| 1 | Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp. |
| 2 | Picking BT Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with a lift upto 3 m and lead upto 1000 m as per Technical Specification Clause 301.4. |
| 3 | Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A |
| 4 | Spreading the collected US gravel to watering and hand roller rolling including cost and supply of well Gravel from approved quarry and stacking to departmental gauge for premeasurements etc complete as per standard specifications and as directed by the departmental officers KM 0 / 000 - 1/000 |
| 5 | KM 1/000 - 1/830 |
| 6 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 7 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., |
| 8 | BITUMINOUS MACADAM : Providing and Laying bituminous Macadam with hot mix plant using crushed aggregates of gradign as per Table 500.4 premixed with bituminous binder, transported to site upto lead of 1000m laid over a previously prepared surface with paver finisher to the required grade , level and alignment and rolled to achieve the desired compaction as per Technical Specification |
| 9 | BITUMINOUS CONCRETE 25 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5 |
| 10 | Provision for HM ,Km Stone charges etc complete HM Stone |
| 11 | KM Stone |
| 12 | Provision for Name board, |
| 13 | Provision for Sign board, |
| 14 | Provision for Hard bed Wearing Coat Please Enable Macros to View BoQ information |