| 1 | Custom Labour for transporting single pole by hired vehicle to a distance up to 5 km excluding loading & unloading charges. |
| 2 | Loading HT A type pole from the stacking place and unloading the same at work site (transport by vehicle). |
| 3 | Dismantling one damaged LT PSC/RCC pole after disconnecting stays, strut etc. and stacking the same. |
| 4 | Dismantling (without damage) one km LT 3ph 4 wire OH line, cross arms, insulators and stacking the conductors in rolls. |
| 5 | Dismantling (without damage) one km LT Sph 2 wire OH line, cross arms, insulators and stacking the conductors in rolls. |
| 6 | Dismantling (without damage) one km LT additional conductor line, cross arms, insulators and stacking the conductors in rolls. |
| 7 | Dismantling of Anchor clamp / dead end clamp for LT AB cable |
| 8 | Dismantling of suspension clamp suitable for LT AB cable |
| 9 | Dismantling of 1.1 kV Aerial bunched cable of size 3 x 70 + 1 x 16 (Street Light) + 1 x 50 Sq.mm. (Insulated Messenger) |
| 10 | Dismantling (without damage) one 11kV PSC/RCC pole after disconnecting stays, strut etc. and stacking the same. |
| 11 | Dismantling one Transformer (upto and incl. 160kVA) from existing structure to ground. |
| 12 | Dismantling transformer station in DP structure excluding the rate of dismantling earthing |
| 13 | Dismantling one section fuse |
| 14 | Dismantling one V cross arm/Channel cross arm from existing Pole, and bringing back to section store. |
| 15 | Dismantling one Channel cross arm from existing DP structure, and bringing back to section store. |
| 16 | Fitting and erecting one HT PSC Pole in position incl. fitting cross arm, digging & back filling pit, drawing earth leads. |
| 17 | Fitting and erecting one HT A type Pole in position incl. fitting cross arm, digging & back filling pit, drawing earth leads. |
| 18 | Fitting 6 channel cross arms, AB switch, DO fuse, LA, HT & LT connections on existing DP, 3 LT fuses. |
| 19 | Fitting one Additional V cross arm in existing single pole incl. conveyance of materials. |
| 20 | Fitting one Additional 75x40mm, 1.8m Channel cross arm in existing single pole incl. conveyance of materials. |
| 21 | Fitting one Additional 2.4m Channel cross arm in existing single pole incl. conveyance of materials. |
| 22 | Stringing of one km 3 PH 11kV line with XLPE Insulated ACSR Raccoon |
| 23 | Additional rate for providing one disc set on any type of HT pole for making cut point. |
| 24 | Erection of Anchor clamp / dead end clamp for LT ABC of any size |
| 25 | Erection of suspension clamp for LT ABC of any size |
| 26 | Stringing of 1.1 kV Aerial bunched cable of size 3 x 70 + 1 x 16+1x 50 sqmm with bare/insulated Messenger through existing poles |
| 27 | Stringing one km LT Sph 2 wire line (Rabbit) incl. fitting cross arm etc. removing touchings and conveyance of materials. |
| 28 | Stringing one km LT Sph 3 wire line (Rabbit for Ph&N, Weasel for St.main) incl. fitting cross arm etc. removing touchings and conveyance of materials. |
| 29 | Stringing one km LT 3ph 4 wire line (Rabbit for Ph, Weasel for N) incl. fitting cross arm etc. removing touchings and conveyance of materials. |
| 30 | Stringing one km LT 3ph 5 wire line (Rabbit for Ph and Weasel for N&St.main) incl. fitting cross arm etc. removing touchings and conveyance of materials. |
| 31 | Fitting and providing one Strut using HT PSC pole incl. digging & back filling pit. |
| 32 | Fitting and providing one HT Stay for 11kV pole incl. digging & back filling pit. |
| 33 | Dismantling (without damage) one km 11kV line (3 conductors), cross arm, insulators, disc, rolling the conductor and stacking. |
| 34 | Fitting one Additional 2.4m/3m Channel cross arm (75x40x6mm), in existing 11kV DP incl. conveyance of materials. |
| 35 | Additional rate for refitting/redoing one Disc set while renewing any type of 11kV cut pole |
| 36 | Providing concrete muffing (0.45x0.45x1.5m) inclusive of cost of all material (as per specification). |
| 37 | Erecting one 100kVA Transformer to existing DP and giving connections, incl. loading & unloading, excluding transportation. |
| 38 | Providing one Driven Earth using GI earth pipe at standard distance away from the pole/structure in loose soil. |
| 39 | Doing one cable end termination on cables of sizes beyond 3x185 sqmm and upto and incl. 3x300 sq mm using the cable jointing kit supplied departmentally. |
| 40 | Laying 11kV 3x300sqmm. XLPE UG cable by HDD method along/across roads, supplying,pulling 110 mm HDPE/GI pipe duct, drawing 11kV cable through the duct including surveying site with modern sensing equipment, restoring the damages to the satisfaction of the road owner,loading the cable from yard and transporting the cable using contractor\"s vehicle and unloading the same at work site complete except the cost of 11kV XLPEUGCable. ( laying of UG cable as per the standard described in the detailed description ) |
| 41 | Mounting the cable ends of all sizes upto and incl. 3x300 sq mm with special type cable clamps incl. cost of extra materials if needed and giving necessary connections. |
| 42 | Fitting one set AB switch and giving connection |
| 43 | Drilling hole of various sizes on existing Channel/Cross Arm. |
| 44 | Fitting and erecting one HT DP using A type pole in position incl. fitting 2 channel cross arms, digging & back filling pit, drawing earth leads. |
| 45 | Fitting one Additional 2.4m/3m Channel cross arm (100x50x6mm), in existing 11kV DP incl. conveyance of materials. |
| 46 | Providing one Earth using earth pipe incl. digging separate pit at standard distance away from the pole/structure & backfilling. |
| 47 | Providing one Earth using earth pipe incl. digging & backfilling pit and supply of charcoal, salt, sand etc. Please Enable Macros to View BoQ information |