| 1 | Name of the work : 1. Strengthening the Road From Sekkapatti Kannimar Kovil Road KM 0/0-1/00 (R111) (plastic Waste)Est Rs :29,96,000/- |
| 2 | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp. |
| 3 | Earth work excavation from borrow pits for filling in all classes of soils, such as gravelly soil hard red earth shales, murrams gravel stoney earth and earth mixed with 50% lair sized boulders and hard gravel soil exept sand and hard rock requiring blasting as per SS 20A |
| 4 | Picking the existing old metal for the B.T. surface and sectioning the undulations and all compacting charges etc., complete |
| 5 | Providing and Laying Gravel to a compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction |
| 6 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 100mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 7 | Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. |
| 8 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., |
| 9 | Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 |
| 10 | Providing and fixing of HM stones for standard specification |
| 11 | Providing and fixing of 60 cm Equilateral triangle cautionarysignboard standard specification |
| 12 | Providing and fixing of Name board Information board for standard specification |
| 13 | Provision for Causeway |
| 14 | Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel bars, near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days,using curing compound (where specified ) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501 |
| 15 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column \"BB\" for all works in this package} |
| 16 | Name of the work : 2. Strengthening the Road From Kattakammanpatti Edamailyan Kovil road Road KM 0/0-0/8 H/O Kattakammanpatti (R32) Est Rs :44,44,000/- |
| 17 | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp. |
| 18 | Earth work excavation from borrow pits for filling in all classes of soils, such as gravelly soil hard red earth shales, murrams gravel stoney earth and earth mixed with 50% lair sized boulders and hard gravel soil exept sand and hard rock requiring blasting as per SS 20A |
| 19 | Picking the existing old metal for the B.T. surface and sectioning the undulations and all compacting charges etc., complete |
| 20 | Providing and Laying Gravel to a compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction |
| 21 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 100mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 22 | Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. |
| 23 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., |
| 24 | Providing, laying 50mm consolidated thick Bituminous Macadam using 0.20cum of 26.50- 13.20mm, 0.43cum of 13.20-2.36mm and 0.08cum of 2.36mm & below size IRC metal with 34.04 Kgs of VG30 Grade bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen, aggregate and mixing them in required temperature using Central hot mix plant 20-30ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory Roller to the required density etc., including labour for attending to paver to site etc., including hire and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including all other incidental charges etc., complete as per specification using CMP as per clause 504 of MORTH Rev-5 |
| 25 | Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete asper specification using CMP as per clause 507 of MORTH Rev-5 |
| 26 | Providing and fixing of HM stones for standard specification |
| 27 | Providing and fixing of 60 cm Equilateral triangle cautionarysignboard standard specification |
| 28 | Providing and fixing of Name board Information board for standard specification |
| 29 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column \"BB\" for all works in this package} |
| 30 | Name of the work : 3. Strengthening the Road From Kottaikarupusamy Kovil road Road KM 0/0-0/6 H/O P.Viralipatti(R54) Est Rs :26,71,000/- |
| 31 | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp. |
| 32 | Earth work excavation from borrow pits for filling in all classes of soils, such as gravelly soil hard red earth shales, murrams gravel stoney earth and earth mixed with 50% lair sized boulders and hard gravel soil exept sand and hard rock requiring blasting as per SS 20A |
| 33 | Picking the existing old metal for the B.T. surface and sectioning the undulations and all compacting charges etc., complete |
| 34 | Providing and Laying Gravel to a compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction |
| 35 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 100mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 36 | Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. |
| 37 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., |
| 38 | Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete asper specification using CMP as per clause 507 of MORTH Rev-5 |
| 39 | Providing and fixing of HM stones for standard specification |
| 40 | Providing and fixing of 60 cm Equilateral triangle cautionarysignboard standard specification |
| 41 | Providing and fixing of Name board Information board for standard specification |
| 42 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column \"BB\" for all works in this package} |
| 43 | Name of the work : 4. Strengthening the Road From G.Thummalapatti Burial Ground road Road KM 0/0-0/8 H/O G.Thummalapatti (R131) Est Rs :27,19,000/-(plastic waste) |
| 44 | Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp. |
| 45 | Earth work excavation from borrow pits for filling in all classes of soils, such as gravelly soil hard red earth shales, murrams gravel stoney earth and earth mixed with 50% lair sized boulders and hard gravel soil exept sand and hard rock requiring blasting as per SS 20A |
| 46 | Providing and Laying Gravel to a compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction |
| 47 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 100mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. |
| 48 | Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. |
| 49 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., |
| 50 | Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 |
| 51 | Providing and fixing of HM stones for standard specification |
| 52 | Providing and fixing of 60 cm Equilateral triangle cautionarysignboard standard specification |
| 53 | Providing and fixing of Name board Information board for standard specification |
| 54 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column \"BB\" for all works in this package} Please Enable Macros to View BoQ information |