| 1 | Dismantiling of Existing Damaged RCC Roof Slab including machineries and Labour Charges etc complete., |
| 2 | Supply and delivery of Centrifugal Monoblockmotor with Pumpset 200Lpm x 50m head 5HP with ISI mark as per IS 8034 including cost and conveyance of Materials at site etc., Completed. |
| 3 | Supply and Fixing of 5HP Suitable for Centifugal Monomotor Three phase panel board DOL Starter with single phasing preventor with ammeter conforming to IS 13947 with auto restart facility including cost and conveyance of Materials at site etc., Completed. |
| 4 | Supply and Fixing of 4.00sq.mm PVC Insulated and sheated 3 core flat copper cable confirming to IS 694/1990 including cost and conveyance of Materals at site etc., Completed. |
| 5 | Supply and delivery of following GI Pipes (Medium) B Class with Specials with ISI mark including cost and conveyance of all materials etc., complete complying with standard specification. 100mm Dia GI Pipe |
| 6 | 100mm Dia GI Bend |
| 7 | 100mm Dia GI Union |
| 8 | 100mm Dia GI Flange with Rubber Set |
| 9 | 110mm Dia PVC Pipe 6Kg |
| 10 | 110mm Dia PVC Adopter |
| 11 | 110mm Dia PVC Bend |
| 12 | Supply and fixing of following Electrical materials including cost and conveyance of all materials and labour charges etc., completed. TW Plank of size 600mmx450mmx19mm with supporting reepers of 1\\" thick on both side with painting and with bolt,nut and washer etc., completed. |
| 13 | Supply and fixing of 32amps porcelain fuse Unit (1200V) |
| 14 | 32Amps DP Switch with metal clad |
| 15 | Supply and run of 4 of 4 sq.mm. (56/0.3) PVC insulated sc unsheathed copper core conductor of 1100v on 7/20 GI bearer wire for service connection mains- (SD 63) |
| 16 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum |
| 17 | Plain Cement Concrete 1:4:8 (one part of cement, four part of Crushed Stone Sand (M- Sand) and eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification |
| 18 | Brick work in CM 1:5 (one cement & Five Crushed Stone Sand (M- Sand)) using II class ground moulded bricks of size 9\\" X 43/8\\"X 2 3/4\\" including finishing, curing, etc., complete complying with standard specification - 100CFT |
| 19 | Plastering with cement mortar 1:5 (One part of Cement and Five part of Plastering Sand (P- Sand)) 12mm, thick in all floors including cost and conveyance of all materilas to site and labour charges etc,complete as per standard specifications |
| 20 | Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38 |
| 21 | Suppling and fabricating and placing in position MS (or) R.T.S. bar for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors. |
| 22 | Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone Sand (M- Sand), but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - |
| 23 | Manufacturing, Supplying and Fixing of Stainless Steel Grill Work using 20mm dia Steel Rod and Allround 25*25 Box Angle The rate is inclusive of the charges for cutting, bending, welding, grinding, polishing, conveyance, electrical charges, etc. complete Please Enable Macros to View BoQ information |