| 1 | Providing and laying dense graded bituminous macadam Grading-I with 120 TPH batch type HMP producing an avarage output of 75 tonne per hour using crused aggregates of specified grading premixed with bituminous binder @ 4.50 percent by weight of total mix and filler , transporting the hot mix to work site , layig with hydostatic paver finisher with sensor control to the required grade , level and aligmnment , rolling with smooth wheeled , vibratory and tendom roller to achieve the desired compaction as per MoRT&H Specification Clause 505 complete in all respects. (Including All Taxes, Labour cess , Royalty etc. but Excluding GST) for proper completion of Work. |
| 2 | Providing and applying tack first coat with VG.- 10 using bitumen pressure distributor at the rate of 0.20kg per sqm in the norms bituminous surface cleaned with mechanical broom. (Including All Taxes, Labour cess , Royalty etc. but Excluding GST) for proper completion of Work. |
| 3 | Providing and laying bituminous concrete with higher capacity batch type hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects. (Including All Taxes, Labour cess , Royalty etc. but Excluding GST) for proper completion of Work. |
| 4 | Providing and laying of hot applied thermo plastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area thickness of 2.5 mm is exclusive of surface applied glass bed as perIRC 35 inclduing cost of all materials, labour, Machinaries, T&P etc. requared for peoper completion of work i/c all other charges and taxes. The finishied surface to be level uniform and free from streks and holes as per MORTH specification no. 803. (Including All Taxes, Labour cess , Royalty etc. but Excluding GST) for proper completion of Work. |
| 5 | P/L hot applied thermoplastic compound 5mm thick, 300 wide and 600 mm gape including reflectorising glass @ 500 gms per sqm area, thickness of 5mm is exclusive of surface applied glass beads as per IRC:35 the finished surface to be level, uniform and free from streak and holes (Transverse Bar/Repeated Bar) (Including All Taxes, Labour cess , Royalty etc. but Excluding GST) for proper completion of Work. |
| 6 | Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2. (Cartage) (Including All Taxes, Labour cess , Royalty etc. but Excluding GST) for proper completion of Work. |
| 7 | Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2. (Including All Taxes, Labour cess , Royalty etc. but Excluding GST) for proper completion of Work. Please Enable Macros to View BoQ information |