| 1 | Civil Work |
| 2 | Disposal of malba from the site upto 5 km cartage. (site Clearance) |
| 3 | Earthwork in excavation for structure as per drawing and technical specification Clause305.1 including setting out , construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead 50 m. dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification Clause 300 i/c all cess, labour cess, levy, toll fee, royalty, Contractor profit but excluding GST. Ref. to MORD Spec. 300 |
| 4 | Earth work in cutting or in embankment in ordinary soil excavation to be in the form of regular pits not exceeding 0.50 M. in depth and earth work in embankment to be 20 cm. layers including remming and dressing the surface to required levels and slopes and also including 1.50 M. lift and 30 M. lead. The earth from cutting to be used in making embankment or to be deposited as spoil banks with in 30 M. distance directed by the Engineer-in-charge. (Royality removed by Govt.) for small works / Abadi area. (Where machine can not move). S.I.NO. (253+261b+231a). |
| 5 | Supply and fixing of P.V.C pipes 110 mm dia. & 6 kg./Sq-cm. (ISI Marked) complete As item no. 30A (iv). 200 + 200 x 20% + 30 = 270 |
| 6 | Making house connection from distribution line to inner wall of house, with supply of G.I. pipe (Average 10.0 mtr.) including specials, Bib cock, Brass ferrule, Saddle clamp etc. of suitable size, T&P etc. including excavation, laying and jointing for proper completion of work as per instructions of Engineer-in-charge |
| 7 | 1:4:8 (1 cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources). S.I.NO. 4.1.8. |
| 8 | Plain / reinforced cement concrete (R.C.C.grade M -25) in substructure complete as per drawings and technical specification clauses 802, 804, 805, 806, 807,1202 and 1204 i/c all cess, labour cess, levy, toll fee, royalty, Contractor profit but excluding GST. |
| 9 | Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawings and technical specifications clauses 1000 and 1202 i/c all taxes, labour cess, levy, toll fee, royalty, Contractor profit but excluding GST. |
| 10 | Providing laying spreading and compacting stone aggregates of specific sizes to water bound macadam Grade - 3 specification including spreading in uniform thickness, hand packing, rolling with smooth, hand / vibratory roller 5 tonnes in stages to proper grade and camber, applying and brooming requisite type of stone screening to fill up the interstices of coarse aggregate, watering and compacting to the required density as per Technical Specification Clause 405. ( as per Analysis Rate) |
| 11 | Cement concrete with 2 cm gauge approved stone grit, coarse sand and cement in proportion of 1:1.5:3 in cc pavement (thickness as per design) cement coarse and fine aggregate conforming to IS standard mixed in concrete mixture / plant of not less then 0.2 cum capacity and appropriate weight batcher using approved mix design, laid in approved fixed from work (steel channel) laying and fixing of 125 micron thick polythene film, wedges, steel plates including levlling the form work spreading the concrete with shovels, racks, compacted using needle, screed and plate vibrators and finished in continious operation including hassion cloth for curing of concrete pavements for not less then 14 days curing compound (where as specified) and water finishing to lines & grade including supply of all materials, labour, T&P etc. required for proper completion of the work and also including complete shifting of Recron 38 fiber reinforcement material etc. & concrete etc.. S.I.NO. New item 9 / Chapter-20 |
| 12 | M.S. iron work for crossing. Please Enable Macros to View BoQ information |