| 1 | 11 KV LINEWork Supply & Fixing Supply & Fixing of PCC Pole 8.5 Mtr Long. |
| 2 | Supply & Fixing of STP Pole 11 Mtr Long. |
| 3 | Supply & Fixing of Stone Ped (300x300x75 mm) |
| 4 | Supply & Fixing of ACSR Weasel cond |
| 5 | Supply & Fixing of 11 kv V-X Arm |
| 6 | Supply & Fixing of F Clamp pcc/stp |
| 7 | Supply & Fixing of Holding Clamp with N& B |
| 8 | Supply & Fixing of T- Channel |
| 9 | Supply & Fixing of P.G Clamp |
| 10 | Supply & Fixing of Clamp & nut Bolt |
| 11 | Supply & Fixing of 11 KV Disk insulator with Fitting |
| 12 | Supply & Fixing of 11 Kv pin insulator with pin |
| 13 | Supply & Fixing of Number Plate with clamp & nut bolt |
| 14 | Supply & Fixing of Danger Plate with clamp & nut bolt |
| 15 | Supply & Fixing of Red Oxid Paint |
| 16 | Supply & Fixing of Aluminium Paint |
| 17 | Supply & Fixing of Barbered Wire |
| 18 | Supply & Fixing of Stay Set Complete. |
| 19 | Supply & Fixing of Earthing Set Complete. |
| 20 | Supply & Fixing of N& B |
| 21 | Supply & Fixing of Concreting of Stay |
| 22 | Supply & Fixing of Concreting of Pole |
| 23 | Supply & Fixing of G.I WIRE |
| 24 | Supply & Fixing of Gurding Angle |
| 25 | Supply & Fixing of Double pole on PCC 8.5 MTR POLE COST |
| 26 | Supply & Fixing of Double pole on STP 11 MTR POLE COST |
| 27 | LT LINE Work Supply & Fixing Supply & Fixing of PCC Pole 8.5 Mtr Long. |
| 28 | Supply & Fixing of LT ABC 3.5X120 SQ MM |
| 29 | Supply & Fixing of E HOOK |
| 30 | Supply & Fixing of Ded End clamp |
| 31 | Supply & Fixing of PRC Connector |
| 32 | Supply & Fixing of Concreting of Pole |
| 33 | Supply & Fixing of Earthing Set Complete. |
| 34 | Supply & Fixing of Suspension clamp |
| 35 | Supply & Fixing of L.T Distribution box |
| 36 | Supply & Fixing of L.T Clamp With N&B Note - GST Extra paid as per Rules.2- All rate are included 1% Labour cess that shall be deduct at the time of payment Please Enable Macros to View BoQ information |