| 1 | item discription |
| 2 | (1) 40HP motor Super enameled Copper wire |
| 3 | F' class insulating materials, dr. Beck, varnish etc. (15% of S.E. Copper wire) |
| 4 | Flexible glass leads for terminal connection |
| 5 | Soldering like soldering stick |
| 6 | Decarbonising, cleaning, varnish, nut, bolt |
| 7 | Mechanical job: both side shaft as per bearing size housing sleeve changing. |
| 8 | Both side housing bearing welding, machining as pe bearing size. |
| 9 | Rotor shaft rebuilding as per proper size |
| 10 | Bar bleazing by Rupto bar |
| 11 | Dismantling, refitting charges of motor |
| 12 | Motor rewinding charges (15% of S.E. Copper wire) |
| 13 | (2)40HP motor Super enameled Copper wire |
| 14 | F' class insulating materials, dr. Beck, varnish etc. (15% of S.E. Copper wire) |
| 15 | Flexible glass leads for terminal connection |
| 16 | Soldering like soldering stick |
| 17 | Decarbonising, cleaning, varnish, nut, bolt |
| 18 | Motor shaft broken opening by hydraulic jack |
| 19 | Supply of new Metal shaft (EN-24) |
| 20 | Mechanical job: both side shaft as per bearing size housing sleeve changing. |
| 21 | Both side housing bearing welding, machining as per bearing size. |
| 22 | Rotor shaft rebuilding as per proper size |
| 23 | Bar bleazing by Rupto bar |
| 24 | Dismantling, refitting charges of motor |
| 25 | Motor rewinding charges (15% of S.E. |
| 26 | (A) ABC make Drill Panel Complete rewinding of transformer coil with super enameled copper wire & good insulation materials after deduction of scrap value. |
| 27 | Supply & fixing of terminal with insulator |
| 28 | Supply & fixing of contactor Unit |
| 29 | Supply & fixing of Thermal overload. |
| 30 | Supply & fixing of Earth leakage relay |
| 31 | Supply & fixing of fuse with carrier |
| 32 | Supply & fixing of 12 Point connector, |
| 33 | Supply & fixing of wiring wire |
| 34 | Supply & fixing of Isolator |
| 35 | reparing cost |
| 36 | (B) Technogeneous make Drill panel Complete rewinding of transformer coil with super enameled copper wire & good insulation materials after deduction of scrap value. |
| 37 | Supply & fixing of terminal with insulator |
| 38 | Supply & fixing of contactor Unit |
| 39 | Supply & fixing of Thermal overload |
| 40 | Supply & fixing of Earth leakage relay |
| 41 | Supply & fixing of lamp holder |
| 42 | Supply & fixing of wiring wire |
| 43 | Supply & fixing of Isolator |
| 44 | Repairing Cost |
| 45 | Complete rewinding and repairing of NGF Make 720 RPM 550 V Slipring type S.E. Copper wire |
| 46 | F' class insulating materials (15% of S.E.Copper wire) |
| 47 | Cost of flexible glass lead for terminal |
| 48 | Soldering materials for connection. |
| 49 | Labour for rewinding of starter (15% of S.E.Copper wire) |
| 50 | Dismantling and refitting motor |
| 51 | Mechanical repairing of both side shaft as per bearing size |
| 52 | Taking out bearing, repairing of bearing portion |
| 53 | Dismantling and removing of old copper |
| 54 | Supply of copper strip |
| 55 | F class insulating materials (15% of S.E.Copper wire) |
| 56 | Insertion of copper wire into rotor |
| 57 | Soldering materials |
| 58 | Labour cost for assembling & fitting |
| 59 | Repairing of slip ring by copper brass |
| 60 | Supply and fixing of joint make with MS |
| 61 | Transporting, Loading, Unloading Charges |
| 62 | Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information |