Name of Work:- CONSTRUCTION OF CHATAL OF MUSLIM GRAVEYEARD AT RAIHATILAND, DHANSA JL NO - 19 , POLT NO - 890, 875
Sl. No.
Item Description
1
Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 mm.
2
(B) Filling in foundation or plinth by fine sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand. (payment to be made on measurement of finished quantity)
3
Earth work in filling in foundation or plinth by earth excavated by fresh exacavation in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete.
4
Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand.
5
Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes. (i) Pakur Variety.
6
Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. (a) For works in foundation and upto roof of ground floor/upto 4 m III. OTHER MANUFACTURERS NOT SPECIFIED
7
Hire & Labour charges of shuttering without staging & necessary centering upto 4 m using approved stout props and thick hard wood plank of approved thickness with required bracing for concrete slab beams,columns,lintel curved or straight including fitting Ref: PWD Sch VP 42
8
Supplying and laying thermocol strip
9
Add GST …………..@ 18.00 %
10
Add Contingency charge ……………. @ within 3.00 % Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.