| 1 | DRILLING & DEVELOPMENT : Drilling of bore hole of suitable diameter upto required depth by water jet system through any type of soil including hire and labour charges for boring pipes, scaffolding, other tools and plants etc. and taking out same all complete and other incidental works in this connection. The bore hole shouid have minimum 65 mm gap in between outside of the tube well pipe and bore . I) For lowering 100mm. dia GI/PVC pipe |
| 2 | II) For lowering 150mm. dia GI/PVC pipe |
| 3 | Labour charges for lowering of pipe, strainers, blank pipes etc. and fitting, fixing the same including cutting, threading where necessary complete including bucket washing and other incidental works in this connection. i)100 mm dia UPVC Pipe with bottom cutter, Screen (Ribbed) pipes, blank pipe |
| 4 | iv) 150 mm dia UPVC Housing Pipe |
| 5 | Supply of gravel for use as pack in the tube well of 2mm to 4mm size (As per IS:4097) and gravel treatment of tubewell including screening washing, cleaning etc. of the gravels at the site all complete as per direction of Engineer-in-Charge .iii)For site at any district of West Bengal upto 180 km distance from quarry |
| 6 | Supplying, fitting and fixing including supplying of suitable jointing compound for fixing in position, threading, if necessary etc. all complete. a) 100 mm dia CI/Steel cutter piece upto 450 mm long with socket. |
| 7 | b) 150 mm dia GI threaded top cap fixed in position. |
| 8 | c) 80 mm dia plug of approved make conforming to I.S. Specifications. |
| 9 | Washing and development by pumping with 30 cum per hour capacity pump for a period till sand free water comes out and the discharge is about 30 cum per hour, followed by final yield test; inclusive of all tools, plants and scaffolding and hire charge of submersible pump, generator etc. all complete. |
| 10 | Charges for mobilisation of drilling equipments, tools & plants etc and transportation of departmental materials from sub-divisional store to work site and returning excess departmental materials if any, to sub divisional store after completion of work . |
| 11 | Electrologging of bore hole of different dia tubewell for locating water bearing strata and saline aquifer, if any, after conducting relevant geophysical tests. All test reports, compiled data and raw data sheets should be submitted to the Engineer-in-Charge (Cost is inclusive for all charges for equipments, labour, data aquisition and compilation of data sheets as per direction of the Engineer-in-Charge). |
| 12 | Instalation of submersible electro motor pumping set of following capacities ....opening out of the top cap of housing pipe of the tubewell and testing of motor both in loading as well as in unloaded condition before and after installation of the same. (The rate is inclusive of hiring charges of tools & plants.) |
| 13 | DISTRIBUTION CHAMBEER AND PLATFORM: Earthwork in excavation of foundation trenches or drains in all sorts of soil (including mixed soil but excluding laterite and sand stone), including removing, spreading or stacking the spoils, within a lead of 75 m as directed.The item includes necessary trimming the sides of trenches, levelling,dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1500 mm. |
| 14 | Single brick flat soling of picked Jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. |
| 15 | Hire and labour charges for shuttering with 25 mm to 30 mm thick hard wood plank including fitting and fixing and striking out after completion of works. |
| 16 | Ordinary Cement Concrete (1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, as per relevent IS codes. With local hard blackstone varieti chips . |
| 17 | Reinforcement for reinforced concrete work in all sorts of structure including distribution bars, stirrups, binders etc. including supply of rods, initial straightening of bend bars excluding coil bars and removal of loose rust (if necessary) cutting to requisite length, hooking, bending to correct shape, placing in proper position and binding with 1.626 mm (16 SWG) black annealed wire at every inter section complete as per drawing and direction . Tor steel. |
| 18 | 65 mm thick1.2 m internal diameter R.C.C ring made with cement concrete 1:1.5:3 with stone chips and 0.80 % reinforcement (including the cost of shuttering and reinforcement ) cast at site fitted and fixed in position after proper curing true to plumb including jointing with cement motor 1: 2 complete as per direction. |
| 19 | Supplying fitting and fixing 75 mm dia PVC control valve as per approved make quality as direction by EIC. |
| 20 | Applying decorative cement based paint of approved quality after preparing the surface including scraping the same thoroughly (plastered or concrete surface) as per manufacturer's specification |
| 21 | Solar Module: Supply , transport , installątion and commissioning of ISI marked SolarModules as per following specification: 1. Cell: Indigenous mono crystalline silicon SPV cells 2. Solar Module: Monocrystalline cell with PERC technology / module with bifacial cell. 3. Standards: 1st marked as per IS 14286 and having certification of IEC 61853(1), 61730(1&2), 61710 4.ModuIes must qualify to lS 170210 (Part 1) 5.Min. Efficiency: 19.5%. 6. Fill factor: More than 75% . 7. Module wattage mismatch in the SPV array: within -t3% 8. Wattage output warranty:ShouId not be less than 90% at the end of 10 years and 80'X at the end of 25 years.9.The power output of individual PV modules used in the PV array, under STC: minimum 300 Wp. Necessary test certificates also to be supplied. For detail information please see CI. no. 2.1 of technical specification. d)For 5 HP Off-grid / On-grid Solar Water Pumping System with Monocrystalline/Monocrystalline PERC/bifacial SPV modules - 5400-5800 Wp.. d)For 5 HP Off-grid / On-grid Solar Water Pumping System with Monocrystalline/Monocrystalline PERC/bifacial SPV modules - 5400-5800 Wp. |
| 22 | Construction of 6- Module structure (RCC) 1 no as per drawing and specification , Dual axis , manual tracking , SPV module Col size(500x500) mm. foundation size-1500x1500mm ( As per Drawing) |
| 23 | Construction of 4- Module structure (RCC) 1 no as per drawing and specificationual Dual axis , manual tracking , SPV module .Col size(500x500)mm.foundation size-1250x1250 mm.( As per Drawing), |
| 24 | Module Mounting Structure ( For1 HP, 2 HP, 3 HP, 5 HP and 10 HP Solar Water Pumping System): Supply , transportation & installation of G.I manual tracking / Fixed structure made of MS hollow sections, pipes, plates, angles etc as per IS:4923, IS:1161/1239, IS:1079/2062, to hold min 300 Wp SPV Module as per drawing and technical specification. The steel structure is to be protected with minimum 80 micron gaIvanisation(hot dip) and provided with fixed arrangement or dual axis manual tracking arrangement for three times in a day and seasonal tilting to face the sun optimally.(The approximate weight of the Module Mounting Structure given in Clause no.5.1 should be followed.) |
| 25 | Power conditioning unit with IP54 enclosure:Power condltlonlng unit with enclosure :Supply , transport , installation and commissioning of Solar Power conditioning Unit consisting of following components and features:1) Variable frequency Drive with Inbuilt MPPT, voltage range suitable for operating pump-motor set of 1HP to 20 HP, detail mentioned In cl.6.12) Power Input : DC source for 1HP, 2HP and 3HP.3) Power input : AC / DC source or hybrid for SHP and above.4) Incomer: DC MCB 2 Pole 16 amp upto 5 HP, 25 amp for 7.SHP and 10 HP, 40 amp for 15 to 20 HP as per IS/IEC 60947-25) Incomer: AC MCB 4 pole 16 amp for 5.0 HP, 25 amp for 7.5HP and 10 HP, 40 amp for IS to 20 HP ar per IS/IEC 60947-16) Type II DC SPD of 40 KA.7) Type II AC SPD of 40 KA for AC/ DC or Hybrid Input.8) Dual Input (solar/Grid) 25 amp changeover switch for SHP and 7.5 HP, 40 amp for 10 HP, 63 amp for 1S to 20 HP9) Reverse protection diode 1600 VDC with heat sink.10) Data Logger.11) Remote menltoring system.12) Should have built -In EMC filters . 13)IP 65 elands for cable In and out.14) Min. IP 54 enclosure.For detail features, protections, RMS, Communicationarchitecture, Security, Data storage, tolerance of various parameters, standards to be qualified, etc. please refer to CI. 6.1 of technical qualification.Note: AC SPD, AC MCB and Selector switch to be provided only for item no. 3(f) to 3(I). d) For 5 HP capacity Pump-motor set with DC input |
| 26 | Cable and Accessories :Supplying, fitting and fixings of UV rated Copper Cable laid inside HDPE conduit and other accessories as per followings with necessary connection with the Solar PV Module, MPPT etc. For 5 HP structure. Two or more structure 9 m distance between them. i. 4.0 Sq mm single core multi studs - 26 Mtrs (Minimum)ii. Lugs, HDPE Pipe, Flexible Pipe, Saddle, Cable tie etc. |
| 27 | Earthing: Earthing with 50 mm dia GI pipe 3.64 mm thick x 3.04 Mts. long and 1 x 4 SWG GI (Hot Dip) wire (4 Mts. long), 13 mm dia x 80 mm long GI bolts, double nuts, double washers incl. S & F 15 mm dia GI pipe protection (1 Mts. long) to be filled with bitumen partly under the ground level and partly above ground level driven to an average depth of 3.65 Mts. below the ground level as below: (a) By ISI-Medium GI pipe including excavation of soil for installation of Earth Electrode and filling & ramming and connecting to individual structure to earth electrode including S&F 20 mm x 3 mm galvanised (Hot Dip) MS flat on wall/floor with GI saddles as required and connection to equipments incl. drilling holes, with bolts, nuts, washers etc. |
| 28 | a) Lighting System at Scheme: (with lighting Pole) :Dawn to dusk lighting arrangement of 4 mts height above ground level with(Hot dip) Galvanished 80 mm x 50 mm G.I. pipe with Solar Battery 12 V, 15 Ah 2 in 1 Lithium ion /Ferophospate battary within built 7-11 watt LED lamp (reputed brand- tubular type), Charge controller, 50 Wp solar panel,to cover the scheme area.The light should be warrented 5 years rom the date of installation. |
| 29 | Lightning protection (Pole mounted): Lightning protection with 3\\" X 1.5\\" G.I pipe of 6 mts height with base flange in proper RCC foundation and S & F Lightning Conductor Air Terminal made of 20 mm dia 1000 mm long GI pipe (ISI Medium) having five discharge prongs of 4 SWG GI (Hot Dip) wire at top duly soldered with 7/16 stranded GI (Hot Dip) wire and 85 mm dia 6 mm thick GI base plate at bottom incl. necessary holes etc including supply & fixing GI (Hot Dip) strips 20 mm x 3 mm thick for horizontal run on the Parapet/Roof/ Wall with GI Saddles 1100 mm apart incl. mending good the damages to building works including Earthing with 65 mm dia GI pipe (TATA-Medium)x 3.0 Mts. long and 1 x 19/10 stranded GI (Hot Dip) wire (4 Mts. long), 20 mm dia x 125 mm long galvanized bolt, double nuts, double washers including socketing at both ends of stranded GI (Hot Dip) wire by crimping sockets/ thimbles and S & F 40 mm dia GI pipe (ISI-Medium) protection (3 Mts. long) to be filled with bitumen partly under the ground level and partly above ground level to an average depth of 3.65 Mts. (Provision of one lightning protection for each scheme |
| 30 | 5 HP 3 phase AC Pump-Motor set having discharge at required head as below:- iii) Submersible Pump-motor set for LDTW with external part made of stainless steel of grade 304 or higher as per I5 6911 and IS 3444,with discharge of 7.5 Lps- 5.83 Lps at 30 mts.- 35 mts. total head with cable (3m), cover plate, Socket, Flanged Nipple, Rubber Insertion,Nuts& bolts and all other accessories including transportation of Bend, Column Pipes, cable, Set sluise valve, lay flat hose pipe etc. from Deptt. Store to site within t00km. The pump motor should be tested as per IS 8034:2048(third revision) |
| 31 | Testing and commissioning of scheme after completion of all work |
| 32 | Comprehensive maintenance charges for 4 years beyond 1 year warranty period (which cover monthly inspection, Yearly training to WUA, to attend breakdown within 3 days and to keep the scheme in operation without lapse of time) c) For 5HP both for Submersible & Surface pump. Note: Total comprehensive maintenance charge is to be withheld in addition to Securirty Deposit . Security Deposit will be released after expiry of warranty period of 1 year & Comprehensive maintenance charges will be released @ iii) Rs. 0.75 for 5 HP Submersible & Surface per Wp per year at the end of each maintenance period i.e. at the end of 2nd year, 3rd year, 4th year, 5th year. In case the “Bidder” does not provide service during the warranty & comprehensive maintenance period, the amount so held up will be forfeited |
| 33 | Insurance @ 2% to be of item no-21,25,28,30/d(iii) for a periods of five years I,e Solar Panel, Pump motor, Pump Controller,Dawn to dusk light(.Note:2Ist year’s Insurance charge Is to be paid on production of Original Receipt of premium payment. Remaining 4 years Insurance payment is to be withheld which will be released during 2nd, 3rd , 4th & Sth year on production of Original Receipt of premium payment.) |
| 34 | Remote monitoring for 5 years: Provision for remote monitoring for the pumps must be made in the pump controller through an integral arrangement having following basic functions:a. Controller must be assigned with a unique serial number and its live status must be observed remotely on online portal through login credentials.b. Ltve status must indicate whether controller is ON/ OFF. The parameters i.e. the water output, water flow rate, in fault condition, array input voltage/ current, power and motor frequency should at logged at an interval of 10 minutes c. Controller must have a back up to store the data locally ( at least for 1 year) supply & installation of GSM/GPRS based Data Transmitter or Modem and to provide remote monitoring service to transmit the parameters to central server from the solar pumping system with time stamp at user-defined interval and report generation at the buyer end. (Refer Technical Spec.) |
| 35 | Cleaning and washing of modules once in a month with clear water to remove deposited dust and dirt on the module surface and keep the modules clean throughout the year. The activity to be performed for eight months in a year excluding four monsoon months. A log book should be maintained at thr site for the said purpose. |
| 36 | Supplying, fitting and fixing including transportation of sign board for identifying the exact location of MINI RLI scheme (one at road side and other at site) the board will be made 3 mm thick MS plate of size 300 mm x 600 mm and fitted and fixed on 50 mm GI Pipe of IS 1239/90 (part-1) including cutting, welding LS and writting of both sides of Sign board. Base - Yellow, and words - Red. Both bottom end of the stands pipe will be grouted in 1:2:4 CC on a single brick flat soling. This will include one materials and labour complete as per drawing and direction of E.I.C. |
| 37 | MATERIALS : PVC PIPES & SCREEN (RIBBED) PIPES: PVC pipes of nominal dia 100 mm , wall thickness 5.0 mm , conforming to IS : 12818/1997 (medium casing) . |
| 38 | 150 mm nominal dia 7.5 mm wall thick PVC Casing (medium casing) pipes as per IS : 12818/1997 . |
| 39 | PVC Screen (Ribbed) Pipes of nominal dia 100 mm (O.D. 117 mm) , wall thickness 5.0 mm, conforming to IS : 12818/1997 . |
| 40 | PVC socket of size 150 mm x 100 mm as per IS 12818. |
| 41 | Column pipe : 80 mm dia GI (medium quality) pipe including necessary socket with ISI mark. TATA make |
| 42 | ELECTRICAL ACCESSORIES ( Pump motor , Pump controller etc are included in the component of Solar pumping system) : 3 Core 2.5 sqmm Flat Weather Proof Copper PVC insulated heavy cable as per IS Specification (Brimsin or of any other reputed brand as per direction of EIC). |
| 43 | OTHER ACCESSORIES: Supppying, fitting and fixing of 80 mm NB heavy duty Supporting Clamps intwo halves made of MS flats for holding 80 mm NB ColumnPipes, thickness of the clamp 10 mm, width of the clamp 75 mm, extended lengthof the arm 150 mm, space between adjacent holes in either side of the extendedarm 75 mm, equally spaced from the centre line of the arm, dia of bolt 16 mm.The gap between arms of clamp and pipe assembly beforetightening should bebetween 6 mm to 10 mm. Two nos. of bolt of 16 mm size shall be provided oneither side of the clamp, in other words there will be all together 2 rows of boltwith the provisions of 4 nos. of bolt with nuts and with spring and flat washer.nos. of bolt with nuts and with spring and flat washe |
| 44 | Supplying 80 mm dia Supply of galvanised iron socket with I.S.I. mark. |
| 45 | Supplying 80 mm dia GI plain bend with ISI mark. |
| 46 | Supplying, fitting & fixing of M.S. plate of size 20 cm x 20 cm,thickness 6 mm, make of two halves (20cm x 10 cm), placed over Housing Pipe of LDTW to rest the supporting clamps, with semi circular hole of 90 mm dia. at centre including locking arrangement between the two halves on both sides, including fitting, fixing of 25 mm dia. G.I. bend by making a hole on plate for passing submersible cable smoothly and complete in all respect. |
| 47 | Supply of lay flat hose of 75 mm nominal size polyster reinforced lay flat hose ( the hose should have wall thickness 1.3 mm workimg pressure 3.0 kg/sqm & brusting pressure 9 kg /sq m. The lay flat hose should have a standard length od 100 m roll. |
| 48 | G. S. T. @ 18% on only for item no-1 to 36 |
| 49 | Add Labour well fare Cess @1% of item no-1 to 36 + GST Please Enable Macros to View BoQ information |