| 1 | Safe Carriage of Following Material From Store to Work Site Including Safe Loading & Un Loading at Both Ends (0 to 40 KM) |
| 2 | PCC Pole 11 mtr Long |
| 3 | Earthing set complete |
| 4 | GI- wire 4/8 SWG |
| 5 | ACSR Rabbit conductor |
| 6 | Cable Box O/D 11 KV 3x70 XLPE |
| 7 | Cable Box ST.TH. 11 KV 3x70 XLPE |
| 8 | Cable HT XLPE 11 KV 3x70 sqmm. |
| 9 | Stay set 16x1800 |
| 10 | Stay wire GI (7/4 mm) 7/8 SWG |
| 11 | 11 KV Polymeric pin insulator |
| 12 | 11 KV Polymeric disc insulator |
| 13 | 11 KV V-Type cross arm 65x65x6 mm |
| 14 | Disc fitting 45KN (T&C) |
| 15 | MS Angle 65x65x6 mm |
| 16 | MS Channel 100x65 mm |
| 17 | Errection of Single Support of PCC Pole 11 Mtr Long and fixing all accessories as per norms (Nut, bolts and clamps will be provided by contractor) |
| 18 | Errection of Double Pole Structure of PCC Pole 11 Mtr Long and fixing all accessories as per norms (Nut, bolts and clamps will be provided by contractor) |
| 19 | Providing and Fixing of Danger board with clamp. |
| 20 | Providing and Fixing of Number place with clamp. |
| 21 | Laying of ACSR Rabbit Condouctor |
| 22 | Febrication of MS channel/angle |
| 23 | Providing and fixing of G.I. barbed wire 13 mm pitch fixed at pole both ends. |
| 24 | Filling of Cable Box O/D 11 KV 3x70 XLPE |
| 25 | Filling of Cable Box ST.TH. 11 KV 3x70 XLPE |
| 26 | Guarding of 11 KV Line with (Holding clamp with bolts and nut, EYE bolt will be bprovided by contractor) |
| 27 | Errection of earthing complete (Fixing All Accessories As Per Norms) |
| 28 | Errection of stay complete and Grouting of stay rods including all work of excavation, cement concreet in size .60x.60x.30mm in ration 1:4:4 (Cement, sand, 40mm brick ballast) as per drg. including back filling & proper ramming etc. with fixing tightening & nuzzling of stay set with the pole (all material provided by contractor). |
| 29 | Concreting of PCC pole including all work of excavation, cement concreet in size .60x.60x.30mm in ration 1:4:8 (Cement, sand, 40mm brick ballast) as per drg. Including. |
| 30 | Laying of HDPE pipe through HDD trenchless machine (HDPE pile 6\\" dai will be provided by contractor) |
| 31 | Laying of Cable HT XLPE 11 KV 3x70 sqmm through HDPE pipe |
| 32 | Laying of Cable HT XLPE 11 KV 3x70 sqmm in air |
| 33 | Providing & fixing G.I. pipe 6\\" dia |
| 34 | Dismentiling of following materials and carrage of materials from site to JE Store inculding safe loading and unloading at both ends as per site condition - |
| 35 | Steel Scrap RS Joist |
| 36 | Alluminium Scrap |
| 37 | Steel Scrap Round Pole Please Enable Macros to View BoQ information |