| 1 | Strengthening the road from Pasupathi shop toDhanapal house at Gandhi nagar Km 0/0-0/265 |
| 2 | Clearing the Scrub jungle by uprooting including allcutting charges and disposing of the products andclearing as directed by the departmental officersincluding all incidental charges etc., complete |
| 3 | KM 0/0 - 0/265 |
| 4 | Picking 5 cm to 10 cm old metalled surface andsectioning - 1 sq m |
| 5 | KM 0/0 - 0/265 |
| 6 | collection and supply of carted earth from approvedquarry an average lead 1km including cost andconveyance of all materials to site anf labourcharges etc. |
| 7 | KM 0/0 - 0/265 |
| 8 | Providing and laying spreading and compactinggraded stone aggregate to Wet Mix acadam(WMM)specification including premixing the material withwater at OMC in machanical mix plant carriage ofmixed material by tipper to site laying in uniformlayers 250mm thick with pavers in SubBase/Basecourse on well prepared surface and compactingwith vibratory roller to achieve the desired densityincluding cost of material,labour charges, rentals formachinery, fuel and all other incidental charges etc.,complete. |
| 9 | KM 0/0 - 0/265 |
| 10 | Applying PRIMECOAT over WMM surface at7.00Kg of SS-1 Bitumen Emulsion / 10 sq.mincluding labour for spraying, hire charges forbitumen sprayer etc. Comp |
| 11 | KM 0/0 - 0/265 |
| 12 | Applying TACK COAT over Primed WMM surfaceat 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.mincluding labour for spraying, hire charges forbitumen sprayer etc. Comp. |
| 13 | KM 0/0 - 0/265 |
| 14 | using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials toCMP site, heating the bitumen and aggregate torequired temperature and mixing them in requiredtemperature in central hot mix plant 20-30 toncapacity, conveying the mix by tipper trucks to paversite, spreading the mix to uniform thickness of 40mmwith mechanical paver to the specified grades andcross sections and consolidated by 8-10 tonneVibratory to the required density etc., includinglabour for attending to paver to site etc., includinghire charges and fuel charges for 20-30 t CMP withbitumen boiler, tipper trucks, Paver Finisher,Vibratory roller and all other tools and plant required,including fuel and all other incidental charges etc.,complete as per specification using CMP as perclause 507 of MORTH Rev-5 |
| 15 | KM 0/0 - 0/265 |
| 16 | Providing and laying of hot Road Making with HotApplied Thermoplastic compound with eflectorisingglass beads @ 250GMs per Sqm area, thickness of 2.50mm is exclusive of surface applied glass beads as per IRC:35, The Finished surface to be level uniform and free from Streaks and holes etc.,Complete as per MORTH&H Specification No.803 |
| 17 | KM 0/0 - 0/265 |
| 18 | Provision for Hecta Metre Stone - Nos |
| 19 | Provision for Sign board charges |
| 20 | 2.Providing CC Pavement from Sithanur mainroad Vasantha house to Kaliyamman kovil viaSakthi nagar H/O Mallamooppampatty (193mx3m) |
| 21 | Earth work Excavation in all soils & Sub Soil to fulldepth as may be directed except in hard rockrequiring blasting but inclusive of shoring strutting,Sectioning the street to lay concrete pavement perSS 20 B. |
| 22 | Cement concrete 1 : 4 : 8 mix using 40mm HBGmetal for foundation including watering wherevernecessary and laid in layers of not more than 15cmthick., compacting etc., complete |
| 23 | Supplying and erecting centering shuttering including necessary supports for planesurface in foundation and basement and in all floorsfor R C C column footing column plinth beam,beams, roof slabs, staircase steps, bed blocks,critical pier etc,. complete |
| 24 | Plain Cement Concrete 1:2:4 (one cement, twoM.Sand and four hard broken stone jelly)using 20mm jelly for wearing coat including laying,compacting, finishing and curing, etc., complete asper standard specificatins and as directed by thedepartmental officers |
| 25 | Provision for Bitumen pad |
| 26 | GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column \\"BB\\" for all works in this package} Please Enable Macros to View BoQ information |