| 1 | Safe Loading carriage including unloading & proper stacking of following store S/S materials from ESC Balrampur/JE store to site of work. (40 Km Approx ) |
| 2 | 33 KV Pin insulators Polymeric |
| 3 | 33 KV line Isolator(Set) |
| 4 | 33 KV Bus Isolator(Set) |
| 5 | 33 KV post insulators |
| 6 | 33 KV VCB 800A, 750 MVA with Single T/F Control Panel, C.T. 200/100/1-A with CT Structure |
| 7 | 33 KV PT, 33 KV/110V-1 Phase |
| 8 | 33 KV Lightning Arrestors |
| 9 | 33/11 KV 5 MVA Transformer (New/old & Used) |
| 10 | 11 KV Pin Insulator polymeric |
| 11 | 11 KV VCB (Incoming) 600/300/5A 350 MVA |
| 12 | 11 KV VCB (Out going) 200/100/5A 350 MVA |
| 13 | 3×300 mm2 XLPE |
| 14 | 3×185 mm2 XLPE |
| 15 | Bus Cuppler 350 MVA |
| 16 | S.T. Pole 13Mtr Long |
| 17 | S.T. Pole 11Mtr Long |
| 18 | A.C.S.R. Rabbit Conductor (H.T. Line) |
| 19 | 11 KV Polymer Pin Insulator with Nut |
| 20 | PCC 11 Mtr Long |
| 21 | Stay Complete with Stay Wire & Insulator |
| 22 | 11 KV Disc Polymer Insulator set with fitting |
| 23 | Earthing Complete |
| 24 | 3X185 Sqmm 11 kv Xlpe Cable |
| 25 | LT XLPE 1X240 Sq Mm Cable for DP Exposer |
| 26 | \"V\" Type Cross Arm. |
| 27 | Sub-Station Base |
| 28 | 63 kva Transformer 11/0.4 kv |
| 29 | 11 KV Ring Main Unit Complete with Earthing |
| 30 | ERECTION & INSTALLATION OF 33/11KV, 5MVA TRANSFORMERS Erection and installation of 33/11KV,5MVA transformer in a leveled position on the plinth. The work include shifting of transformer to the site of installation within the substation premises, assembling fixing and fitting of all accessories and filling of transformer oil to the desired level and insuring that there is no leakage. All the jump ring & connection are included in the scope of work. |
| 31 | PLINTH OF 5 MVA.33/11 KV T/F:- Construction of plinth of size 3.46x3.46 Mtr. For 5 MVA T/F HAVING 0.4 Mtr. above ground level. The work including excavation of foundation .base concreting in CC 1:6:12 ratio (cement ,fine sand & brick ballast)first class brick work in cement, morter of ratio 1:4 foundation CC in 1:4:8 ratio (cement ,fine sand & brick ballast) and RCC working ratio 1:2:4 (cement ,coarse sand and store grit of 20mm gauge using MS Bars of 10mm dia( tor ) in reinforcement including its cutting ,bending &binding in required shape .The work also includes laying of 2 Nos. 3.46 Mts.Long each rail piece complete with cutting welding & proper fitting etc. The plinth will be made as per drawing and shall be plastered/ finished on top and sides of the plinth in C.C. 1:3 ratio (cement, coarce sand) (Provided by Department 90 Lbs. Rail pieces for T/F Wt. 44.6 Kg/Mtr. @ Rs. 22.10 Per Kg.- 14 mtr) |
| 32 | Stringing and Sagging of 3 phase 11KV line on ACSR Rabbit conductor as per RESSPO Norms. |
| 33 | Special Earthing of Neutral & Body for 5 MVA T/F / P.T. of Incoming S/G / 33 KV C.T. 200/100/1-1A & Lightening Arrestor by way of boring and lowering of \"B\" class GI pipe 50mm dia from ground upto the water level (minimum 40 meter deep) as per standard practice. |
| 34 | PLINTH FOR VCB:- Construction of plinth of size 2.0 mtr x 1.5 mtr x 0.9 mtr suitable for erection of upper structure for 33KV VCB including grouting of anchor bolts in proper alignment and level. Scope of work includes excavation of foundation base concreting in CC 1:6:12(cement, fine sand & brick ballast), 1st class brick work in cement mortar of ratio 1:4 CC in ratio 1:4:8 and RCC work in ratio 1:2:4(cement coarse sand and stone grit of 20mm gauge) as per drawing. |
| 35 | Laying of 11 KV cable including cost of sand & bricks. |
| 36 | Making ofd 11 KV Cable Box and mounting of switch Gear and Transformer |
| 37 | Painting of sub-station structure & Equipment |
| 38 | Making of cable trench for UG cable complete |
| 39 | Interlocking of switch yard with cementel bricks |
| 40 | Construction of SSO\"s Approatched Road 1.2 Mtr. Wide in switch yard. |
| 41 | Construction of 11/0.4 KV S/S for 63 KVA T/F with mounting and fitting of T/F on plinth/double pole with proper fitting of all acessories and connecting with all circuit. |
| 42 | Installation of 33 KV VCBInstallation of 33 KV 750 MVA 800 Amp VCB on 33 KV VCB structure along with earthing by G.I. strip 50x6 mm size with main earthmat of Switchyards complete in all respect including commissioning. |
| 43 | INSTALLATION OF ISOLATORS:-Assembling and installation of Line Isolator(Set) on the isolator structure adjusting of opening mechanism in proper alignment so as to ensure smooth operation of the same in case of line isolator proper operation of earth links shall also be insured. The work includes fabrication for proper flexing if required. |
| 44 | INSTALLATION OF ISOLATORS:-Assembling and installation of Bus isolator(Set) on the isolator structure adjusting of opening mechanism in proper alignment so as to ensure smooth operation of the same in case of line isolator proper operation of earth links shall also be insured. The work includes fabrication for proper flexing if required. |
| 45 | INSTALLATION OF Post Insulator:- Installation of Post Insulators on the post insulators structure. The work includes fabrication for proper fixing if required |
| 46 | INSTALLATION OF PT:- Installation of 33 KV PT, 33 KV/110V-1 Phase on the Structures. As per RESSPO norms. |
| 47 | INSTALLATION OF LIGHTENING ARRESTORS:- Assembling and installation Mounting of 3Nos (1 set) lightening arrestors on the L.A. Structure complete with making earth connections (separate) and line connections the work includes fabrication for proper fixing if required. |
| 48 | INSTALLATION OF SWITCHGEARS IN CONTROL ROOM:-Shifting carefully & safely 11KV I/C & O/G switchgear from outside of the switchgear room, including grouting the two No.100x50x6mm channels pieces (each 800mm long including cutting to size) and foundation bolts in 1;2:4 CC (including cutting of CC of the floor and finishing of floor)as per direction of Engineer in charge, placing and fixing of switchgear on foundation providing G.I. Nuts & Bolts of proper size in proper position and alignment and checking, complete work with Mounting of P.T on incoming S/G. (11 KV VCB I/C=1 & O/C=2) |
| 49 | H.T.CABLE LAYING:- Laying & dressing of 11KV,3X300sq.mm under ground cable from 5MVA T/F to 11KV incoming switchgear in the trench 450 mm wide,900mm deep providing 150mm fine sand, cushion bench and 150mm fine sand cushion above the cable. The cable shall be duly protected by bricks, sand & stone slab .The work includes supplying of fine sand , bricks and stone slab and refilling & ramming of the left out soil ,closing the trench and leveling. Spare cable shall be left and burried in the trench in the shape of rings at both ends cable laying work includes unrolling cutting make ring and sealing both ends of the cable. |
| 50 | Laying & dressing of 11KV,3X185 sqmm. under ground cable in the trench 450 mm wide,900mm deep providing 150mm fine sand, cushion bench and 150mm fine sand cushion above the cable. The cable shall be duly protected by Ist class bricks/stone slab. The work includes supplying of fine sand & bricks & stone slab & refilling and ramming of the left out soil and leveling. Spare cable shall be left and burried in the trench in the shape of rings at both ends. |
| 51 | Errection of Sectional Double Pole support /Exposure Double Pole:-The excavation of foundation pit of size (750x450) mm and having depth of 1/6 of the full length of the support. Errection of support, complete with providing & Fixing of all clamps and other accesories as per dwawing. The work includes carriage and handling of supports from sectional store to pit site, fixing of Top Channel, Droper channel & MS T-off channel and cross bracing sets as well as any fabrication work if required. (3 Nos. 33 KV G.I Pin with nuts, Top channel clamps, Bracing angle Clamp, E-Bracket, Disc fitting, bolt and nuts, stone pad as per norms etc shall be provided by Contractor.) |
| 52 | P.C.C. Pole 11 Mtr. |
| 53 | S.T. Pole 11 Mtr Long |
| 54 | S.T. Pole 13 Mtr Long |
| 55 | Errection of Single ST Pole 11 Mtr. Long :-The excavation of foundation pit of size (750x450) mm and having depth of 1/6 of the full length of the support. Errection of support, complete with providing & Fixing of all clamps and other accessories as per drawing. The work includes carriage and handling support from sectional store to pit site as well as any fabrication work if required. (3 Nos. 33 KV G.I Pin, necessary clamps, F-Bracket, stone pad shall be provided by Contractor.) |
| 56 | Installation & Errection of 33 KV Electronic TVM. as per RESSPO norms. |
| 57 | Grouting of supports in PCC 1:4:8 (cement, sand, & 20 mm size stone Grit). Grouting will be done in the block of size (450x450)mm x 1/6th of full length of support, upto ground level, 300mm plinth above the ground level with C.C 1:3:6 (Cement, Coarse sand and Stone grit of 20mm of size with muffing as per drawing). |
| 58 | P.C.C. Pole 11 Mtr. |
| 59 | S.T. Pole 11 Mtr Long |
| 60 | S.T. Pole 13 Mtr Long |
| 61 | Muffing of ST Pole (13 Mtr. & 11 Mtr.) |
| 62 | Fixing of Stay set complete (size 20x1800 mm) on different types of supports as per RESSPO norms. |
| 63 | Fabrication of 11 KV Ring Main Unit Complete with Earthing. |
| 64 | Erection of 11 kv Pilfer Proof Metering Cubical CTR 100/5 Amp. |
| 65 | Erection of 11 KV Double Metering Combind Unit CT/PT CTR 100/5 Amp. |
| 66 | Railway Crossing UG XLPE cable.(02 set) |
| 67 | Laying of 11 KV 3x185 sq.mm. with HDPE Pipe through Machine. |
| 68 | Looping & Hosting of XLPE cable |
| 69 | Fitting of LT XLPE 1X240 Sq Mm Cable for DP Exposer |
| 70 | Earthing Complete for CT PT & Pilfer Unit Earthing Complete (Pipe Bore 40 feet) |
| 71 | Proviiding & Fixing of below itme\"s and rest all the material including civil material will be arranged by the contractor itself. Any other material if required for completion of work which might not have been mentioned in bid document, shall be arranged by the contractor. As per RESSPO UPPCL norms. |
| 72 | Terminal Gantry |
| 73 | Main Bus Bar complete with structure new/ Old & Reused |
| 74 | ACSR Panther Conductor |
| 75 | PG Clamp Panther to Panther Conductor |
| 76 | Structure for Line Isolator & Bus Isolator |
| 77 | Structure for Post Insulator |
| 78 | Structures for PT & 33 KV VCB |
| 79 | 33 KV Fuse Set |
| 80 | Structure for 33 KV Fuse Set |
| 81 | Structure for Lightning Arrestor |
| 82 | 90 Lbs. Rail pieces for T/F Wt. 44.6 Kg/Mtr. @ Rs. 22.10 Per Kg. |
| 83 | M.S. Angle (50×50×6)mm |
| 84 | M.S. Channel (100×50)mm |
| 85 | M.S channel proper size for different-2 structure |
| 86 | M.S. Angle (65×65×6)mm |
| 87 | 3×300 mm outdoor kit |
| 88 | 3×300mm indoor Epoxy Type |
| 89 | 3×185 mm2 outdoor Epoxy Type |
| 90 | 3×185 mm2 indoor Epoxy Type |
| 91 | 24 Volt Battery & Battery Charger with cabinet for panel |
| 92 | 2×2.5 mm2 control cable |
| 93 | 4×2.5 mm2 control cable |
| 94 | Earth Mat for outdoor equipment with complete fitting, GI strip with painting. |
| 95 | Earth Mat for indoor equipment with complete fitting, GI strip with painting. |
| 96 | L Type Structure for above M.S. Channel 100×50mm |
| 97 | L.T.P.V.C. Cable 3½×70 mm2 |
| 98 | Lighting of outdoor switchyard |
| 99 | 10\" inch exhaust Fan Complete in every respect |
| 100 | Cost of Misc. Items i.e. Rubber Matting Single Line Diagram Board, Tripping Chart Board, S/S Board |
| 101 | Fire Fighting equipments including 02 Nos. 4.5 Kg. Co2 Fire Extinguisher potable type and 02 Nos. Foam type Fire Extinguisher potable type |
| 102 | Top Channel Holding Clamp |
| 103 | Dropper Channel Holding Clamp |
| 104 | Danger Plate with fitting |
| 105 | Clamp for \"V\" Type Cross Arm. |
| 106 | Clamp for Sub Station Base. |
| 107 | D.O. Fuse Set for 11 kv |
| 108 | Clamp for T-OFF Channel for DP Xposer |
| 109 | \"F\" Bracket with Nut Bolt |
| 110 | GI Pipe 6\" Mtr Dia (3.5MTR.) |
| 111 | Nut & Bolt |
| 112 | Alluminium paint |
| 113 | Red oxide paint |
| 114 | Clamp For XLPE Cable |
| 115 | Proper Size Of Lugs For DP xposer & UG XLPe Cable |
| 116 | 120 Mm HDPE Pipe |
| 117 | UG Cable Route Marker of Concrete (1 feet under ground &1.5 feet upper side of ground |
| 118 | Clamp For GI Pipe |
| 119 | O/D Cable Jointing Kit For 3X185 XLPE Cable |
| 120 | I/D Cable Jointing Kit For 3X185 XLPE Cable |
| 121 | Dropper Channel |
| 122 | T-OFF Channel for DP Xposer |
| 123 | Top Channel |
| 124 | Straight Through for 11kv 3x185 sqmm xlpe cable |
| 125 | PG Clamp for Rabbit Conductor |
| 126 | Hot Dip Galvanised Earting Pipe Electrode of Size Dia 1.5 Dia |
| 127 | Earting Strip Please Enable Macros to View BoQ information |