| 1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means over areas (exceeding 30cm in depth, 1.5m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth, lead up to 50m and lift up to 1.5m,as directed by Engineer-in-Charge. |
| 2 | All kinds of soil |
| 3 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift. |
| 4 | Providing and laying in position ready mixed plain cement concrete, with cement content as per approved design mix and manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for plain cement concrete work, including pumping of R.M.C. from transit mixer to site of laying and curing, excluding the cost of centering, shuttering and finishing, including cost of curing, admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer-in-charge.” Note : Excess/less cement used than specified in this item is payable/ recoverable separately.All works upto plinth level : |
| 5 | M-10 grade plain cement concrete (cement content considered @ 220 kg/cum) |
| 6 | Concrete of M25 grade with minimum cement content of 300 kg /cum |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form for |
| 8 | Foundations, footings, bases of columns, etc. for mass concrete |
| 9 | Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. |
| 10 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. |
| 11 | Thermo-Mechanically Treated bars of grade Fe-500D or more. |
| 12 | Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge; for the following grades of concrete. Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the specified minimum cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement.All works upto plinth level : |
| 13 | Concrete of M25 grade with minimum cement content of 330 kg /cum |
| 14 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in foundation and plinth in: |
| 15 | Cement mortar 1:6 (1 cement : 6 coarse sand) |
| 16 | 12 mm cement plaster of mix : |
| 17 | 1:6 (1 cement: 6 coarse sand) |
| 18 | 15 mm cement plaster on rough side of single or half brick wall of mix : |
| 19 | 1:6 (1 cement: 6 coarse sand) |
| 20 | Finishing walls with Acrylic Smooth exterior paint of required shade : |
| 21 | New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm) |
| 22 | Providing and applying white cement based putty of average thickness 1 mm, of approved brand and manufacturer, over the plastered wall surface to prepare the surface even and smooth complete. |
| 23 | Demolishing cement concrete manually/ by mechanical means including disposal of material within 50 metres lead as per direction of Engineer - in - charge. |
| 24 | Nominal concrete 1:3:6 or richer mix (i/c equivalent design mix) |
| 25 | Nominal concrete 1:4:8 or leaner mix (i/c equivalent design mix) |
| 26 | Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. |
| 27 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. |
| 28 | In cement mortar |
| 29 | Dismantling manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge : |
| 30 | Water bound macadam road |
| 31 | bituminous road |
| 32 | Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved. |
| 33 | Providing and laying Dense Graded Bituminous Macadam using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers as per specifications to achieve the desired compaction and density, complete as per specificatons and directions of Engineer-in-Charge. |
| 34 | 50 to 100 mm average compacted thickness with bitumen of grade VG-30 @ 5% (percentage by weight of total mix) and lime filler @ 2% (percentage by weight of Aggregate) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity. |
| 35 | Providing and laying Bituminous concrete using crushed stone aggregates of specified grading, premixed with bituminous binder and filler, transporting the hot mix to work site by tippers, laying with paver finisher equiped with electronic sensor to the required grade, level and alignment and rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction and density as per specification, complete and as per directions of Engineer-in-Charge. |
| 36 | 40/50 mm compacted thickness with bitumen of grade VG-30 @ 5.5% (percentage by weight of total mix) and lime filler @ 3% (percentage by weight of Aggregate) prepared in Batch Type Hot Mix Plant of 100-120 TPH capacity. |
| 37 | Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5mm), including making drainage opening wherever required complete etc. as per direction of Engineer-in-charge (length of finished kerb edging shall be measured for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge). Note : Excess/less cement used than specified in this item is payable/ recoverable separately. |
| 38 | Construction of granular sub-base by providing close graded Material conforming to specifications, mixing in a mechanical mix plant at OMC, carriage of mixed material by tippers to work site, for all leads & lifts, spreading in uniform layers of specified thickness with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per specifications and directions of Engineer-in-Charge. |
| 39 | With material conforming to Grade-II (size range 53 mm to 0.075 mm) having CBR Value-25 |
| 40 | Providing, laying, spreading and compacting graded stone aggregate (size range 53 mm to 0.075 mm ) to wet mix macadam (WMM) specification including premixing the material with water at OMC in for all leads & lifts, laying in uniform layers with mechanical paver finisher in sub- base / base course on well prepared surface and compacting with vibratory roller of 8 to 10 tonne capacity to achieve the desired density, complete as per specifications and directions of Engineer-in-Charge. |
| 41 | Providing and erecting 2.00 metre high temporary barricading at site; each panel of size 2.50mx2.00m made of 40x40x6mm angle iron or 50x50x3mm hollow MS tube posts/horizontal members/bracings covered with 1.63mm thick MS sheet. The sheet shall be fixed with 30x5mm MS flat by suitable welding/riveting. The panels shall be made so that gap of 50cm above the ground is available making overall height as 2.5m. MS channel ISLC 75 @ 5.70 kg/m, 50cm long shall be provided at the bottom having oval shaped holes of size 50x25mm at both ends with 50cm long MS angle 40x40x6mm bracing. Suitable arrangement shall be made to fix the barricading to avoid from overturning by providing 250mm long expansion fasteners at both ends. The work shall be executed as per drawing/direction of Engineer-in-Charge which includes writing and painting, arrangement for traffic diversion such as traffic signals during construction at site for day and night, glow lamps, reflective signs, marking, flags, caution tape as directed by the Engineer-in-Charge. The barricading provided shall be retained in position at site continuously i/c shifting of barricading from one location to another location as many times as required during the execution of the entire work till its completion. Rate include its maintenance for damages, painting, all incidentals, labour materials, equipments and works required to execute the job. The barricading shall not be removed without prior approval of Engineer-in-Charge. (Note :- One time payment shall be made for providing barricading from start of work till completion of work i/c shifting. The barricading provided shall remain to be the property of the contractor on completion of the work). |
| 42 | Taking out existing kerb stones of all types from footpath/ central verge, including removal of mortar etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge. |
| 43 | Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge. |
| 44 | Providing and laying 60mm thick factory made cement concrete interlocking paver block of M -30 of any design/ shape laid in required line, level, curvature, colour and pattern over 20 mm thick bed of cement mortar 1:4 (1 cement: 4 coarse sand) compacting and proper embedding/laying of inter locking paver blocks including grouting the joints with white cement mixed with matching pigments etc. Complete as per the direction of Engineer-in-charge. |
| 45 | Providing and laying graded stone aggregate in foundation as rubble soling of size range (a) 90 to 40 mm |
| 46 | Add 3% Cost Index on DSR 2023 |
| 47 | Modified Estimated Cost due to correction in GST Rate @ 0.973 =(Estimated cost based on DSR 2023 items *0.973) = (-) (11914588*0.027= 321694) |
| 48 | Hiring of Hydra machine at site on hire basis for lifting of RCC slab, beam and railing etc. including driver, helper, supervisor, required T&P and D.O.L. completed as per direction of Engineer-in-charge. |
| 49 | Providing & fixing Fabricated and manufactured solid RCC precast drain, drain cover, box culvert and other precast concrete element (Concrete grade M50) with provisions of shear keys, connecting loops, dowel tubes and proper lifting accessories for walls, beams, slabs, stairs, column, drain, drain cover etc, of various thickness, shape and size of different concrete grades manufactured in controlled factory environment with approved methodology including moulds (Pallet system, Tilts form, table moulds, battery moulds, vertical moulds, beam moulds, column moulds, staircase moulds, Facade mould, etc.), mixing, transporting and placing of concrete, vibrating, curing, finishing, making necessary cutout/holes of required sizes for services, yard handling & stacking all complete as per IS 11447:1985 and as per approved shop drawings, IS Code and design mix as per the direction of Engineer-in-Charge. Providing Thermo-Mechanically Treated bars of grade Fe-500D or more in precast U shaped drain, drain cover and other precast concrete element as per approved shop drawing for RCC. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. The transportation of RCC precast drain, drain cover, box culvert and other precast concrete element upto any lead by flat bed Trailor (Double/Triple axle 40ft. Length with proper accessories like A frame etc) from factory including the cost of loading, unloading & stacking at site with the help of required capacity cranes. The Erection & Installation of RCC precast drain, drain cover, box culvert and other precast concrete element in correct & final position with proper line level and plumb at site making all arrangements (i.e cranes, push-pull jacks & all another T & P for lifting Placing & Alignment of elements, within erection tolerance as per IS 15916 as per approved shop drawings and all complete as per the direction of Engineer-in-Charge including the cost of sim pads, non shrink grout and steel works i.e hangers. All work upto plinth level. RCC precast manufactures shall have facilities of automated steam curing and automated reinforcement cage making along with product testing facility and NABL, approved testing laboratory within plant premises. The precast drain shall be capable of carrying a wheel load of minimum 5.00 tonne for heavy vehicle movement. |
| 50 | Deduction for Salvage Value of Dismantled materials which will be taken out from site by the Agency and clearing the site as per direction of Engineer in Charge. (Dismantled materials shall be the properties of the Contractor for which credit have been made from the bill of the contractor by the Department). |
| 51 | Old Kerb Stone |
| 52 | Old Interlocking paver tiles |
| 53 | Old Reinforcement bar |
| 54 | Old bricks Please Enable Macros to View BoQ information |