| 1 | Clearing snow (with frost) from roads Manual/Mechanically) |
| 2 | Clearing snow (without frost) from roads Manual/Mechanically) |
| 3 | Snow depth upto 150 mm |
| 4 | Snow depth over 150 mm but upto 250 mm |
| 5 | Snow depth over 250 mm but upto 350 mm |
| 6 | Snow depth over 350 mm but upto 450 mm |
| 7 | Snow depth over 450 mm but upto 550 mm |
| 8 | Snow depth over 550 mm but upto 650 mm |
| 9 | Snow depth over 650 mm but upto 750 mm |
| 10 | Snow depth over 750 mm but upto 850 mm |
| 11 | Snow depth over 850 mm but upto 950 mm |
| 12 | Snow depth over 950 mm but upto 1050 mm |
| 13 | Snow depth over 1050 mm but upto 1150 mm |
| 14 | Snow depth over 1150 mm but upto 1250 mm |
| 15 | Galla cutting in compressed snow |
| 16 | 150 mm deep and 4 mtr wide |
| 17 | 1200 mm deep and 4 mtr wide |
| 18 | Slip Clearance |
| 19 | Slip Clearance in mixed soil i.e, ordinary soil, Soils mixed with moorum kankar/shingle/Boulders and decomposed rock by blasting are any other means including safe disposal as per the directions of the Engineer in-Charge at site without Damaging the Public/Pvt. Property. |
| 20 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 metres: All kinds of soils |
| 21 | Construction of crate work by way of handpacking of stones in wire crates including cost of stones & crates of 4mm dia GI wire conforming to IS:280 & IS:4826 in 100mm*100mm mesh (woven diagonally) |
| 22 | Backfilling/surface filling by way of dumping of stones in horizontal including cost of stones |
| 23 | Dry random rubble masonry with hard stone in foundation and plinth/ superstructure with bond stone. |
| 24 | Deployment of labour for removal of individual boulders, opening of blocked drains/choked culverts including cleaning the BT surface. |
| 25 | Disposal of surplus mulba for safe disposal by MT from private land including loading/unloading complete without damaging the Public/Pvt. Property (Qty @ 80%) from pvt. Land. |
| 26 | Carriage of stones from source to site of work including loading/unloading complete by MT for an average distance of 05 kms Please Enable Macros to View BoQ information |