| 1 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sand stone) including removing, spreading or stacking the spoils within a lead of 75 m as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete.(a) Depth of excavation not exceeding 1.5 mRef. Page -1, Item -2 a), PWD SOR Vol-I w. e. f. 1.11.2017 |
| 2 | Supplying and laying Polythene Sheet (150gm / Sq.M) over damp proof course or below flooring or roof terracing or in foundation or in foundation trenches. Ref. Page -47, Item -3, PWD SOR Vol-I w. e. f. 1.11.2017 |
| 3 | Cement concrete with graded jhama khoa (30 mm size) excluding shuttering In ground floor and foundation. (a) 1:3:6 proportionRef. Page -23, Item -1a), PWD SOR Vol-I w. e. f. 1.11.2017 and P-9 of 96, Item -26, 3rd CORRIGENDA & ADDENDA wef 04.06.2018 |
| 4 | Brick work with 1st class bricks in cement mortar (1:6)(a) In foundation and plinthRef.Page -15, Item -8 a), PWD SOR Vol-I w. e. f. 1.11.2017 and P-2 of 96, Item -4, 3rd CORRIGENDA & ADDENDA wef 04.06.2018 |
| 5 | 125 mm. thick brick work with 1st class bricks in cement mortar (1:4) in ground floor.Ref. Page -16, Item -16, PWD SOR Vol-I w. e. f. 1.11.2017 and P-3 of 96, Item -8, 3rd CORRIGENDA & ADDENDA wef 04.06.2018 |
| 6 | Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding / staging where necessary (Ground floor).(i) With 1:6 cement mortar (c) 15 mm thick plasterRef. Page -189, Item -1, PWD SOR Vol-I w. e. f. 1.11.2017 and P-49-50 of 96, Item -1, 3rd CORRIGENDA & ADDENDA wef 04.06.2018 |
| 7 | Ordinary Cement concrete (mix 1:2:4) with graded stone chips (6mm nominal size) excluding shuttering and reinforcement,if any, in gound floor as per relevant IS codes.Ref. Page -41, Item -33 PWD SOR Vol-I w. e. f. 1.11.2017 and P-20 of 96, Item -49, 3rd CORRIGENDA & ADDENDA wef 04.06.2018 |
| 8 | Neat cement punning about 1.5 mm. thick in wall, dado, window, sills, floor, drain etc.NOTE : Cement 0.152 cu.m. per 100 sq.m.Ref. Page -192, Item -15, PWD SOR Vol-I w. e. f. 1.11.2017(0.125+0.375+0.3+0.375+0.125) |
| 9 | Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement,if any, in gound floor as per relevant IS codes. (a) Pakur VarietyRef. Page -24, Item -4 a), PWD SOR Vol-I w. e. f. 1.11.2017 3rd CORRIGENDA & ADDENDA wef 04.06.2018 |
| 10 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. (a) For works in foundation, basement and upto roof of ground floor/upto 4 m(i) Tor steel/Mild SteelIII. Other then SAIL/TATA /RINLBsaed on Analysis RateRef. Page -43-44, Item -40 II), PWD SOR Vol-I w. e. f. 1.11.2017 8th Addenda & Corrigenda w. e. f. 18.04.2018) |
| 11 | Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor)(f) 25 mm to 30 mm shuttering without staging in foundationRef. Page -43, Item -36 f), PWD SOR Vol-I w. e. f. 1.11.2017 |
| 12 | Add 18 % GST |
| 13 | Add 1 % Cess Please Enable Macros to View BoQ information |