| 1 | Earth Work in exavation & foundation in ordinary soil (loam clay or sand) including lift up to 1.50 Mtrs. (5ft) and lead up to 30 Mtrs.m (100ft) and including filling, watering & ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of suplus earth as direction by the Engineer-in-charge up to a distance of 30 Mtrs. (100ft) from the foundation trenches. (S.I. no. 251) |
| 2 | Earth work in cutting or Filling in ordinary soil including all labour etc comp. (S.I. No. 253) |
| 3 | Cartage of earth including supply of all labour T&P etc. required for proper completion of works as per direction of engineer in charge. |
| 4 | Cement concrete with 4 cm gauge approved stone ballast, approved coarse sand, cement in the proportion 8:4:1 including supply of all materials, labour and tools and plants etc. required for proper completion of the work. |
| 5 | RCC work with cement approved coarse sand and 2cm (3/4’’) gauge approved stone ballast in the proportion 1:1½:3 in lintels of door and windows, excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.I. wire and including necessary cantering and suttering etc and also including supply of all materials, labour and tool and plnats etc.required for proper completion of the work binding wire to be supplied by the contactor free of coast. |
| 6 | Mild srteel of iron in plain work such as reinforced concrete/ brick work (when not included in over all rates) wrought to required shape as necessary of the work and including supply of steel, its wastage and hooks and authorized over lapping shall be measured. |
| 7 | Random course Rubble massonary in 1:4 cement and fine mortar in foundation and plinth, including supply of all materials, labour & T&P etc. required for proper completion of the work. |
| 8 | Class-150 brick work in 1:4 cement and fine sand of 1.25 fineness modulus mortar fine foundation and plinth including supply of all materials, labour and T& P comp. etc. Required for proper completion of the work. In superstructure walls of one brick thick (S.I. no 305+309) |
| 9 | 12 mm thick plaster with cement work 1:4 over brick work minimum thickness not less than 3/8\" (10mm) thick including supply of all material, labour and T&P etc. required for proper completion of the work. (Sl. No. 579) |
| 10 | Cement concrete with 2 cm gauge approved stone ballast, approved coarse sand, cement in the proportion 3:1½:1 including supply of all materials, labour and tools and plants etc. required for proper completion of the work. |
| 11 | Painting work with enemal paint including all material labour T&P etc. required for proper completion of the work |
| 12 | Providing and laying red sand stone with its cutting, moulding, finishing including all material labour T&P etc. required for proper completion of the work as per direction of Engineer-in-charge. |
| 13 | Excavation in foundation in ordinary soil ( Loam clay or sand) including lift up to 1.5 meter (5ft) and lead upto 30m (100ft) and including filling,watering & ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as direction by the Engineer-in-charge upto a distance of 30m(100ft) from the foundation trenches. |
| 14 | Earth work in cutting or Filling in ordinary soil including all labour etc comp. (S.I. No. 253) |
| 15 | Cartage of earth including supply of all labour T&P etc. required for proper completion of works as per direction of engineer in charge. |
| 16 | Cement concrete with 4 cm gauge approved stone ballast, approved coarse sand, cement in the proportion 8:4:1 including supply of all materials, labour and tools and plants etc. required for proper completion of the work. (As per Chap-5 S.I. No. 281) |
| 17 | Random course Rubble massonary in 1:4 cement and fine mortar in foundation and plinth, including supply of all materials, labour & T&P etc. required for proper completion of the work. (chap-8 Add Item (b)) |
| 18 | Raised pointing with cement and fine sand of 1.25 fineness modulus mortar on brick work in proportion of 1:2 including supply of all materials, labour and tools and plants etc. required for proper completion of the work |
| 19 | Cement concrete with 2 cm gauge approved stone ballast, approved coarse sand, cement in the proportion 3:1½:1 including supply of all materials, labour and tools and plants etc. required for proper completion of the work. |
| 20 | Supply of M.S. Angle iron door, windows ventilation frame made of approved M.S. angle iron wroght to required form including drilling hole, welding and recetting where necessary and also including supply of all material, such as steel hinges of required size, nut & bolts etc. and also including all taxes, wastage and one coat of red oxide paint complete in all respect as per direction of Engineer-in-charge for proper completion of work at site of work. |
| 21 | Finishing walls with textured exterior paint of required shade : New work (Two or more coats applied @ 3.28 ltr/10 sqm) over and including priming coat of exterior primer applied @ 2.20kg/10 sqm |
| 22 | Painting or Vernishing new iron work in small areas or new wood work with two coat (up to one Sq. meter) of ready mixed priming paint and two coat of approved superior quality ready mixed paint or varnish including supply of all materials labour and tools and plants etc. required for proper completion of the work. Paint to be used should confirm the ISI no. 103-1950. |
| 23 | Construction of granular sub-base by providing well graded material (Stone Dust) 0.15 Mtrs. compacted thickness spreading in uniform layers with moter grader on prepared surface, mixing by mix in place method with rotavator at OMC and compacting with smooth wheel roller to achieve the desired density complete as per technical specification clause 401. |
| 24 | Construction of granular sub-base by providing coarse graded material spreading in uniform layers with moter grader on prepared surface, mixing by mix in place method with rotavator at OMC and compacting with svibratory roller to achieve the desired density complete as per technical specification clause 401 (place method). |
| 25 | Interlocking Concrete Block PavementProviding and laying of Rubble mouled ZigZag coloured Interlocking Concrete Block Pavements having thickness 80 mm as per drawings and Technical Specification clause 1504 |
| 26 | Supply and fixing of Inaguration BG stone including all material labour T&P etc. required for proper completion of works as per direction of Engineer-in-charge. |
| 27 | Supply and fixing of Granite Stone bences including all marerial labour T&P etc. required for proper completion the work. |
| 28 | Add 8 % on Total for electrification work |
| 29 | Add 18 % GST Please Enable Macros to View BoQ information |