| 1 | Earth work excavation for foundation in hard stiff clay,except in hardrock reqiring blasting inclusive of shoring shuttering and bailing out water wherever necessary refilling the sides of foundation with excavated soil well rammed and completed depositing the surplus excavated soil with in the compound in places shown by the departmental officrs with initial lead and lifts and cleaning, levelling, the site etc., complete as per SS 20B for foundation |
| 2 | Cement Concrete 1:4:8 (One cement, four fine aggregate and eight course aggregate) mix using 40mm HBG ISS metal from approved quarry including cost and conveyance of all materials to site and labour charges, including dewatering if found necessary and laid in layers of not more than 15cm thick and compacted etc., complete complying with standard specifications as directed by the departmental officers |
| 3 | Centering for soffits of CC slabs of plane surface like lintels, beams, etc., including strutting 3m high using mild steel sheets of size 90cm x 60cm x and BG 10 stiffened with MS angles of size 25mm x 25mm x 3mm laid over silver oak joists of size 10cm x 6.5 cm spaced at about 90 cm c/c and supported by consurina props of 10 cm to 13cm dia spaced of 75cm c/c complying with standard specifications and as directed by the departmentsl officers etc., complete |
| 4 | Centering for soffits of RCC slabs of plane surface like lintels, beams, etc., including strutting 3m high using mild steel sheets of size 90cm x 60cm x and BG 10 stiffened with MS angles of size 25mm x 25mm x 3mm laid over silver oak joists of size 10cm x 6.5 cm spaced at about 90 cm c/c and supported by consurina props of 10 cm to 13cm dia spaced of 75cm c/c complying with standard specifications and as directed by the departmentsl officers etc., complete |
| 5 | Plain Cement Concrete 1:2:4 (One cement Two aggregate and Four course aggregate) mix using 20mm HBG ISS metal for all RCC items of works excluding centering and shuttering and cost of reinforcement grill but including curing the same and also fixing fan clamps and fixtures in RCC works whereever necessary as directed by the departmental officer etc., complete |
| 6 | Finishing the top of flooring with granothatic flooring with cement concrete 1:2:4 (one cement, two M- Sand and four aggrigate) using 10 to 12mm stone chips – 25mm tk etc., Complete. |
| 7 | Supplying and fabrication of steel and placing in position of TMT steel rods for RCC works as per design given including cost of steel and GI binding wire in all floors etc., complete complying with standard specification |
| 8 | Reinforced Cement Concrete 1:1½:3 Mix (One part cement, one and half part sand and three part of aggregate)using 20mm size ISS HBG metal machine crushed from approved quarry including cost and conveyance of all materials to site, loading and unloading charges and labour charges for mixing, laying and curing but excluding cost of reinforcement etc. Complete with std. Specifications |
| 9 | Towards cost and supply of Manhole Cover SFRC 60x60cm Heavy duty withframe including cost and conveyance of all materials and labour charges ete., complete complying with standard specifications as directed by the departmental officers |
| 10 | Supply and Delivery of 90mm dia 6Ksc PVC pipe as per IS 4985/2000, the cost shall including loading , unloading and stacking charges etc., complete as per standard specification |
| 11 | Removing the excavated earth from the site to 2Km lead including cost and conveyance of all materials and labour charges for loading the earth from the site and unloading the earth in low level portions as pecified by the engineer any where in town panchayat limit etc., complete Please Enable Macros to View BoQ information |