| 1 | Excavation for foundation in earth, soils of all types, sand, gravel, soft murum including shoring and strutting, dewatering as necessary and disposing off excavated stuff as directed etc. complete. ( By /manaual Means ) a) Upto 1.50m lift Normal Rate b) 1.50m to 3.00m lift, Add 10% c) 3.00m to 4.50m lift, Add 20% d) 4.50m to 6.0m lift, Add 30% |
| 2 | Providing dry/ trap/ granite/ quartzite/ gneiss rubble stone soling 15 cm to 20 cm thick including hand packing and compacting etc.complete. |
| 3 | Providing and laying Cast in situ/ Ready Mix cement concrete in M15 of trap /granite /quartzite /gneiss metal for foundation and bedding /steps including steel centering, formwork, laying/ pumping, compacting, roughening them if special finish is to be provided, finishing uneven and honey combed surface and curing etc. complete. The Cement Mortar1:3 plaster is considered for rendering uneven and honey combed surface, only. Newly laid concrete shall be covered by gunny bag, plastic ,tarpaulin etc. (Wooden centering will not be allowed.), with fully automatic microprocessor based PLC with SCADA enabled reversible Drum Type mixer/concrete Batch mix plant (Pan mixer) etc. complete. With fine aggregate (Crushed sand VSI Grade) |
| 4 | Providing and laying Cast in situ/ Ready Mix cement concrete M-40 of trap /granite /quartzite /gneiss metal for R.C.C. work in foundations like raft, strip foundations, grillage and footings of R.C.C. columns and steel stanchions etc. columns as per detailed designs and drawing or as directed including steel centering, formwork, cover blocks, laying/ pumping, compaction finishing the formed surfaces with cement mortar1:3 of sufficient minimum thickness to give a smooth and even surface or roughening if special finish is to be provided and curing etc. complete. (Excluding reinforcement and structural steel). with fully automatic microprocessor based PLC with SCADA enabled reversible Drum Type mixer /concrete Batch mix plant (Pan mixer) etc.complete. With fine aggregate (Crushed sand VSI Grade) |
| 5 | For Raft |
| 6 | For Wall/Slab |
| 7 | Providing, cutting, bending, hooking, tying and laying in position TMT FE 500 steel bars for reinforcement for all RCC works as per detailed drawings etc. complete. |
| 8 | Structural Steel -Providing and fabricating structural steel work in rolled sections like joists, channels, angles, tees etc. as per detailed design and drawings or as directed including cutting, fabricating, hoisting, erecting, fixing in position making riveted /bolted /welded connections without connecting plates, braces etc. and including one coat of anticorrosive paint and over it two coats of oil painting of approved quality and shade etc. complete. |
| 9 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing to proper grade and camber, applying and brooming requisite type of screening/binding Materials to fillup the interstices of coarse aggregate, watering and compacting with Vibratory roller. to the required density.By Mechanical Means-GradingI (Using Screening Type A (13.2) mm Aggregate) |
| 10 | Granular sub base (GSB) with Coarse graded material ( Table: 400-2) ( Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader /Paver on prepared surface and compacting with vibratory roller to achieve the desired density, complete as per clause401-- Plant Mix Method and Grading - I Material |
| 11 | Wet Mix Macadam--Providing ,laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub-base/ base course on well prepared surface and compacting with vibratory roller to achieve the desired density. Laying By Grader/Paver. |
| 12 | Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate ( natural sand/ VSI grade finely washed crushed sand) conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, , cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant/ Weigh batch mixer, transported to site with all leads and lifts, laid with a paver with electronic sensor /by suitable means as approved by Engineer-in-charge , compacting with vibratory roller, finishing, curing and including preparation of subgrade surface if required etc. complete. with fully automatic micro processor based PLC with SCADA enabled reversible Drum Type mixer/ concrete Batch mix plant (Pan mixer) etc. complete |
| 13 | Providing and laying Pavement Quality Concrete M-40 grade (cast in situ) of trap metal including providing 125 micron thick impermeable plastic sheet membrane over the surface to be covered,coarse and fine aggregates of specified gradation using minimum cement content of 350 kg/cum., approved admixtures, mixing as per the design mix to the specified workability,providing necessary side forms, rails and guidewires, transporting the mix with transit mixers and laying and spreading within fixed form by mechanical auger and compacting with plate vibrator and minimum ten needle vibrators,curing withapproved resin based aluminised reflective curing compound and covering with moist hessian or ponding and sprinkling of water for a minimum period of 14 days, Providing and fixing dowels, tiebars, cutting joints, joint-fillers, sealants and all types of joints and finishing to the desired surface texture including all material, labour,machinery with all leads and lifts etc complete. |
| 14 | Providing and Laying hot applied thermoplastic road marking strip on Bituminous Surface of specified shade/ colour of 2.5 mm thick including 1.5 Refractive index reflectorizing glass beads @ 250gm/sqm .Thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC 35:2015. Initial Dry reflectivity RL shall be > 250 mcd/sqm/lux measured in the initial 7 days and sustained reflectivity RL of 100 mcd/sqm/ lux and Qd of 100 mcd/sqm/ lux measured at the end of 2 years by means of a Standard Reflectometer of Zehntner, Easylux, Delta make capable of measuring RL & QD both according to IRC 35:2015 clause 15.5. The finished surface to be level, uniform, and free from streaks and holes complete as per direction of Engineer-in-charge and in accordance with applicable specifications.(Refer MORTH Clause 803 for technical Specification and Performance for IRC 35:2015). |
| 15 | Providing & applying two coats flat oil paint :- of approved colour, shade |