| 1 | Fitting and providing one HT Stay for 11kV pole, including digging and back filling pit in ordinary soil. |
| 2 | Additional rate for excavation of one Pit for HT Pole/HT Stay in Hard Laterite. |
| 3 | Additional rate for excavation of one Earth Pit (2.5m depth) in Hard Laterite. |
| 4 | Providing one Earth using GI earth pipe of size 38.1mm dia, 2.5m length including digging separate pit (0.45x0.45x2.5m) at a minimum distance of 1.5m away from the pole/structure and maintaining standard distance between different earth pipes in ordinary soil & backfilling. |
| 5 | Fitting one set (3No.) 11kV LA and giving connections excluding earthing. |
| 6 | Doing one cable end termination on HT XLPE UG cables of sizes beyond 3x185 sqmm and upto and including 3x300 sq mm using the cable jointing kit supplied departmentally after making fencing,caution board and all other safety measures including charges for cable jointer etc. complete as per the direction of the departmental officers. |
| 7 | Doing straight joint on HT XLPE UG cables of sizes beyond 3x185 sqmm and upto and including 3x300 sq mm using the cable jointing kit supplied departmentally as per specification after providing proper traffic signalling and caution board fencing etc. wherever necessary, including charges for cable jointer and other sundries etc. as per the direction of departmental officers at site. |
| 8 | Transporting poles by hired vehicle to a distance upto 5km and carrying upto 4 numbers of poles excluding loading& unloading charges. |
| 9 | Excavation of cable trench of appropriate size ( normally 1.2m deep and 0.35m /0.5m wide for single/double run) in all classes of soil including breaking clods, watering, ramming and sectioning of soil bank etc. and back filling the soil after cable laying and consolidating the soil in layers of 75cm (excluding laying of cable). |
| 10 | Laying HT XLPE UG cable of sizes beyond 3x185 sq mm and upto and including 3x300 sqmm including conveying cable from Sub Regional Store/stacking place to work site and laying it carefully using cable rollers, taking through stone ware/G.I.pipes at road crossing/culverts/bridges etc. whereever necessary, providing identification tags at 5m intervals, filling the space around the cable with riddled soil and covering the top with bricks, providing cable route markers at 100m intervals, inclusive of cost of all materials (other than cost of GI/HDPE pipe & UG Cable), labour and transport including crane charges excluding excavation and backfilling. |
| 11 | Additional rate for excavating trench on tarred/concrete surface of specified size. |
| 12 | Additional rate for excavation of cable trench of appropriate size (normally 1.2m deep and 0.35m /0.5m wide for single/double run) in exceptionally hard conditions (like in ordinary rock). * (As per the PWD Standard Data book ,ordinary rock is defined as any material which can be quarried or split with crowbars or wedges). |
| 13 | Fitting and erecting one HT Double Pole Structure using A type pole in position including fitting 2 No. channel cross arm, digging and back filling pit in ordinary soil, drawing sufficient length of GI earthing leads through all cross arms to the ground for earthing (excluding provision of earthing). |
| 14 | Fitting one Additional 2.4m/3m Channel cross arm (100x50x6mm), in existing 11kV DP including conveyance of materials. |
| 15 | Labour charges for loading HT A type pole from the stacking place and unloading the same at work site (transportation by any vehicle). |
| 16 | Mounting and connecting HT XLPE UG cable ends of all sizes upto and including 3x300 sq mm with special type cable clamps, bolts, nuts, terminal protectors etc.including cost of extra materials if needed and giving necessary jumper connections. |
| 17 | Providing concrete muffing of size 0.45x0. 45x1.5m (0.5m above GL and 1m below GL). Excavation 0.45x0.45x1m, concrete (1:3:6, 20mm) 0.45x0.45x1.5m, Plastering (1:3) 12mm 0.45x0.45mx5sides. |
| 18 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 19 | Object Marking (traffic signal painting) in one LT, HT, HT/LT pole for a height of 1.5m from ground level using approved quality primer one coat and two coats anti algal black and fluorescent white paint in alternate rings of 25cm width including cost of paints. |
| 20 | Pole numbering using printed Aluminium sheets of 22 SWG having size 20 x 12 cm or Painting the surface of line supports where numbers are to be inscribed, Pole numbers shall be painted in circular / rectangular background, using approved quality anti algal yellow paint in two coat after scraping and cleaning the surface at a height of 2.5 metre above ground level. The number and letters should be in black synthetic enamel paint. The size of the number should be at least 2cm in height x 1.5cm in width. including cost of paint. |
| 21 | Horizontal Directional Drilling (HDD), supplying and pulling 110/125 /160 mm HDPE pipe duct for drawing 3 × 300 sq.mm Aluminium XLPE underground (UG) cable through the HDPE Pipe , including drawing, pulling, and laying of the UG cable; including route survey for identification of underground utility installations and other obstructions using suitable modern sensing equipment, pit excavation, pilot drilling, pre-reaming, reaming, and duct pulling, using bentonite or approved drilling fluid wherever necessary for bore stability and lubrication; cable pulling, backfilling and closing of pits with normal soil and proper consolidation or by any method as directed by the Department Authorities, without causing damage to existing utility services; supplying and providing route markers at 100m intervel and providing danger/caution boards as per the directions of Department Officers, etc |
| 22 | Quoted Amount as per BOQ 1 |
| 23 | GST amount in Percentage Please Enable Macros to View BoQ information |