| 1 | Picking up and removing old bituminous layer or sand sealing coat from old black topped surface and cleaning the exposed surface by scraping and stacking the material as directed. (a) By manual means : (i) From 25 mm to 50 mm thick. , Ref - PWD (Rds & Brdgs)-2018, It. No. 18.02 Page No.331 |
| 2 | Box cutting or filling in Road embankment in all sorts of soil including spreading the spoils properly over the flank as necessary or on berm to approximate grade & camber and rolling the sub-grade with power roller to proper camber and grade as per direction and satisfaction of Engineer-in-charge including uprooting and removing plants and jungles when and where necessary. (a) Depth up to 150 mm. , Ref - PWD (Rds & Brdgs)-2018, It. No. 3.16 Page No.240 |
| 3 | Water Bound Macadam Sub Base by consolidating Jhama metal / Laterite chelly or stone metal / shingles of specific size in hard crust to requisite thickness (measured after compaction) in layers including screening of metals etc. as necessary, hand packing, sweeping, watering and rolling in stages with power roller to proper line, grade and camber, lighting, guarding & barricading and making necessary earthen bundh of one metre width on each side where necessary to protect edges and preparing the bed by necessary cutting or filling and rolling all complete including the cost of all materials and hire and labour charges of all men and machineries and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (i) For Construction of Sub Base by consolidating Jhama metal / Laterite (63 mm to 45 mm) (Moorum replaced with course sand) , Ref - PWD (Rds & Brdgs)-2018, It. No. 4.10(i) Page No.247 & page-222 sl. No- 1 & 5 (e) |
| 4 | Providing and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming to IS: 8887-1978 on the prepared surface cleaned with Hydraulic broom, moistening the surface including cost and carriage of emulsion, hire charges of machinery and labour, cost of fuel and lubricants all complete as per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (ii) On Granular surfaces treated with primer. (Using Bitumen emulsion at the rate of 0.25 to 0.30 kg per sqm.) , Ref - PWD (Rds & Brdgs)-2018, Page No.213 (Table No.3.3–1) & Page No. 251, It. No. 5.02, Table no.I-2 of pg-219, pg-220 Format-B, PWD(R&B) 2018, pg-228 item-1.03 (i), Pg-230,Table-I, It-4, |
| 5 | Taking out stone slab of kerb & channel of road side drain and stacking as directed. b) flat channel stone. , Ref - Rate based on PWD Current SOR. [PWD(B)2017,p-303] |
| 6 | Taking out stone slab of kerb & channel of road side drain and stacking as directed. a) vertical kerb stone. , Ref - Rate based on PWD Current SOR. [PWD(B)2017,p-303] |
| 7 | Resetting of Stone Slabs of kerb & channel of road side drain to correct line and level including cement pointing (1:2). a) Vertical Kerb , Ref - Rate based on PWD Current SOR. [PWD(B) 2017, p-303 & 3rd corri. Addea dtd-04.06.2018. P-52 ] |
| 8 | Resetting of Stone Slabs of kerb & channel of road side drain to correct line and level including cement pointing (1:2). b) flat channel stone. , Ref - Rate based on PWD Current SOR. [PWD(B) 2017, p-303 & 3rd corri. Addea dtd-04.06.2018. P-52 ] |
| 9 | Tack Coat: Providing and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming to IS:8887-1978 on the prepared surface cleaned with Hydraulic broom, moistening the surface including cost and carriage of emulsion, hire charges of machinery and labour,cost of fuel and lubricants all complete as per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (i) On Bituminous Surface (Using Bitumen Emulsion at the rate of 0.20 to 0.30 kg per sqm.) , Ref - Rate as per PWD(WB) schedule of rates 2018 (Roads & Bridge Work), page-213(table-3.3-1) & 251 (item-5.02) |
| 10 | Cement concrete with graded jhama khoa (30 mm size) excluding shuttering In ground floor and foundation. (a) 1:3:6 proportion , Ref - PWD (Bldg.)-2017, It. No. 1, Page No.23 & 3rd Corrigenda Addenda dtd-04.06.18, P-9 & 10 |
| 11 | Raising gully pit cover and frame with CBW (1:4), 250 mm thick up to 100mm high with 20mm thick sand and cement plaster with neat cement after dismantiling the existing setting and taking out and refixing the existing cover and frame with cement concrete (1:1.5:3) with stone chips all round the frame surface including removal of surplus spoils. , Ref - Rate based on PWD Current SOR, PWD(R&B) 2018, p-233 (it -2.05), p-332(it-18.06), p-222 sl-5(a), p-332 (it -18.05)), pg-227, I-1.03, pg-230,Table-I , Table III-2 pg-226, PWD(B) 2017 , p-189 (it -1) and 3rd corria. & Adda., p-49&50, Date 04.06.2018, p-192 (it -15), p-26 (it -10(i)), consumption chart pg-B-60, sl-3 and Annex-II , Format-A & 3rd Corr. & adda. dtd-04.06.2018, p-303 , p-191 (i -6)and 3rd Corr. & Adda, page-52, p-303, p-269 (it -1) and 1st Corria & Adda, Page-4, Date 08.01.2018, page-12 (item -13) |
| 12 | Raising manhole cover and frame with CBW (1:4), 250mm thick up to 100mm high with 20mm thick sand and cement plaster including finishing with neat cement after cutting the asphaltum pavement and taking out and re-fixing the existing manhole cover and frame with cement concrete (1:1.5:3) with stone chips all round the frame surface including removal of surplus spoils. , Ref - Rate based on PWD Current SOR, PWD(R&B) 2018, p-233 (it -2.05), p-332(it-18.06), p-222 sl-5(a), p-332 (it -18.05)), pg-227, I-1.03, pg-230,Table-I , Table III-2 pg-226, PWD(B) 2017 , p-189 (it -1) and 3rd corria. & Adda., p-49&50, Date 04.06.2018, p-192 (it -15), p-26 (it -10(i)), consumption chart pg-B-60, sl-3 and Annex-II , Format-A & 3rd Corr. & adda. dtd-04.06.2018, p-303 , p-191 (i -6)and 3rd Corr. & Adda, page-52, p-303, p-269 (it -1) and 1st Corria & Adda, Page-4, Date 08.01.2018, page-12 (item -13) |
| 13 | SANITARY AND DRAINAGE WORKS (B)-(IV)INSPECTION PIT,SEPTIC TANK,SOAK PIT ETC.8.Supplying, fitting and fixing in position reinforced cement polymer concrete manhole /gully pit cover with matching frame.As per I.S-12592(M.D) (viii) 5 MT load bearing capacity gully pit cover with frame and hinge arrangement for opening of size (viii) 5 MT load bearing capacity gully pit cover with frame and hinge arrangement for opening of size Cover: 470 mm X 420 mm X 80 mm Frame: 590 mm X 550 mm X 170 mm opening: 380mm x 305mm Weight: 100 kg (approx) , Ref - PWD.SANITARY AND PLUMBING 2017 92-B.B.IV.8(viii) |
| 14 | SANITARY AND DRAINAGE WORKS (B)-(IV)INSPECTION PIT,SEPTIC TANK,SOAK PIT ETC.8.Supplying, fitting and fixing in position reinforced cement polymer concrete manhole /gully pit cover with matching frame.As per I.S-12592(M.D) (iii) 20 MT load bearing capacity round manhole cover provided with two lifter hooks fitted with matching frame of size Cover: 600 mm X 75 mm Frame: 750 mm X 150 mm opening: 525mm Weight: 170 kg (approx) , Ref - PWD.SANITARY AND PLUMBING 2017 |
| 15 | Transportation and laying 40 mm thick hot asphaltum mixture from kmc plant to the work site including rolling but excluding the cost of tack coat (covered area- 1250 square meter per 100 mt hot-mixture) a) without paver finisher i) Night Time , Ref - As per KMC Rates, taxes, fees & Charges for the year 2019-2020, As per present market Price, Rate appvd. By D.G.(Civil) Circular No-21 of 2016-17 dtd-25.10.16 vide resolution MIC meeting (Item no-M-29.22 dtd-21.09.16), Mpl. Secretary Circullar no-02 of 2018-19 dtd.04.04.2018 |
| 16 | Transportation and laying 40 mm thick hot asphaltum mixture from kmc plant to the work site including rolling but excluding the cost of tack coat (covered area- 1250 square meter per 100 mt hot-mixture) a) without paver finisher i) Day Time , Ref - As per KMC Rates, taxes, fees & Charges for the year 2019-2020, As per present market Price, Rate appvd. By D.G.(Civil) Circular No-21 of 2016-17 dtd-25.10.16 vide resolution MIC meeting (Item no-M-29.22 dtd-21.09.16), Mpl. Secretary Circullar no-02 of 2018-19 dtd.04.04.2018 |
| 17 | Liquid Seal Coat (Type A) : Providing and laying Liquid Seal Coat (Type A) with approved quality stone chips and bitumen binder on thoroughly cleaned black top surface, spreading screened & cleaned stone aggregates (100 % passing through 11.2 mm sieve and retained on 2.36 mm sieve) uniformly @ 0.09 m3 of dry aggregate per 10 m2 of area using suitable means, brushing the chips, if necessary, to ensure uniformity, followed by rolling with power roller including the cost and carriage of binder and stone chips, cost of heating the binder and all other incidental charges, cost of fuel and lubricants, including hire charges of machineries, tools & plants required for construction and quality control complete as per Clause 511 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (ii) With Cationic Bitumen Emulsion (@ 15.00 kg / 10 sqm.) , Ref - Ref. - Item No. - 5.13(A)(II), P-258 of P.W(R)D Schedule 2018, Format-B, P-220 of P.W(R)D Schedule 2018, TABLE No. T-1, Item no.- 4/A, P-230 of P.W(R)D Schedule 2018, TABLE III- 2, ROW-16, P-226 of P.W(R)D Schedule 2018, Ref-TABLE No. T-1, Item no.-3/A, P-230 of P.W(R)D Schedule 2018, 1.03 A (C), P-227 of P.W(R)D Schedule 2018, TABLE No. T-1, Item no.- 3/A, P-230 of P.W(R)D Schedule 2018) |
| 18 | (b) Priming one coat on timber or plastered surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc. , Ref - PWD (Bldg.)-2017, It. No. 1, Page No. 200 |
| 19 | Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary : (a) On timber or plastered surface : (iv) Two coats (with any shade except white) , Ref - PWD (Bldg.)-2017, It. No. 2, Page No. 200 |
| 20 | Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary : (a) On timber or plastered surface : (ii) Two coats (white in shade) , Ref - PWD (Bldg.)-2017, It. No. 2, Page No. 200 |
| 21 | Sub Total |
| 22 | GST 18% |
| 23 | CESS 1% Please Enable Macros to View BoQ information |