| 1 | Item Description/ Heading |
| 2 | Making & providing of IBR socket from IBR 75mm forging bar thread cutting and complete machining |
| 3 | After getting the approve by the boiler inspector, fixing and welding by IBR welder with IBR approved electrodes |
| 4 | Providing and fixing of new fusible plug with IBR TC |
| 5 | Oxygen |
| 6 | Welding rod (IBR quality) |
| 7 | Providing all fittings of lancashire boiler related material ie tape joint, hold tight compound, nut bolt with washer, rubber joint, high pressure joint asbestos (graphite) bush, rubber conical washer for gauge glass etc |
| 8 | Supply & fitting of 20\" long 3/7 dia gauge glass tube |
| 9 | Fabrication of gauge column cock extended pipeline with all required materials (08 nos of IBR quality flange 4\", IBR quality seamless pipe 1\" x 2m length) |
| 10 | Removing of damaged/defective fusible plug with damaged socket by gas cutting, removing the same |
| 11 | Boiler all mounting, valve repairing overrolling & ready for inspection with all consumables & labour charges |
| 12 | Fabrication & refitting of fire bar for both side of furnace of lancashire boiler |
| 13 | Replacement and refitting of manhole studs 40mm dia & 225m length |
| 14 | Arrange of hydraulic test inspection by boiler inspector approved |
| 15 | Arrange of boiler steam test as per Reg. 380 of IBR rules |
| 16 | After approval complete fitting, commissioning the above boiler ready for steaming position with all consumable material & labour |
| 17 | Repairing isolated pitting new thickness different shell stacks 6 oclock and 7 oclock 04 nos position build up properly by welding which are marked by boiler inspector |
| 18 | Repairing of bottom shell water side suggested by boiler inspector 02 nos at 2nd strake area |
| 19 | Transportation 02 times boiler inspector visit and 03 times materials shifting |
| 20 | Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information |