| 1 | Sand filling in foundation trenches and at the back of abutments, wing-walls etc. with good local sand free from earth in layers not exceeding 15 cm. including inundating each layer by profuse water and poking and ramming layer by layer complete including supply of sand. Quality of sand is to be approved by the Engineer-in-charge.cum 193.00 343.00 Note : 1. Labour rate per m³ is provided; Cost of sand is to be added to arrive at the complete item rate |
| 2 | Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. |
| 3 | Supplying and laying Polythene Sheet (150gm/sq.m.) over damp proof course or below flooring or roof terracing or in foundation or in foundation trenches |
| 4 | Ordinary Cement Concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS code |
| 5 | Hire and labour charges for Shuttering with or without staging upto 4.0 m height using approved stout props with wooden planks/ply wood/steel sheet plate with required bracing for any kind of plain or reinforced concrete works in all sorts of minor structure including culvert, box culvert, crossdrain etc. The rate is inclusive of fitting, fixing and striking out after completion of work as per specification and direction.(b) Where staging is not required. |
| 6 | Earth work in filling in compound, tank, low land, ditches etc. with good earth, in layers not exceeding 150 mm. including breaking clods and consolidating the same by ramming and dressing complete.(Payment will be made on profile measurement before and after the workb(ii) With carried earth arranged by the contractor within a radius exceeding 3 km. but not exceeding 5 km. including the cost of carried earth. |
| 7 | Providing & fixing Concrete Sign Board as per IRC pecification of size 900 x 750 x 37 mm. thick made with RCC 1:1½:3 with pakur variety stone chips reinforced with double layer IRC febric (75 x 75 mm. mesh) and fixed with necessary nuts & bolts on two RC precast posts 100 mm. x 150 mm. of height 2.65 m. of which top 750 mm. is of ection 100 x 13 mm. and 1.90 metre above GL & 0.75 metre below GL including digging hole, repacking the same with cement concrete 1:3:6 with jhama khoa or with local stone chips etc. complete including painting two coats on both faces lettering sign marks etc. as per direction of the Engineer-in-Charge. (The rate is inclusive of cost of reinforcement, concrete, huttering, nuts & bolts, washer etc. complete |
| 8 | Earth work in excavation of foundation trenches or drains, in all sorts of soil including mixed soil but excluding laterite or sandstone) including removing, preading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete.(a) Depth of excavation not exceeding 1,500 mm. |
| 9 | Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work) (a) With earth obtained from excavation of foundation. |
| 10 | Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. |
| 11 | Supplying and laying Polythene Sheet (150gm / sq.m.) over damp proof course or below flooring or roof terracing or in foundation or in foundation trenches |
| 12 | Ordinary Cement Concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS code |
| 13 | Providing and laying reinforced cement concrete pipe NP3with spigot socket for culverts on first class bedding of granular material in double row including fixing with cement mortar 1:2 as per Technical Specification Clause 1106 for rural roads of MORD (E) 900 mm dia |
| 14 | C.G.S.T 9% |
| 15 | S.G.S.T 9% |
| 16 | Labour cess 1% Please Enable Macros to View BoQ information |