| 1 | BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 10. Stripping off worn out plaster and raking out joints of walls, celings etc. upto any height and in any floor including removing rubbish within a lead of 75m as directed. |
| 2 | SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface] i) With 1:6 cement mortar (b) 20 mm thick plaster |
| 3 | SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface] i) With 1:6 cement mortar (c) 15 mm thick plaster |
| 4 | SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface](ii) With 1:4 cement mortar (c) 10 mm thick plaster |
| 5 | (B) - SANITARY AND DRAINAGE WORKS.(B)-(III) WATER CLOSETS AND URINALS.a) Original Works.(4)Supplying, fitting and fixing Orissa pattern water closet in white glazed vitreous chinaware of approved make in position complete excluding 'P' or 'S' trap (excluding cost of concrete for fixing).(ii) 530 mm X 410 mm |
| 6 | SECTION(B) - SANITARY AND DRAINAGE WORKS.(B)-(II) SOIL PIPE AND FITTINGS.(a) Original Works.(14)Supplying,fitting and fixing cast iron 'P' or 'S' trap conformimg to I.S. 3989/ 2009 and 1729/ 2002 including lead caulked joints and painting two coats to the exposed surface. (Painting to be paid seperately).(A) 'P' Trap.(iii) 100 mm. |
| 7 | (B) - SANITARY AND DRAINAGE WORKS.(B)-(III) WATER CLOSETS AND URINALS.a) Original Works.(9)Supplying, fitting and fixing Foot rest for water closet of size 275 mm X 125 mm with.(b) Porcelain of approved make. |
| 8 | BUILDING WORKS (G) WOOD AND PVC WORKS A. DOOR WINDOW FRAME 3. Supplying, fitting and fixing fibre reinforced polymer (FRP) Composite door frame as per approved section with glass fibre reinforced plastic moulded skins and a special sandwich core, so as to impart monolitaheic composite structure as per approved technology of Department of Science and Technology (DST) to safisfy IS: 4020 door testing performance criteria (ii) 66mm x 70mm |
| 9 | BUILDING WORKS (G) WOOD AND PVC WORKS B. DOOR WINDOW SHUTTER 14. Supplying, fitting & fixing fibre reinforced polymer (FRP) Composite door shutters as per approved design with glass fibre reinforced plastic moulded skins and a special sandwich core, so as to impart monolitaheic composite structure as per approved technology of Department of Science and Technology (DST) to satisfy IS:4020 door testing performance criteria. In ground floor (ii) 25 mm thick (For upper floors refer to item H(4) also) |
| 10 | BUILDING WORKS(D) Flooring..A. ORIGINAL WORKS?(17)18 mm. to 22 mm. thick, kota stone slab set in 20 mm thick (avg) cement mortar (1:4) in floor, stair & lobby including pointing in cement slurry with admixture of pigment matching the stone shade, including grinding & polishing as per direction of Engineer - in - charge to match with the existing work. [Slurry for bedding @ 4.4 kg/Sq.m and pointing @2.0 kg/Sq.m](Add extra for each addl, floor over the rate for item 22, 25, 26, 17, 20, 31, 32 & 15 of subhead A. (I) upto 4 th floor- Rs. 12/-per Sq.m II) above 4th floor -Rs. 16/- per Sq.m |
| 11 | BUILDING WORKS (D) Flooring A. ORIGINAL WORKS 35. Supplying, fitting & fixing 1st quality Ceramic tiles in walls and floors to match with the existing work & 4 nos. of key stones (10mm) fixed with araldite at the back of each tile & finishing the joints with white cement mixed with colouring oxide if required to match the colour of tiles including roughening of concrete surface, if necessary or by synthetic adhesive & grout materials etc. (B) Wall. With Sand Cement Mortar (1:3) 15 mm thick & 2 mm thick cement slurry at back side of tiles using cement @ 2.91 Kg/Sq.m & joint filling using white cement slurry @ 0.20kg/Sq.m. (a) Area of each tile upto 0.09 Sq.m (i) Coloured decorative. Note: 2. Add extra for each addl, floor over the rate for item 35 & 36 of subhead A. (i) upto 4 th floor-Rs 5/ Sq.m (i) above 4 th floor-Rs 6.25/ Sq.m |
| 12 | Sub Total |
| 13 | GST 18% |
| 14 | CESS 1% Please Enable Macros to View BoQ information |