| 1 | Design of 110KV double circuit overhead lines towers, foundation , survey of line route, preparation of plan and profile drawings as per clause no.1 of specification. |
| 2 | Supply, installation, testing and commissioning of High Tension Steel hot dipped galvanised 110KV tower with hanger & other tower steel parts along with all required GI hardwares such as GI nuts and bolts, step bolts and spring washers including inspection of existing 110 KV towers as per clause No. 2 of specification. |
| 3 | Only Installation of Polymer Silicon Rubber Insulator String complete along with required galvanised hardware fittings and conductor accessories like strain clamp with U bolts complete suitable to ACSR Panther conductor with all required material such as nut and bolts, washers etc. of following types including removal of old insulator string with hardware fitting as per clause No. 3 of specification |
| 4 | Double Strain Polymer Silicon Rubber Insulator String |
| 5 | Single Suspension Polymer Silicon Rubber Insulator String |
| 6 | SITC of Hardware Insulator for Polymer Silicon Rubber Insulator String as per Clause no. 4 of specification |
| 7 | Double Suspension |
| 8 | Single Suspension |
| 9 | SITC of ACSR Panther Conductor as per clause No.5 of specification |
| 10 | Only Installation of ACSR Panther Conductor as per clause No.6 of specification |
| 11 | Only Installation of 7/3.66 mm high tension galvanised steel (HTGS) shielding wire including dismantling of old rusted guard wire as per clause No. 7 of specification |
| 12 | SITC of Suspension Clamp with nut, bolts and washer etc. suitable to 7/3.66 mm high tension shielding wire (HTGS) on existing 110 KV tower as per clause No. 8 of specification |
| 13 | SITC of GI Pipe Electrode earthing along with GI wire for grounding of 110 KV existing towers including all required Pad connectors, GI nuts & bolts, washers complete connected to tower legs, removal of material, back filling of metal, etc as per clause No. 9 of specification |
| 14 | Supply and Installation of Anti climbing device (ACD) with barbed wires on 110KV tower with required fixing angles, GI nuts & bolts and washers including dismantling of rusted anti climbing device etc. as per clause No. 10 of specification |
| 15 | Supply and Installation of 110 KV Tower Accessories e.g. Phase plates, Danger board, Line Name plate & Tower Number plate along with all required hardware, GI nuts & bolts and washers etc. including removal of old rusted accessories etc. as per clause No. 11 of specification |
| 16 | Removal of wild vegetation of approach pathway and Right of way of existing 110 KV lines as per clause No. 12 of specification |
| 17 | Protective coating to 110KV existing tower footing members with 2 coats of bituminous black paint as per clause No. 13 of specification |
| 18 | Dismantling of old existing towers. Transportation of all removed components of lines including dismantling of existing towers (7 Nos., which includes 5 no. of 110KV towers and 02 Nos. of 22KV towers) from Hill to Trombay village within BARC premises (approx. 5 kms) as per clause No. 14 of specification |
| 19 | Excavation of earth as per clause No.15 of specification. |
| 20 | Soft soil |
| 21 | Murram/Asphalt road |
| 22 | Hard rock/Concrete |
| 23 | Metal filling. Supply and Installation of metal of 20 mm size as per clause no 16 of specification. |
| 24 | Rubble stone hard core. Supplying, Stacking and Laying of 230 mm Thick Soling stones as per clause No 17 of specification. |
| 25 | P.C.C. Providing and laying in position Reinforced Cement concrete( RCC) as per clause No 19 of specification. |
| 26 | R.C.C. Providing and laying in position Reinforced Cement concrete( RCC) as per clause No 19 of specification. |
| 27 | Reinforcement with HYSD bars. Providing Reinforcement for reinforced cement concrete as per clause No 20 of specification. |
| 28 | Centring and shuttering. Providing, cantering, shuttering Form work as per clause No 21 of specification. |
| 29 | Murrum filling. Excavation, Transport & Filling charges for Murum Filling of specified thick as per clause No 22 of specification. |
| 30 | Only installation of Dampers. Only installation, of dampers suitable to ACSR panther conductor of 110KV double circuit overhead lines as per clause no. 23 of specification. |
| 31 | Random Rubble Masonry. Rebitment work required around the towers as per clause no. 24 of specification. |
| 32 | OPGW 24 Core and accessories. Supply, installation, testing and commissioning of 24Core OPGW as per clause no 25 of specification. |
| 33 | SITC of Aviation Light (Low Intensity). SITC of Low Intensity Aviation Light as per Clause 26 of the specification. |
| 34 | SITC of Single Suspension Polymer Silicon Rubber Insulator string complete along with required galvanised hardware fittings and conductor accessories like suspension clamp with U bolts complete suitable to ACSR Panther conductor with all required material such as nut and bolts, washers etc. of following types including removal of old insulator string with hardware fitting as per clause No. 27 of specification Please Enable Macros to View BoQ information |