| 1 | STRENTHENING TO THE ROAD FROM MULLIMUNAI BUS STOP TO SEASHORE ROAD KM 0/0-0/600-R-773-(VPR) 600M IN MULLIMUNAI PANCHAYAT |
| 2 | Clearing the Light Jungle with out uprooting including all labour charges |
| 3 | Picking the Existing B.T surface including all labour charges etc complete |
| 4 | Earthwork in all soils except hard rock requiring blasting and conveying for formation of bund with lead of 0 to 100 metre deploying earth moving machineries and tippers including benching, formation fo bunds, breaking clods, sectioning etc., complete. |
| 5 | Providing and Laying Gravel Soling to compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, water and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content and hire and fuel charges for power roller, water sprinkler and all other incdidental charges such as traffic barricading and providing danger lights etc., complete. |
| 6 | Km 0/0 - 0/600 |
| 7 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 8 | Km 0/0 - 0/600 |
| 9 | Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. |
| 10 | Km 0/0 - 0/600 |
| 11 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all |
| 12 | Km 0/0 - 0/600 |
| 13 | Providing and laying Bituminous Concrete to 30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP asper clause 507 of MORTH Rev-5 |
| 14 | Km 0/0 - 0/600 |
| 15 | Provision for Road Marking With That Applied Thermo Plastic Compound etc |
| 16 | Km 0/0 - 0/600 |
| 17 | 60 cm Equilateral Triangle Cautionary Sign Board |
| 18 | 60 Cm Circle (Mandatory ) Sign Board |
| 19 | Chevron Signs 90cm Octagon (Curves) |
| 20 | Reflector |
| 21 | Guard Stone (Precast ) |
| 22 | Hecta metre stone |
| 23 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \\"BB\\" for all works in this package} Please Enable Macros to View BoQ information |