| 1 | Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. As per DSR 2023 SI No. 15.7.3 (Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) |
| 2 | Construction of embankment with approved material obtained from borrow pits with 1 km. lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of 95% of proctor density as per S.I. No 305(3.16) (Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) |
| 3 | Construction of granular sub-base by providing close graded material , spreading in uniform layers with motor grader on prepared surface , mixing by mix in place method with rotavator at OMC , and compacting with vibratory rollar to achieve the desired density , complete as per clause 401 (Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) |
| 4 | Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with Approved Material. Specification N. 304 (S.N. 12.01i) (Ordinary Soil) (Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) |
| 5 | Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. SI. No. - 12.04 (Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) |
| 6 | Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. (RCC M-30) SI.No.12.08 (Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) |
| 7 | Supplying, fitting and placing HYSD bar reinforcement in foundation comlete as per drawing and technical specifications (Foundations) SI.No.12.42 (1600) (Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) |
| 8 | Providing weep holes in Brick masonry/Plain/ Reinforced concrete abutment, wing wall/ return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H towards drawing foce. Complete as per drawing and Technical specification. SI. No. 13.08 |
| 9 | Providing and laying Cement concrete wearing coat M-35 grade including reinforecement complete as per drawing and Technical Specifications SI. No-14.4 (Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) |
| 10 | Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. (WMM) (Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) |
| 11 | Providing and laying prime coat with bitumin emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 Kg/ Sqm. using mechanical means as per Technical specification clause 502(1). (Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) |
| 12 | Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects.(Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) |
| 13 | Providing and laying tack coat with bitumen VG-10 using emulsion distributer at the rate of 0.20 Kg / Sqm. on the prepared granular surface treated with primer and cleaned with hydraulic broom as per technical specification clause no. 503 (I) (Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) |
| 14 | Providing and laying bituminous concrete with 100-120 TPH batch type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 509 complete in all respects(Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) |
| 15 | Providing & laying pitching on sloples laid over prepared filter media including boulder apron laid dry in front of toe of embankment complete as per drawings and Technical specification MORT&H Specification 2504 sr. No.16.04 (Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) |
| 16 | Stone Boulders pitching in slopes including cost of Labour T&P etc, required proper completion of the work. SOR 15.1 (Including Cost of All Matarial T&P, Taxes, Labour Cess etc but Excluding GST ) Please Enable Macros to View BoQ information |