| 1 | Road Maintenance |
| 2 | Removable of rank vegetation/weeds and undesirable vegetation from shoulders,embankment slopes upto ROW(both sides) complete in all respects including breaking of clods, rough dressing and disposal of waste material and vegetation at a place outside ROW as per direction of Engineer-in-charge and as per maintenance Standards Clause 3.3 (Frequency will be once in a quarter) |
| 3 | a) Shoulder including side slopes of embankment upto toe line on both sides of the carriageway.(Frequency of cleaning will be four times in a year; however limited to only areas prone to growth of rank/undesirable vegetation and weeds). |
| 4 | Corporation - Km 1/4 - 2/4, Km 7/650 - 10/070, Km 10/350 - 15/6 , Km 17/560 - 18/560 and Km 20/860 - 21/6 of NH 181 |
| 5 | Non - Corporation - Km 25/7 - 26/350, Km 27/6- 29/2, Km 29/2 - 29/790, Km 32/0 - 37/5, Km 40/4 - 41/2 and Km 42/0 - 50/0 of NH 181 |
| 6 | Hill - Km 50/0 - 63/2 of NH 181 |
| 7 | Clearing slab/ box type culverts and pipe culverts including clearing, clearing and reshaping of upstream and down stream faces of these culverts with in right of way. The job includes disposal of excess material recovered from site including vegetation outside ROW with all leads and lifts complete in all respect as per direction of Engineer In-charge and as per maintenance Standards Clause 3.1 (frequency of cleaning will be Twice in a year i,e. before start and end of monsoon) (SOP - Road Maintenance - Item No - 1.8) |
| 8 | Corporation - Km 1/4 - 2/4, Km 7/650 - 10/070, Km 10/350 - 15/6 , Km 17/560 - 18/560 and Km 20/860 - 21/6 of NH 181 |
| 9 | Slab Culvert (upto 3m) |
| 10 | Minor Bridge (3m to 10m) |
| 11 | Non - Corporation - Km 25/7 - 26/350, Km 27/6- 29/2, Km 29/2 - 29/790, Km 32/0 - 37/5, Km 40/4 - 41/2 and Km 42/0 - 50/0 of NH 181 |
| 12 | Slab Culvert (upto 3m) |
| 13 | Slab Culvert (3m to 10m) |
| 14 | Box Culvert (upto 3m) |
| 15 | Minor Bridge (3m to 10m) |
| 16 | Minor Bridge (more than 10m) |
| 17 | Major Bridge (more than 10m) |
| 18 | Hill - Km 50/0 - 63/2 of NH 181 |
| 19 | Slab Culvert (upto 3m) |
| 20 | Slab Culvert (3m to 10m) |
| 21 | Pipe Culvert (upto 3m) |
| 22 | Box Culvert (upto 3m) |
| 23 | Cut Stone Culvert (upto 3m) |
| 24 | Minor Bridge (3m to 10m) |
| 25 | Minor Bridge (more than 10m) |
| 26 | Major Bridge (more than 10m) |
| 27 | Providing spot reconditioning, reconstruction and regravelling to repair specific erosion or other damages for restoring the eroded area to originally constructed cross section on cuts and fills slopes/ shoulders conforming to Technical Specifcations Clause no. 3002. Fiel material should be brought from borrow areas located outside ROW conforming to Technical Specification no. 305 Watered and well compacted With plate Compactor or power rammer with all leads and lifts as directed by the Engineer (Quantity of Compacted Fill material to be measured on cross sectional area basis) (SOP - Road Maintenance - Item No - 1.1) |
| 28 | Corporation - Km 1/4 - 2/4, Km 7/650 - 10/070, Km 10/350 - 15/6 and Km 20/860 - 21/6 of NH 181 |
| 29 | Non - Corporation - Km 25/7 - 26/350, Km 27/6- 29/2, Km 29/2 - 29/790, Km 32/0 - 37/5, Km 40/4 - 41/2 and Km 42/0 - 50/0 of NH 181 |
| 30 | Hill - Km 50/0 - 63/2 of NH 181 |
| 31 | Clearing and removing silt deposit abutting the centre median on both sides for an average width of 0.75m on either sides including collection and removal of silt deposit, loading including conveying away including conveyance charges, traffic diversion etc., complete (once in 2 months) |
| 32 | Corporation - Km 1/4 - 2/4, Km 7/650 - 10/070, Km 10/350 - 15/6 and Km 20/860 - 21/6 of NH 181 |
| 33 | Non - Corporation - Km 25/7 - 26/350, Km 27/6- 29/2, Km 29/2 - 29/790, Km 32/0 - 37/5, Km 40/4 - 41/2 and Km 42/0 - 50/0 of NH 181 |
| 34 | Painting Two Coats on old Concrete Surfaces (Painting two coats after filling the surface with synthetic enamel paint in all shades on old plastered concrete surfaces) (Frequency of Painting will be as per site requirement however limited to once in a year) |
| 35 | Corporation - Km 1/4 - 2/4, Km 7/650 - 10/070, Km 10/350 - 15/6 and Km 20/860 - 21/6 of NH 181 |
| 36 | Non - Corporation - Km 25/7 - 26/350, Km 27/6- 29/2, Km 29/2 - 29/790, Km 32/0 - 37/5, Km 40/4 - 41/2 and Km 42/0 - 50/0 of NH 181 |
| 37 | Pavement Repairs |
| 38 | Providing treatment and repair to pot holes / ruts and any depth / patch repair of all types of bitumen pavement complete as per Technical Specification Clause 3004.2 and as per direction of engineer by using paving grade bitumen / emulsion/ cold ready mix material. the job includes removal of all failed material, trimming of completed excavation to provide firm vertical faces, cleaning of surface, painting of tack coat on the sides and base of excavation as per clause 503, back filling the pot holes with hot bituminous material as per clause 504, compacting, trimming and finishing the surface to form a smooth continuous surface, all as per clause 3004.2 of Technical Specification. |
| 39 | Corporation - Km 1/4 - 2/4, Km 3/0 - 5/4, Km 10/350 - 15/6 and Km 20/860 - 21/6 of NH 181 |
| 40 | Non - Corporation - Km 40/4 - 41/2 and Km 47/0 - 50/0 of NH 181 |
| 41 | Hill - Km 50/0 - 57/0 and Km 58/3 - 63/2 of NH 181 |
| 42 | Providing and laying of hot applied Thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35. The finished surface to be level, uniform and free from streaks and holes etc., complete as per MoRT&H specification No.803. |
| 43 | Non- corporation and Hills Please Enable Macros to View BoQ information |