP as per model selection of pumps |
| 131 | starters shall be provided with Automatic level controller As Required |
| 132 | Notes: |
| 133 | All MCCBs / MCBs shall be of 18 / 10 KA breaking capacity and suitable for motor duty application. |
| 134 | All motor starters shall be provided with Automatic level controller |
| 135 | DOL starters shall be used for motors below 10HP and Star-Delta Starters for other motors . |
| 136 | Provision for dry run protection shall be made in the panel. |
| 137 | MCC for STP as described above |
| 138 | All Control system to Make the STP fully automatic. The operation of the pumps shall be controlled by the level controller. |
| 139 | Supplying & Fixing of Cables , Conector, Cable Trays, to make Electrical Installation Complete. Necessary cable alleys, internal / cabling, wiring, cabling from MCC to various pumps / equipment and interlocking. |
| 140 | Total PART B : Supply, Installation, testing & commissioning of 30 KLD capacity Effluent treatment plant as per above specification |
| 141 | Note :- The scope of work as provided above (in Part A and Part B) is tentative however, any unforseen item involved for completion of the work in all respect upto the commissioning stage shall be part and parcel of the contract & cost for the same shall be borne by the bidder without any additional financial burden to the client. |
| 142 | PART C Online Effluent Quality Monitoring System |
| 143 | * Online Effluent Quality Monitoring System (COD, BOD, TSS, pH ) |
| 144 | PART D OPERATION & MAINTENANCE FOR 05 YEAR STP and ETP |
| 145 | The SITC of Both Sewage Treatment Plant and Effluent Treatment Plant includes 05 Years of operation and maintenance All Parts and Machinery maintenance, Replacement included in 05 Year DLP. The Operation and maintanance of above STP/ETP will be for 05 Years which includes 24x7 operation of STP and ETP each by skilled operator, regular backwashing/cleaning, all Consumables and any other activity required for un-hindered operation of STP and ETP. The Payment of O&M cost will be done on quarter basis (after every 3 months) after getting report of outlet parameters matching with prevailing RPCB/CPCB norms. 3 % of SITC Work for first year |
| 146 | Five Year O & M ( O & M with All Labour/Operator's and All Consumable Chemicals and Part’s Replacement. ) |
| 147 | OPERATION & MAINTENANCE COST FOR 1st YEAR |
| 148 | OPERATION & MAINTENANCE COST FOR 2nd YEAR |
| 149 | OPERATION & MAINTENANCE COST FOR 3rd YEAR |
| 150 | OPERATION & MAINTENANCE COST FOR 4th YEAR |
| 151 | OPERATION & MAINTENANCE COST FOR 5th YEAR Please Enable Macros to View BoQ information |