| 1 | Item Description/ Heading |
| 2 | Cleaning/removal of spillage coal in UG from belt conveyor structure, loading points, tailend drum, transfer point of belt conveyor and direct loading the same on to belt conveyor. |
| 3 | Groove cutting manually by using chised/pick-axe in solid coal/stone for foundation, manhole/duggi hole /pits and excavated material to be removed and stacked separately within 50 Mtr. distance.(In Soft stone) |
| 4 | Groove cutting manually by using chised/pick-axe in solid coal/stone for foundation, manhole/duggi hole /pits and excavated material to be removed and stacked separately within 50 Mtr. distance.(In coal) |
| 5 | Carriage of materials by maual labour including loading, unloading and stacking for lead less than 0.50 Km. (Cost for Ist 50 Mtr.) For Lime : |
| 6 | Carriage of materials by maual labour including loading, unloading and stacking for lead less than 0.50 Km. (Cost for Ist 50 Mtr.) For Sand : |
| 7 | Carriage of materials by maual labour including loading, unloading and stacking for lead less than 0.50 Km. (Cost for Ist 50 Mtr.) For Stone aggregate below 40mm nominal size : |
| 8 | Carriage of materials by maual labour including loading, unloading and stacking for lead less than 0.50 Km. (Cost for Ist 50 Mtr.) For Cement : |
| 9 | Carriage of materials by maual labour including loading, unloading and stacking for lead less than 0.50 Km. (Cost for Ist 50 Mtr.) For Steel : |
| 10 | Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete.Cold twisted bars |
| 11 | Centring and shuttering including strutting, propping etc. and removal of form for : walls (any thickness) including attached plisters, buttresses, plinth and string courses etc. |
| 12 | Providing and laying in position specified grade of reinforced cement concrete excluding the cost of centring, shuttering, finishing and reinforecement & all Maerial Cost- all work upto plinth level :1:2:4 (1 Cement : 2 Coarse sand : 4 Graded stone aggregate 20 mm nominal size) |
| 13 | 12 mm thick cement plaster (1:6, 1 Cement: 6 coarse sand) on brick work up to 5 mtr. And above in UG including curing etc. complete. (excluding cost of materials) |
| 14 | 6 mm thick cement plaster (1:4, 1 Cement: 4 coarse sand) on RCC/PCC work up to 5 Mtr. and above in UG including curing etc. complete. (excluding cost of materials) |
| 15 | White washing in UG with lime to give an even shade on Old work/new work. (One coat). (excluding cost of materials) |
| 16 | Material rate for : Coarse Sand : |
| 17 | Material rate for : Metal/ Graded Stone aggregate 20mm nominal size : |
| 18 | Material rate for : Cement : |
| 19 | Material rate for : Twisted Steel bar/ Steel (10mm) : |
| 20 | Material rate for : Lime : |
| 21 | Total impact of GST for the purpose of CTC Please Enable Macros to View BoQ information |